HomeMy WebLinkAboutAgenda Statement 1978/04/25 Item 04• CITY OF CHULA VISTA
COUNCIL AGENDA STATEMENT Item No. 4
For meeting of 4-25-78
ITEM TITLE Resolution 9082 Granting Extension of Time, Edgemere Avenue
Improvements, "C" Street to I-54 Freeway
SUBMITTED BY Director of Public Works/City Engineer 1r1
ITEM EXPLANATION (4/5TH'S VOTE REQUIRED YES NO x )
The Griffith Company has requested a fifty-two day extension of the
contract time for the Edgemere Avenue widening project. The contract
was awarded by Council Resolution No. 8891. The contract time expires
on May 3, 1978.
The extension of time was 'requested because of inclement weather.
There was a total of 31 calendar days of rain between January 3, 1978
and April 1, 1978. There were 21 calendar days that the contractor
could not work because of saturated and unstable soil conditions.
This totals 52 calendar days that the contractor was delayed because
of inclement weather.
The Division of Engineering has reviewed the request by Griffith
Company and has determined that a fifty-two day extension of time
to the contract is justified.
The extension of time will change the contract completion date to
June 23, 1978.
EXHIBITS
Agreement Resolution x Ordinance Plat Notification List
Other Letter ENVIRONMENTAL DOCUMENT: Attached Submitted on
FINANCIAL IMPACT
None
STAFF RECOMMENDATION
Adopt resolution granting the extension of time.
BOARD/COMMISSION RECOMMENDATION
N.A. ~PPROY~D
by the
COUNCIL ACTION ~'~'~;~? C'o~,~._;il
~®d
W
GRIFFITH COMPANY
~O/1 t3'GTCEOY$ • LICENSE NO. 32168
1501 FRAZEE ROAD, BOX 33187, SAN DIEGO, CALIFORNIA 92103 (114) 297.4455
April 14, 1978
Director of Public Works
City of Chula Vista
P.O. Box 1087
Chula Vista, California
Attention: Dewey Hughes
Subject: I-54 of Street Improvements on Edgemere Avenue
between I-54 Freeway ~ "C" Street in the City
of Chula Vista, California
Re: Job 2-1512
Gentlemen:
Reference is made to our letter dated February 8, 1978, requesting
an extension of time on the subject project due to inclement
weather in the Chula Vista area. It has been determined that this
situation has delayed the project fifty-two (52) calendar days.
Please issue the appropriate extention of time change order.
Very truly yours,
GRIFFITH COMPANY
!(
r., _
Jim Maczko
Estimator
JEM/gw
~~,