HomeMy WebLinkAboutAgenda Statement 1979/02/27 Item 09CITY OF CHULA VISTA
COUNCIL AGENDA STATEMENT Item No. 9
For meeting of 2/27/79
ITEM TITLE Resolution ~J~/~ Accepting Bids and Awarding Contract for
Construction of a Storm Drain System in Madrona Street and
Del Mar Avenue and Improvement of the Alley South of Madrona
Street and West of Del Mar Avenue
SUBMITTED BY City Engineer via Director of Public Works
~~
ITEM EXPLANATION (4/5TH'S VOTE REQUIRED YES NO x )
At 11:00 a.m. on February 1, 1979, in the Engineering Conference Room,
the City Engineer received sealed bids for "The Construction of a Storm
Drain System in Madrona Street and Del Mar Avenue and Improvement of
the Alley South of Madrona Street and West of Del Mar Avenue."
The scope of the project includes: the installation of P.C.C. alley
paving, rolled curb, storm drain pipe, inlets, cleanout, drainage
outlet structure, clearing, grubbing and grading, A.C. and P.C.C.
removal, restoration of property, and other related items of work.
The project will eliminate water flowing through a partial collapsed
culvert under a private residence at the northwest corner cf Del Mar
and Madrona.
Bids were received from four contractors as follows:
Alternate I Alternate 2
1. G. R. Henderson Contractors, Inc. - S.D. $75,074.00 No Bid
2. T. B. Penick & Sons, Inc. - S.D. 84,516.00 $85,817.00
3. Walter H. Barber & Son - La Mesa 85,109.98 No Bid
4. Metro-Young Construction Co. - S.D. 113,855.00 108,295.00
The difference between Alternate 1 and Alternate 2 is in the type of
pipe used in the construction of the storm drain system. Alternate 1
uses Reinforced Concrete Pipe (RCP) and Alternate 2 uses Corrugated
Steel Pipe (CSP) with a fully lined interior. The bid proposal allowed
the City to choose the low bid from either alternative.
We recommend Alternate 1
storm drain system. The
SLH:nr/AO-005
Agreement Resolution x
using the Reinforced Concrete Pipe in the
low bid for this alternate was considerably
- EXHIBITS (continued on supplemental page)
Ordinance Plat x Notification List
Other ENVIRONMENTAL DOCUMENT: Attached Submitted on
FINANCIAL IMPACT
Cost of project is being financed with Block Grant funds. City will
assume maintenance of the improvements upon completion of the project.
STAFF RECOMMENDATION
See attached sheet.
BOARD/COMMISSION RECOMMENDATION
A P P R O V E D
by the
COUNCIL ACTION
~..._
:i d,i; e d
-~~-7 y _ ..._
Agenda Item No. 9
For meeting of 2/27/79
Supplemental Page Two
lower than the low bid for Alternate 2 (CSP).
The low bid submitted by G. R. Henderson Contractors, Inc. is above
the Engineer's estimate by $19,389. This low bid is above the
Engineer's estimate of $55,685 by 34.8%.
We have compared the bids with the consulting Engineer's estimate.
The price to install drainage improvements; i.e., trenching, concrete
pipe and outlet structure, is considerably higher than it was last
year (when the project was budgeted). Since we had four contractors
bid on the project, we don't believe we could get a better price
by readvertising and therefore recommend that the project be awarded.
The Federal Department of Housing and Urban Development has reviewed
and approved the low bidder's eligibility to participate in a federally
financed Block Grant Project.
A transparency is available for Council viewing.
FINANCIAL STATEMENT
Funds have been budgeted in the third year block grant program for this
project. However, the amount of funds budgeted are insufficient. It
will be necessary to transfer a portion of the funds budgeted in the
fourth year block grant program from the "Central Basin Drainage
Culvert, "G" to Parkway" project to provide sufficient funds. This type
of adjustment is allowable under Block Grant Regulations.
It should be noted that additional funds may need to be appropriated
for the Central Basin Drainage Culvert. The latest Engineering Dept.
rough estimate for that project indicates that $70,000 to $100,000 may
need to be additionally appropriated for that project assuming
$31,400 is transferred to the Madrona Alley project.
