COUNCIL AGENDA STATEMENT Item No. 10
For meeting of 11-1-77
ITEM TITLE Resolution 8871: Accepting Bids and Awarding Contract for the
Construction of a Storm Drain on Whitney Street
and Claire Avenue between "H".Street and "I" Stree
SUBMITTED BY Director of Public Works/City Engineer ~~`~(~
ITEM EXPLANATION (4/5TH'S VOTE REQUIRED YES_ NO x )
The Director of Public Works received bids in the Engineering/Planning
Conference Room at 11:00 a.m. on Thursday, October 20, 1977, for the
construction of a storm drain on Whitney Street and Claire Avenue
between "H" Street and "I" Street.
This is the first of three projects funded under the EDA grant for storm
drain projects, Group II. Funding for the three projects contained in
the EDA grant has been set aside as follows:
Claire Avenue and Whitney Storm Drain $ 77,273
Halecrest and Douglas Street Storm Drain 34,190
General Roca Park Storm Drain 99,055
Engineering Consultant Services 13,717
Total grant for Storm Drain Projects $224,235
Group II
Bids were submitted by two contractors as follows:
Mike Masanovich Construction Co.,
Inc., Arcadia, California
Alternate 1 Alternate 2 Alternate 3
$ 86,808.50
Carver Corporation, Santee,
California
$101,726.00 $103,230.50 $104,465.00
(Continued on Supplemental Page)
~._ ". `~~ tXH IiS 1 15
Agreement Resolution x Ordinance Plat_ Notification List!
Other ENVIRONMENTAL DOCUMENT: Attached Submitted on
FINANCIAL IMPACT
Cost of constructing this project is being financed with EDA grant ,funds.
The City will have to assume maintenance of the improvements upon comple-
tion of the project.
STAFF RECOMMENDATION
1. City Council accept bids and award contract to Mike MasanoVich Con-
struction Company for Alternate 1 in the amount of $86808.50.
2. City Council authorize the expenditure of $91,150 from Account No.
645-6450-PW-401.
BOARD/COMMISSION RECOMMENDATION
A,pPROti EL
by the
COUNCIL ACTION Ci.a;;~ Co~~^cil
Choi :~. ~. -,_': z„ Cali:°ornia
AGENDA ITEM N0. 10
Supplemental Page 2
November 1, 1977
Alternate 1 is for reinforced concrete pipe. Alternate 2 is corrugated
steel pipe and Alternate 3 is for asbestos cement pipe. Mike Masanovich
Construction Company submitted the low bid of $86,808 for Alternate 1.
This is 29~ above the engineer's estimate of $67,517. Pending amount of
low bids received for the other two projects under EDA Group II Storm
Drain Project, the City may have to appropriate additional funds or cut
back on the scope of these projects if bids are too high.
Engineering staff has reviewed the two bids and has determined that the
low bid submitted by Masanovich Construction is a reasonable and compe-
titive bid. Reasons for the low bid being 29~ higher than the engineer's
estimate are:
1. Contractors are busy and therefore are not bidding jobs at a minimum
overhead and profit margin.
2. City's projects are in competition with other agencies which also
have to award contracts within the 90-day time constraint imposed
by EDA.
3. Heavy construction activity in the private sector has reduced the
number of contractors available and willing to bid on public works
projects.
4. The lOg minority contractor/supplier requirement and additional
paperwork required by EDA has discouraged contractors from bidding
or those bidding have increased their bids accordingly to compensate
for additional overhead costs.
Financial Statement
Low Bid by Masanovich Construction $ 86,808.50
5~ Contingencies 4,341.50
Total Expenditure Requested $ 91,150.00
Group II Storm Drain EDA Grant - $224,235.00
Account No. 645-6450-PW-401
Engineering Consultant Fees $ 13,717.00
Construction Cost Including Contingencies $210,518.00
Total Unencumbered Funds Remaining in $119,368.00
EDA Grant, Group II
Form No. F-229
12/73
CERTIFICATE OF CITY/DIRECTOR OF FINANCE
Certification of Unappropriated Balance
I HEREBY CERTIFY that the money required for the
appropriation of funds for the purpose set forth in the attached
resolution is available in the Treasury, or is anticipated to
come into the Treasury, and is otherwise unappropriated.
Amount $ Fund
Purpose
Bidder
Director of Finance
The City of Chula Vista
Date
By
Certification of Unencumbered Balance
I HEREBY CERTIFY that the indebtedness and obligation
to be incurred by the contract or agreement authorized by the
attached resolution can be incurred without the violation of any
of the provisions of the Charter of the City of Chula Vista, or
the Constitution or the laws of the State of California, that
sufficient monies have been appropriated for the purpose of said
contract, that sufficient monies to meet the obligations of the
contract are actually in the Treasury, or are anticipated to come
into the Treasury to the credit of the appropriation from which
the same are to be drawn, and that said monies now actually in
the Treasury, together with the monies anticipated to come into
the Treasury, to the credit of said appropriation are otherwise
unencumbered.
Amount Not to Exceed $ 91.150.00 /~
645 6450 PW 401 i~sr~--'~`~" r/
Director of Finance
The City of Chula Vista
Date 10/28/77 By
Fund Public Works Bill
Dept./Activity Public Works Bill
Purpose Construction of Storm Drain on Whitney St. & Claire Avenue
Biaaer Mike Masanovich Construction
Certificate No. 36