HomeMy WebLinkAboutReso 1976-8444RESOLUTION NO. 8444
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA APPROVING AGREEMENT BETWEEN THE CITY
OF CHULA VISTA AND ALFRED E. O'DAY AS PROJECT
°' REPRESENTATIVE FOR THE CIVIC CENTER RENOVATION
PROJECT, AND AUTHORIZING THE MAYOR TO EXECUTE
SAID AGREEMENT
The City Council of the City of Chula Vista does hereby
resolve as follows:
WHEREAS, the attached agreement is an agreement for personal
services which are of a unique nature and not reasonably reducible to
specifications which can be submitted for public bid.
NOW, THEREFORE, BE IT RESOLVED that this agreement need not
be submitted to public bidding.
BE IT FURTHER RESOLVED that that certain agreement between
THE CITY OF CHULA VISTA, a municipal corporation, and ALFRED E. O'DAY
as Project Representative for the Civic Center Renovation Project,
dated the 8th day of December, 1976, a copy of which is attached
hereto and incorporated herein, the same as though fully set forth
herein be, and the same is hereby approved.
BE IT FURTHER RESOLVED that the Mayor of the City of Chula
Vista be, and he is hereby authorized and directed to execute said
agreement for and on behalf of the City of Chula Vista.
Presented by Approved as to form by
,/ / ~.~
e' rady, Direc or of George Lindberg, City Atto y
Building and Ho i -
ADOPTED AND APPROVED by the CITY COUNCIL of the CITY OF
CHULA VISTA, CALIFORNIA, this 14th day of December , 197 6 ,
by the following vote, to-wit:
AYES : Councilmen Egdahl, Hobel, Hyde, Cox, Hamilton
NAYES: Councilmen None
ATTEST
STATE~SF CALIFORNIA)
COUNTY OF SAN DIEGO)
CITY OF CHULA VISTA)
ss.
I, , City Clerk of the
City of Chula Vista, California, DO HEREBY CERTIFY that the above is
a full, true and correct copy of Resolution rdo. , and that the
same has not been amended or repealed. DATED .
City Clerk
ABSENT: Councilmen None
AGREEMENT FOR PROJECT REPRESENTATIVE FOR
THE CHULA VISTA CIVIC CENTER BUILDINGS
THIS AGREEMENT, made and entered into in the City
of Chula Vista, California, this 8 th day of December 1976,
by and between the CITY OF CHULA VISTA, a municipal corporation,
hereinafter referred to as "CITY", and ALFRED E. O'DAY, 1036 Hayes
Street, San Diego, California 92103, hereinafter referred to as
"PROJECT REPRESENTATIVE";
W I T N E S S E T H
WHEREAS, the City, during the renovation of the
Chula Vista Civic Center Buildings, requires the services of an
inspector and qualified professional to perform various services
during said construction; and
WHEREAS, ALFRED E. O'DAY, is an individual who holds
the necessary training and expertise to perform the services listed
below.
NOW, THEREFORE, in consideration of the mutual promises
and upon the terms and conditions contained herein, the City and
Alfred E. O'Day, the Project Representative, agree as follows:
1. The Project Representative agrees to provide the
following professional services as an independent contractor employed
by the City:
Construction Inspection:
1.1 To serve when appointed as an independent building
inspector as directed by the Director of Building and
Housing, or his authorized representative.
1.2 To inspect for the purposes of determining that
all construction activities comply with the following
regulations:
Uniform Building Code 1976 Edition;
Uniform Mechanical Code 1976 Edition;
Uniform Plumbing Code 1976 Edition;
National Electrical Code 1975 Edition;
Title 19, California Administrative Code;
Title 24, California Administrative Code;
Chula Vista City Code.
_ 1.3 To compare the contract plans and specifications for
the purpose of advising the City of any contractor's or
subcontractor's conformance with said plans and specifi-
cations in any building activity.
1.4 To act as a special inspector for the purpose of
inspecting high strength concrete masonry and structural
welding, and to provide such services in accordance with
standard construction practice.
-1-
1.5 To determine that all testing of soil,
concrete and other specified tests are, in fact,
completed in accordance with the applicable
contract plans and specifications or State or
local ordinances.
1.6 To perform concrete cylinder samples and
to perform concrete slump tests and report the
results of such tests.
1.7 To review all shop drawings.
Coordination Activities:
1.8 The Project Representative shall aCt as a
coordinator between the various subcontractors
for the purpose of maintaining the projected job
completion schedule.
1.9 He shall act as a liaison on behalf of the
City between the architect and general contractor.
Material Inspection:
1.10 The Project Representative shall further
inspect materials delivered to the job site to
insure they are of the type and quantity specified
in the contract plans and specifications.
1.11 He shall inspect each delivery ticket of
structural concrete to insure the amount of
concrete utilized is in accordance with the plans
and specifications.
Professional Recommendations:
1.12 The Project Representative shall, in accordance
with his professional training and experience, advise
the City of the following:
1.12.1 Any changes in construction which may
be made to insure a sounder structure and/or
monetary savings.
1.12.2 The reasonableness and approval of any
suggested change orders.
1.12.3 Advise the City and maintain records
of any delays caused by fire, flood, epidemic,
strikes or acts of God.
1.12.4 The percentage of work completed by
the contractor in order to determine whether
the City should make a progress payment.
-2-
2. The Project Representative hereby covenants that
he has the experience to perform the work enumerated above. He further
covenants that his activities shall be as an independent contractor and
that, as such a contractor, he is bound by the terms and conditions set
forth in this agreement and shall not be entitled to any of the benefits
and/or remunerations available to any employee of the City of Chula Vista,
including but not limited to: workmen's compensation, group health
insurance or overtime.
3. The Project Representative further covenants that
he shall provide his own transportation wherever necessary for performance
of his duties under this agreement.
4. The parties to this agreement hereby agree that the
Project Representative shall be paid monthly for his activities on the
first (1st) day of each month, or the next working day thereafter. Parties
further agree that the Project Representative shall be paid for his duties
under this agreement at the rate of ONE THOUSAND SIX HUNDRED DOLLARS AND
NO/100s ($1,600.00) per month. The contract payments shall be prorated
for any portion of a month during which the Project Representative performs
services.
5. The contract period will be for SIX (6) months, provided,
however, that the City of Chula Vista, at its sole option, may terminate said
agreement following no less than Thirty (30) days written notice of the City's
intent to terminate said agreement. Upon the expiration of the six (6) month
period, commencing with the 1st day of April 1977, unless this
agreement is terminated earlier, the agreement may be extended at the sole
option of the City on a month to month basis, in accordance with the terms
and conditions set forth herein.
IN WITNESS WHEREOF, the parties hereto have caused this
agreement to be executed the day and year first hereinabove set forth.
THE CITY OF CHULA VISTA
Mayor of the it of Chula Vist
ATTEST
~~ ~ ~ ~./ f
D¢puty City Clerk
Approved as f m by ~ /
City Attorney
PROJECT REPRESENTATIVE
~~ ~~~ i
Alfred O'Day /J"J
G
-3-