Unencumbered funds are available for this project as follows:
1. Storm Drain at Madrona, BG-39
2. Central Basin Drainage-Parkway & G, BG-47
Total Funds Available
Contract Amount
10~ Contingencies (approximate)
Total Estimated Construction Costs
including inspection
Utility Relocations
Project Cost
STAFF RECOMMENDATION
$ 52,088.65
235,923.94
$288,012.59
$ 75,074.00
7,516.00
$ 82,590.00
810.00
$ 83,400.00
1. City Council authorize the transfer of $31,400 in budgeted
account #632-6320-BG47, Central BAsin Drainage - Parkway &
"G", to Account #632-6320-BG39 Storm Drain @ Madrona.
2. City Council authorize the expenditure of $83,400 from the
following accounts:
a. $52,000 from Storm Drain @ Madrona, Project Account
#631-6310-BG39.
b. $31,400 from Storm Drain @ Madrona, Project Account
#632-6320-BG39.
3. City Council accept bids and award contract to G. R. Henderson
Contractors, Inc. for Alternate 1 (RCP) in the amount of
$75,074.00.
'~5~~
CHANGE ILJ CONTRACT
Construction of a Storm Drain
System in Madrona Street and Del
Mar Avenue and Improvement of
the Alley South of Madrona
Sf rP_ef and W _st of Del Mar Ave CONTRACT
G.R. Henderson Contractors,Inc.CONTR~,CTOR
JOB A0005
The following change shall be made to increase the
contract dated March 22, 1979 , between the City of Chula Vista and
G.R. Henderson Contractors, Inc. , Contractor.
REMARKS AND DETAILS:
At station 4+64 - east side from 5' Type B inlet.
To excavate, remove existing corroded steel pipe,
Prepare base,~~lay 1018" R.C.P. Backfill and Compact
$55.00/Lin. Ft.
Remove and replace 70 sq. ft. concrete sidewalk
at $2.00/f t.
Place 1 concrete lug
Restoration
~=~~`_
ORDER NO. One
DAmy July 20, 1979
Total Change Order
ORIGINAL CONTRACT PRICE
Previous Change Order Nos.
$550.00
140.00
150.00
150.00
$990.00
$ 75.074.00
$ -
Revised Total Contract Price $ 75,074.00
This Change Order No. 1 $ 990.00
It is agreed by the undersigned that all extra work shall be performed
and materials furnished in accordance with the original contract and in
accordance with the statement, if any, attached hereto.
TOTAL CONTRACT $ 76,064.00
APPROVED BY: ACCEPTED BY: ORDERED BY:
John P. Lippitt,
Cit n ine G.R. Henderson Contractors, I
~ Kenneth J oldkamp,
Sen' i
~ ~"`
~~h7
~/ ~ ,~ - _ ~(
QX- J li7e`! ~ ~ ~O ~°
V C /
/~
PW-E-44
S/
CHANGE IN CONTRACT
ORDER No. Two
nstruction of a Storm Drain System
Madrona Street and Del Mar Avenue Df,,mE
d Improvement of the Alley South
Madrona Street"and west of Del MarCONTRACT
enue
G. R. Henderson Contractors ,CONTRACTOR
JOB
August 13, 1979
AO-005
The following change shall be made to increase the
contract dated Marc , , between the City of Chula Vista and .
G R Henderson Contractors, Inc. , Contractor.
REMARKS AND DETAILS;
Remove existing Asphalt Concrete Pavement, beyond limits of contract
worlc, prepare subgrade, place Aggregate Base Material and place
Asphalt Concrete pavement and Seal Coat, for the purpose of
constructing smooth"transition between existing pavement and curb
inlet structures. All work to be in accordance with City specifi-
cations.
Approximately 210 square feet @ $3.30 per sq. ft. _ $693.00
ORIGINAL CONTRACT PRICE $ 75,074.00
Previous Change Order Nos. $ 990.00
Revised Total Contract Price $ 76,064.00
This Change Order No.Two $ 693.00
It is agreed by the undersigned that all extra work shall be performed
and materials furnished in accordance with the original contract and in
accordance with the statement, if any, attached hereto.
TOTAL CONTRACT $ 76,757.00
Shy
APPROVED BY: ACCEPTED BY: UxDEttr:ll t3Y
Jo n P. Lippitt n~R. Hen e,~`son ontracto s, KennetJ/~'o amp
City EncTineer YY ~~~1 fi /~~~tl~~eer
PW-E-44
~ ~