HomeMy WebLinkAboutAgenda Statement 1977/12/13 Item 26_ h 11 T Ur ht1ULF'~; V 1 J I H 26
COUNCIL AGENDA STATEMENT Item No.
For meeting of 12-13-77
ITEM TITLE Resolution #8932: Appropriating Funds for Civic Center Project
Representative, Author?_zinc~ Staff=: to Proceed
with Renovation of City Hall and Accepting
Report on Possible Construction Project Overrun-
SUBMITTED BY Director of Public works/City Engineer ,, 1 rv
flU
ITEM EXPLANATION (4/5TH'S VOTE REQUIRED *YES~ NO )
*(FOR REPORT RECOMMENDATION NO. 2 ONLY)
6Vhen bids were received on October 27, 1977 for the construction contract
of the Civic Center renovation, the contract amount was $1,983,000 which
was 30% higher than the architect's estimate of $1,523,389. A Council
Conference was held on Thursday, November 3, 1977, at which time various
funding sources for the construction contract were discussed. At the
November 8, 1977 meeting, Council appropriated the approximately $68,000
required to amend the previously budgeted amount in order to cover the
contract.
At the November $, 1977 meeting, I indicated to Council that I would re-
port back within 30 to 60 days concerning the funding of the cost over-
runs for the Civic Center renovation and for other projects.
It was realized at that meeting that cost overruns might occur not only
on the renovation project but on many other budgeted projects, in that
additional funds required for the renovation project might be competing
with funds required for cost overruns on other projects. Included with
this Agenda Statement is a report which details the overruns on several
projects. It is concluded that funds are presently available to carry
out the projects at this time. It is anticipated that all projects can
be constructed in their entirety this year if the Council is willing to
use all of the money available to them.
:ph JY-
Agreement
Resolution x
EXHIBITS
Ordinance
Plat Notification List
Other (Report) ENVIRONMENTAL DOCUMENT: Attached Submitted on
FINANCIAL IMPACT
Funds required for project representative, $1.9,000, are available from
the unappropriated balance of Federal Revenue Sharing.
STAFF RECOMMENDLT_ION
Accept report with staff recommendations.
BOARD/COMMISSION RECOMMENDATION
AppF~OVED
1/ ~, 1.~
COUNCIL ACTION C ~ i`- :,;; ~ ~i 1
G
na.ted _ ...............................
December 8, 1977
File No. JY-017
TO: The Honorable Mayor and City Council
VIA: Lane F. Cole, City Manager
FROM: W. J. Robens, Director of Public Works
SUBJECT: Report on Possible Construction Project Overruns
BACKGROUND
When bids were received on October 27, 1977 for the construction
contract of the Civic Center renovation, the contract amount was
$1,983,000 which was 30% higher than the architect's estimate of
$1,523,389. A Council Conference was held on Thursday, November 3,
1977, at which time various funding sources for the construction
contract were discussed. At that time Council appropriated the ap-
proximately $68,000 required to amend the previously budgeted amount
in order to cover the contract. The Director of Public Works indi-
cated that he would be back to Council within thirty to sixty days
to discuss possible methods of reducing the Civic Center construc-
tion costs and also other projects that have been budgeted for
Fiscal Year 1977-78 and for which the estimated amount is now higher
than the budgeted amount.
RECOMMENDATIONS
It is recommended that: (1) the City Council authorize the con-
struction of the plaza, fountain and arcade with the Civic Center
renovation project, (2) the City Council appropriate $19,000 for
a previously approved agreement with the project representative,
(3) the City Council authorize staff to proceed with the renovation
of City Hall -- staff will negotiate the contract with the Architect
and come back to Council at a later time to appropriate funds as
necessary, and (4) the City Council take no other action concerning
the funding of other projects at this time.
DISCUSSION
This report will discuss various projects for which the current
estimate for construction is higher than the amount budgeted in
the Fiscal Year 1977-78 budget. The report will also discuss
possible funding sources for these projects.
Civic Center Renovation
The first project to be discussed is the entire Civic Center reno-
vation. When the application was submitted to EDA, it was antici-
pated that all three buildings (the old library, old post office
and City Hall) would be renovated during the course of the project.
