HomeMy WebLinkAboutAgenda Statement 1979/06/26 Item 13CITY OF CHULA VISTA
COUNC 1 L AGENDA STATEMENT Item No: 13
For meeting of 6/29,/79
Resolution 9~'3 Accepting Bids and Awarding
ITEM TITLE Contract for Construction of Improved Drainage
Channel South of East Naples Street Between
Monserate Avenue and Helix Avenue
SUBMITTED BY City Engineer
ITEM EXPLANATION (4/5TH'S VOTE REQUIRED YES NO x )
At 11:05 a.m, on June 7, 1979, in Conference Room 5 of the
Public Services Building, the City Engineer received and
opened sealed bids for "The Construction of an Improved
Drainage Channel South of East Naples Street Between
Monserate Avenue and Helix Avenue, Chula Vista, California."
The scope of work includes the construction of an open
channel (Portland Cement Concrete or Air Placed Concrete),
transition structures, and installation of pipe. Two
alternatives were bid, the difference being in the type of
pipe used: Reinforced Concrete Pipe (RCPT) for Alternate #1
and Corrugated Steel Pipe (CS P) for Alternate #2.
Bids were received from three contractors as follows:
B IDDER
1. Meza--Hab Construction Company,
Chula Vista
2. T. B. Penick & Sons, Inc.,
San Diego
3.- Sapper Construction Co.,
San Diego
SLH:nr/AN-005
ALTERNATE #1
$58,700.00
NONE
82,559.16
ALTERNATE #2
$58,700.00
56,812.07
81,934.15
(continued on supplemental page)
tXH1~115
Agreement Resolution x Ordinance Plat Notification List
OtherC~motorne~NVIRONMENTAL DOCUMENT: Attached Submitted on
FINANCIAL IMPACT
Cost of project is being financed with Revenue Sharing Funds.
City will assume maintenance of the improvements upon completion
of the project.
STAFF RECOMMENDATION
1. City Council authorize the expenditure of $64,570.00 from
"Concrete Channel s/o Naples Street and w/o Monserate Avenue,"
Project Account #600-6000-RS05.
2. City Council accept bids and award contract to Meza-Hab
Construction Company in the amount of $58,700 for construction
of Alternate #1 using reinforced concrete pipe.
BOARD/COMMISSION RECOMMENDATION
~ ~y.~y
COUNCIL ACTION
' cif
(~ c '~:~
~ ~z<~-~'
/i
Agenda Item No. 13
.. For Meeting of 6/ /79
Supplemental Page Two
The low bid submitted by Mesa Hab Construction Company is
above the Engineer's estimate by $?885. This low bid is
above the Engineer s estimate of $55,815 by 5,170,
~,~° y 3
There was an irregularity in the bidding process in that one
of the bidders tried to submit his bid at the Administration
Office in the City Hall building rather than at the Office
of the City Engineer in the Public Services Building just
prior to 11°00 a.m. At approximately 11..:.01 we received a
call from the secretary in Administration that a messenger
with the bid was there and didn"t know where to go. She
then sent him over to the City Engineer's office. By the
time he brought his bid over to the office of the City
Engineer in the Public Services Building it was
approximately 11005 a.m.
No bids had been opened prior to the submitting of this bid.
The staff accepted the bid and then proceeded to open bids.
This late bid was the low bidder.
The City Attorney was asked to review this matter and
attached is a copy of his response. It was his opinion that
the bid be awarded to the lowest bidder.
We have received an objection from the second lowest bidder
about awarding the contract because the bid was not in the
City Engineer"s office at 11:C0 a.m. However, we concur
with the City Attorney's opinion anti recommend awarding the
contract to the lowest bidder.
Should the Council decide not to award the bid we recommend
that all bids be rejected and the staff be directed to
readvertise for new bids. This may result in receiving
higher bids for the same work because construction will be
occurring further into the rainy season.
FINANCIAL STATEMENT
Unencumbered funds
"Concrete Channel
and w/o Monserate
available in
s/o Naples Street
Avenue ," RSOS
$70,931.93
Contract Amount
10~ Contingencies
TOTAL ESTIMATED CONSTRUCTION COSTS
58,700.00
5,870.00
$64,570.00
DATE: June 13, 1979
TO: John Lippitt, City Engineer
FROM: George D. Lindberg, City Attorney
SUBJECT: Alleged Irregularities in Low Bidder's Bid
Submittal for the Construction of Improved
Drainage Channel South of East Naples Street
between Monserate Avenue and Helix Avenue
You recently informed this office of the fact that bids were
received on Thursday, June 7, 1979 from several contractors
for the construction of improved drainage channel south of
East Naples Street between Monserate Avenue and Helix Avenue.
One of the parties who prepared a bid document did not arrive
at the office of the City Engineer, which is now located in
the newly remodeled annex to City Hall, until after 11:00 a.m.,
the appointed hour. It is clear from your statements to me
that the individual carrying the bid documents was confused
because of the recent relocation of offices and I cannot find
in any way a reasonable basis for rejecting his bid because of
that confusion.
