HomeMy WebLinkAboutAgenda Statement 1977/06/07 Item 15
CITY OF CHULA VISTA ITEM ~JO. 15
•:
COUNCIL AGENDA STATEMENT
FOR MEETING OF: ti-7-77
ITEM TITLE: Resolution 8644 Granting an Extension of Time for the Contract
to Construct Traffic Signal Improvements in Chula Vista - ~'AU
Project No. M-S163(1)
SUBMITTED BY~ Director of Public Works/City Engineer ),,~
ITEM EXPLANATION
On January 4, 1977, the City Council adopted Resolution No. 8467 awarding the
contract for construction of traffic signal improvements at Fifth Avenue/
J Street, Fifth Avenue/K Street, Industrial Boulevard/L Street, Third
Avenue/L Street, Fourth Avenue/K Street, Hilltop Drive/I Street, Third
Avenue/E Street and Third Avenue/F Street to Perry Electric. The construc-
tion was to be completed within 120 calendar days following commencement of
work on February 1, 1977. This schedule required the contractor to complete
construction by June 1, 1977.
Perry Electric has requested a time extension due to delay in receipt of the
controllers for Third Avenue/L Street and Industrial Boulevard/L Street.
This delay is primarily due to the length of time necessary to receive the
controller from the manufacturer and the FAU requirement that the controllers
be tested by the State of California prior to field installation. Caltrans
and FHWA have agreed to a time extension of 10 working days after the con-
trollers are released from the testing lab. We anticipate the controllers
to be released from the testing lab this week.
The attached resolution will extend the contract to a date 10 days beyond the
date that Caltrans releases the traffic signal controller to the contractor.
I~\/1 111"~ITf'\ ATTA/'\1 Ir P\
CJ~I"II[31 I J H I I Hl~l"ICU
Agreement Resolution X Ordinance Plat Other
Environmental Document: Attached Submitted on
STAFF RECOMMENDATION: Approve resolution
BOARD/ COMMISSION RECOMMENDATION
A P P R O V E D
by t'~ e
Ci i;y CouYicil
COUNCIL ACTION Of
,.:lula tiiyta, California
aated...~~'~ ...T..7......~....-..
~~