Approximately $2,016,000 was budgeted to cover the cost of this
project. The construction portion of the old library/post office
renovation, however, was approximately $450,000 over the estimated
amount. On November 3 and November 8, Council was forwarded a two-
page attachment that listed various cost estimates for the entire
Honorable Mayor and, -2- .December 8', 1977
City Council
project, three options to follow during the project and a listing
of possible funding sources. That attachment is again appended
to this report.
The $250,000 estimate for City Hall renovation is a bare-bones
renovation that will consist primarily of mechanical and electrical
improvements to City Hall with approximately $35,000 set aside
for the interior renovation of the building. As the City has re-
quested that EDA delete City Hall from the project as was origin-
ally defined, City forces will be able to do some of the work on
City Hall. This $250,000 estimate is not a detailed estimate as
the architectural/engineering plans and specifications for the
building have not been prepared. It is therefore subject to later
change.
As was discussed during the Council Conference of November 3, Robert
G. Fisher Company, the contractor doing the construction portion
on the old library/post office, has agreed to allow the City a 1000
price deduct for the deletion of various items in the contract. He
has further agreed to allow two representatives, the architect and
a City representative, to examine his cost estimates to ensure that
the City receives the actual 100 deduction. The items that might
be deleted from the construction contract without significantly al-
tering the function of the buildings themselves, were the plaza,
fountain, arcade and plaza furniture. The total amount to be saved
by deleting these items is $148,000.
If Council anticipates the eventual construction of the plaza, ar-
cade and fountain, it would be more cost effective to leave those
items in the current contract. Possible funding sources for the
entire project are indicated on Page 2 of the attachment. Various
funding sources will be detailed toward the end of this report af-
ter other projects which may have cost overruns have been discussed.
Third Avenue Street Improvements
In the Fiscal Year 1977-78 budget, Council appropriated $325,000
from Special Capital Outlay for street improvements on Third Avenue
between "E" and "F". The latest engineer's estimate, prepared on
October 13, 1977, is $435,000. The Community Development Depart-
ment intends to bid the project with three alternatives. The first
will be the entire project, "E" to "F" Streets. The second would
be to do everything on Third Avenue between Davidson and "F" Street.
The approximate estimate for this is very close to the $325,000
that has been budgeted. The third alternate is to do the entire
project between "E" and "F" Streets with certain deductive items.
The estimate for this is approximately $394,000. When bids are re-
ceived, staff will have a better idea of exactly how much the over-
run will be. It is currently anticipated that any overruns in
Third Avenue could be funded as follows: Some additional funding,
approximately $50,000, is eligible for Gas Tax funds for installa-
tion of the storm drain and traffic signal at Davidson and "F"
Street. The remainder could come from the unappropriated balance
of Federal Revenue Sharing.
Honorable Mayor and -3- .December ~, 1977
City Council
Other C.I.P. Projects
RS-5, the concrete-lined channel to be installed south of East
Naples and west of Monserate, for which $74,400 was originally
budgeted, currently has an estimate of $14,000 higher.
RS-6, the construction of a storm drain on Marl Court at East
Reinstra Street, for which $14,000 was originally budgeted, now
has an estimated construction cost of $3,000 higher.
GT-74 which is for purchase of right-of-way on Telegraph Canyon
Road in conjunction with El Rancho del Rey Unit No. 5, was origin-
ally budgeted at $156,000. Latest information from the City's
agent, Sam Blick, indicates that the actual City share will be
closer to $200,000, which means that an additional $44,000 will
have to be budgeted for this project.
The current "F" Street widening project, which has a total of
$332,000 budgeted in GT-53 and GT-75, now has an estimate of
$375,000. During the course of the project and upon completion,
the City will receive approximately $207,000 in FAU funds which
will then be pumped back into Gas Tax funds. However, when the
contract is let, the City must have the entire amount appropriated.
We will therefore require an additional $43,000 in Gas Tax Funds.
There may be other CIP projects to be funded with Community Develop-
ment Block Grant Funds and Park Acquisition and Development Funds
that may have cost overruns. However, there will be enough money
in Block Grant Local Option Funds to cover Block Grant shortfalls
and it is not anticipated that funds other than Park Acquisition
and Development Funds would be used to fund any shortfalls in
those projects. Some of the projects currently budgeted under
current and previous year Gas Tax Funds may, upon receipt of bids,
be higher than the estimated amount. However, since design is not
completed on these projects, the amount of overrun, if any, is not
known.
