For meeting of 5/9/78
ITEM TITLE Resolution 9096 Granting an Extension of Time, Mueller
Neighborhood Park, Phase Two
SUBMITTED BY Director of Public Works/City Engineer
~~ "!
ITEM EXPLANATION (4/5TH'S VOTE REQUIRED YES NO x )
T.B. Penick and Sons, Inc., has requested sixteen days extension of
their contract time for subject project. The project was awarded by
Council Resolution No. 8986, on January 24, 1978.
The Division of Engineering has reviewed the request and determined
that sixteen days is justified. There were eight days of rain during
February and March, and eight days that the ground was too wet to
work.
The extension of time will change the contract completion date to
June 1, 1978.
DMH:rms/
txr~ i rs i i
Agreement Resolution x Ordinance Plat Notification List
OtherLtr fm PenickENVIRONMENTAL DOCUMENT: Attached Submitted on
FINANCIAL IMPACT
None
STAFF RECOMMENDATION
Approve Resolution granting an extension of 16 days to the contract
time.
BOARD/COMMISSION RECOMMENDATION
COUNCIL ACTION
96
Form A-113 (Rev. 5/77)
A P P R O V E D
by the
C~ t;T Cour_cil
of
:Oat ed, , ....... S':.. 9 -..~. ~.~._~___
r~
~ ~ -"
` 5[NfA - ~
~ ~i ..
,o .~M~p,~a,. 864-347ti STREET P.O. BOX 8428 • SAN DIEGO, CALIFORNIA 92102
• TELEPHONE: 239.3046
May 3, 1978
W. J. Robens
Director of Public Works
City of Chula Vista
P. 0. Box 1087
Chula Vista, California 92012
Attention: Dewey Hughes
Dear Mr. Robens:
Subject: Mueller Neighborhood Park, Phase 2
We request an extension of the contract completion date on this
project to May 30, 1978 because of rain and wet grounds during the
months of February, March and April.
Sincerely,
T. B. PEP~ICK & SONS, INC.
Wayne R. Myers
Vice President and Treasurer
WRM:js
96