ITEM TITLE Resolution #8894: Granting a 30-Day Extension of Contract to
Install the Traffic Signal at Orange Avenue/
Hilltop Drive
SUBMITTED BY Director of Public Works/City Engineer VU ,j v
ITEM EXPLANATION (4/5TH'S VOTE REQUIRED YES- (N/0 Jam)
On August 9, 1977, the City Council approved Resolution No. 8773 awarding
the contract for construction of the traffic signal system at Orange
Avenue/Hilltop Drive to Perry Electric Company. The construction was to
be complete in 60 days following the commencement of work on October 1,
1977. This schedule required .the contractor to complete construction by
November 29, 1977.
Perry Electric has requested a 30-day time extension due to delay in de-
livery of traffic signal equipment. According to State of California
Specifications Sec. 8-1.07, the delay in delivery is a justifiable reason
to extend the contract and the delay is due to problems encountered in
obtaining manufacturing materials and has been verified with the manu-
facturer, Automatic Signal Division of the LFE Corporation.
BX013 GRH:ph
tXH1tSl l b
Agreement Resolution x Ordinance- Plat_ Notification List_
Other ENVIRONMENTAL DOCUMENT: Attached- Submitted on
FINANCIAL IMPACT
None
STAFF RECOMMENDATION
Approve Resolution
BOARD/COMMISSION RECOMMENDATION
COUNCIL ACTION
Ay~byp eED
~;;,.,_,;;iJ.
C=~~
03 _ _;ia
-,- -
/ ~Z ~ .............W
Chula ~ 1J ~
Dated.......... ................