Funding Sources for Project Overruns
At the current time there is approximately $100,000 in unappropri-
ated Gas Tax Funds which can be used to fund the shortfall for the
Telegraph Canyon Road right-of-way acquisition and "F" Street
widening. There will also be about $14,000 originally budgeted for
the construction of traffic signals on "L" Street (GT-78) which
will probably not be required unless unforeseen contingencies occur
during that construction project.
The current unappropriated balances of Federal Revenue Sharing Funds
is $349,000 and of Residential Construction Tax is $136,000. As
detailed on Page 2 of the attachment, if RS-9, Brandywine/Orange
Avenue extension, and RS-11, the Orange Avenue Fire Station, are
not constructed this year, an additional $235,000 will be available
in Revenue Sharing for project overruns. Additionally, Revenue
Sharing funded projects that are budgeted for Fiscal Year 1977-78
but will not be constructed during Fiscal Year 1977-78 (RS-3, Orange
Honorable Mayor and 4 December 8, 1977
City Council
Avenue acquisition, Third to Albany, and RS-10,
Center) would make available another $201,000 in
A summary of those funding sources is on Page 2
Salary for Civic Center Project Representative
Senior Citizens
Revenue Sharing.
of the attachment.
As indicated at the November 3 and November 8 meetings, $19,000
is required for the salary of the project representative for Civic
Center renovation. As the agreement with the project representa-
tive has been previously approved by the Council and the project
representative has started work, $19,000 should be appropriated
at this meeting.
CONCLUSIONS
Exhibit B, attached, displays known cost overruns of $663,000.
It also shows available funding in Gas Tax, Residential Construc-
tion Tax, and Revenue Sharing of $$34,800. The amount remaining
for other project cost overruns this year or to be available for
other projects which the Council wants to fund this year or next
year would be $171,800.
At the present time, we foresee no major additional changes to
budgeted projects which would require additional funding in the
near future. However, the way bids have been coming in, I do not
have a strong feeling of confidence as to what might happen in
the next six months.
At this meeting (or the next meeting), it is important that the
City Council make a decision concerning the plaza, fountain and
arcade; because, in January, the contractor will withdraw his
offer of 1000 credit for deduct items. He has scheduled work on
the plaza to begin on January 16, 1978.
If Council wishes to have a completed plaza area which is signi-
ficantly and dramatically different from the plaza today, then it
is my recommendation that the Council authorize the contractor to
proceed with the construction in that area as bid. I make this
recommendation because it is my expectation that, even with a
high bid, in one, two or three years whenever Council wishes to
go ahead, the construction costs would approximate or exceed the
cost as scheduled today anyway. Furthermore, I am aware of no
reason why money would be more available in the future than it
is now. Also, at this time, construction in the area can be
better integrated with the overall construction and the incon-
venience for citizens and employees using City Hall would occur
just during one period rather than during two periods.
If the City Council does not want a significant or dramatic
change in the area in front of City Hall, then it would be my
recommendation to not go ahead with the plaza, fountain and ar-
cade. It would be possible then in the future to redesign the
area so that construction costs could be significantly reduced.
This would require new landscape plans. Savings of $50,000 to
$100,000 might result dependent upon the scope of a future project.
honorable Mayor and 5 December.8, 1977
City Council
Decisions on the other projects discussed in this report need not
be made at this time. It is clear that money is available to com-
plete all of the projects as originally budgeted, if that is Coun-
cil's decision. Since most of the projects seem to be high prior-
ity projects, I would recommend that no specific actions be taken
on those projects at this time. Nonetheless, I recommend that
future approval of additional funding for any of the projects be
given only after careful consideration and understanding of the
priorities since the balance of available funds for Capital Pro-
jects will be significantly lower than expected. This will cer-
tainly impact projects programmed but not budgeted in the approved
Six-Year Capital Improvement Program.
DCB:ph
RENOVATION FUNDING
FUNDS REQUIRED FOR ENTIRE PROJECT
Construction Contract for Old Library/Post Office $1,983,000
(Actual Bid)
Furniture for Old Library/Post Office (Estimate as $ 180,000
of 12/76 + 9o CPI increase)
Project Coordinator's Salary $ 19,000
Sub-Total for Old Library/Post Office
City Hall Renovation (Option B)
TOTAL
/EXHIBIT A
$2,182,000
250,000
$2,432,000
OPTION lA - Award the construction contract in full, as bid. Additional funds would have to
be appropriated. (See Page 2 for possible sources)
Construction Contract (Actual Bid) $1,983,000
2~ Contingency 39,660
Amount for Contract $2,022,660
Currently Appropriated (See Page 2) $1,,954,323
SHORTFALL $ 68,337
OPTION 1B - Award the contract as bid, but reduce the amount through deductive change orders.
Contract as bid plus contingency
Delete Plaza
Delete Fountain
Delete Arcade
Delete Plaza Furniture
Total to be Deleted
Amount of Contract
Currently Appropriated
Remaining Amount
$ 71,000
$ 42,000
$ 21,000
$ 14,000
$2,022,660
$ 148, 000
$1,874,660 " ~~
$1,954,323
$ 79,663
OPTION 2 - Reject bids and rebid contract using Old Library/Post Office as the base and the
plaza, fountain, arcade and plaza furniture as additives.
-~- - *Yage -~ .~
~- _ ~ ~
. _ ~ ~- '
FUNDS AVAILABLE
Previously Budgeted for Renovation $1,231,853
EDA Grant $ 722,470
Sub-Total Currently Appropriated Funds
CIP Projects Budgeted for FY 77-78 That Will
Not be Constructed
RS- 9 Brandywine/Orange Avenue Extension $ 100,000
RS-11 Orange Avenue Fire Station $ 135,800
Sub-Total $ 235,800
Unappropraited Balance of:
Revenue Sharing $ 417,000
Residential Construction Tax $ 136,000
Sub-Total $ 553,000
Sub-Total Funds Available Not Appropriated
Sub-Total
CIP Projects Budgeted for FY 77-78 That Will
Not Be Constructed During FY 77-78
RS- 3 Orange Avenue R/W Acquisition Third to Albany $ 103,000
RS-10 Senior Citizen Center $ 98,100
Sub-Total
TOTAL
$1,954,323
$ 788,800
$2,743,123
r ~nl _ ~ n(1
$2,944,223
__ y
..
/EXHIBIT B/
POSSIBLE C.I.P. EXPENDITURES AND REVENUE SOURCES
r:NOtiā¢rv FUi1DS nE~UIRED OVER BUDGET
Civic Center Renovation
*Furniture for Old Library/
Post Office
*Project Coordinator's Salary
Sub-Total
City Hall Renovation
Total Civic Center Renovation
Third Avenue Street Improve-
ments (Full Project) ($50,000
eligible for Gas Tax)
RS-5, Concrete Channel, south
of E. Naples, west of Monserate
($0 eligible for Gas Tax)
RS-6, Storm Drain, Marl Court
at East Rienstra ($3,000 eligible
for Gas Tax)
GT-74, Telegraph Canyon Road
right-of-way, E1 Rancho del
Rey #5 ($44,000 eligible for
Gas Tax)
GT-53 & 75, "F" Street Widening
($43,000 eligible for Gas Tax)
TOTAL
*These funds are required
whether or not City Hall
is renovated.
FUNDING SOURCES
Gas Tax
$180,000 Unappropriated Gas Tax $100,000
Balance
19,000 GT-78, "L" St. Traffic 14,000
Signals Excess
$199,000
Gas Tax Sub-Total $114,000
250,000
Residential Construction
$449,000 Tax
110,000 Unappropriated Balance $136,000
Revenue Sharin
14,000 Unappropriated Balance $349,000
RS-9 Brandywine/Orange 100,000
Avenue Extension
3,000
RS-11 Orange Avenue Fire 135,800
Station
44 000 ~ Revenue Sharing Sub- $584,800
Total
43,000
$663,000
TOTAL
C.I.P. PROJECTS BUDGETED FOR
FY 77-78 THAT WILL NOT BE CON-
STRUCTED DURING FY 77-78
RS-3 Orange Ave. right-of-way
acquisition Third to Albany
RS-10 Senior Citizen Center
TOTAL
$834,800
$103,000
98,100
$201,100