Secondly, the same bidder had failed to have all of the bid
documents properly executed in that written signatures were
not affixed to some of the documents. Here again, I feel con-
fident that the City would have every right to insist upon
performance under the terms presented in such documents and
that the offer of intent of the parties was clearly understood
and a binding contract established.
Although I recognize that since the individual involved was
clearly the low bidder and the others who had bids higher,
more particularly the next low bidder, have registered objec-
tions as to the alleged irregularities, I cannot concur that
such irregularities justify the rejection of the bids.
It is, therefore, the opinion of this office that the bid be
awarded in the drainage channel construction project noted
hereinabove to the lowest bidder.
GDL:lgk
cc: City Manager Cole
Deputy City Manager Robens
~~53
ALEC L CORY
EMMANUEL SAVITCH
GERALD E. OLSON
PAUL B. WELLS
TODD E. LEIGH
JEFFREY ISAACS
ROBERT J. BERTON
RICHARD B. MUNKS
DENNIS HUGH MCKEE
JOHN C. MALUGEN
FREDERICK K. KUNZEL
ROBERT G. RVSSELL, JR.
GEORGE L. DAMOOSE
K. RONALD LEEPER
THOMAS M. FIO RELLO
KELLY M. EDWARDS
ANTONIA E. MARTIN
RAYMOND G. \V RiG HT
RICHARD HILL GENES
CHARLES T. HAR RINGTON
FILiE~ G
LAW OFFICES OF ~
PROCOPIO, CORY, HARGREAVES AND SAVITCH
AREA cooE X14
1900 CALIFORNIA FIRST BANK BUILDING I TELEPHONE 238-1900
5 3 0 B S TREE T _ ~ ,,, -. ~ ~
SAN DIEGO, CALIFORNIA 92101
A. T. PROCOPIO
I ,.~ 1900-194
June 22, 1979
Honorable Mayor and
City Council
City of Chula Vista
276 Fourth Avenue
Chula Vista, California 92118
Re: East Maple Street drainage system;
Alternate #2
To Whom It May Concern:
HARRY HARGREAVES
R ETIR EO
JOHN H. BARRETT
RETIRED
We are counsel to the Associated General Contractors
of America, San Diego Chapter, Inc.
We are advised that on June 7, 1979, sealed competi-
tive bids were received by the City of Chula Vista for the
construction of the captioned project. We are further ad-
vised that the bid of the apparent low bidder, Mezar H. Hab,
did not conform with either the Invitation or the applicable
law in that the same was submitted after the time set forth
in the Invitation and, further, that the same was unsigned.
The purpose of this letter is to inform you that it
is our intention to take such action as we may deem necessary
to protect the integrity of the competitive bidding pro-
cess should the contract for the construction of the cap-
tioned project be awarded to any person or company other
than the lowest responsive and responsible bidder. Of
course, if our information is correct with respect to the
deficiencies of the bid of the apparent low bidder, it
could in no way be considered to be the lowest responsive
and responsible bidder.
';
Yours v~r•y t ~y,
~,
PAUL B. WELLS, of
Procopio, Cory, Hargreaves
and Savitch ~L~
~~~
PBW:smc ~ ~
~~
cc: City Manager, City of Chula Vista b~~h
Associated General Contractors ~~ ~'"!' ~,/}'
~~ Registered mail; return receipt requested t,•~ ` (i~G'. ~'~"
~~`~
cxANG~ IN CONTRACT
ORDER NO. ONE
The Construction of Improved Drainage
Channel South of East Naples Street DAmE October 24, 1979
Between A~Ionserate Avenue and
Helix Avenue CONTRACT
CONTRACTOR
JOB AN-005
The following change shall be made to increase the
contract dated July 19, 1979, between the City of Chula Vista and
Meza-Hab Construction Co. , Contractor.
REMARKS AND DETAILS:
Item Approx. Qty. Description Price Total
Deletions:
2. 4,201 S.F.__ 2" Air Placed Concrete $2.00 $8,402.00
or Portland Cement
Concrete Paving
3. 80 L.F. 8" Air Placed Concrete 4.00 320.00 -
or Portland Cement
Concrete Berm
6. Lump Sum Trench Shoring 4,996.00 4,996.00
Sub-Total, Deletions 13,718.00
(See attached sheet)
ORIGINAL, CONTRACT PRICE $ 58,700.00
Previous Change Order Nos. $
Revised Total Contract Price $
This Change Order No. 1 $ 11,318.00
It is agreed by the undersigned that all extra work shall be performed
and materials furnished in accordance with the original contract and in
accordance with the statement, if any, attached hereto.
TOTAL CONTRACT $ 70,018.00
ti~
APPROVED BY: ACCEPTED BY: ORDERED BY:
City Council Resolutio
_No. 9824 datedl0/23/7 Meza-Hab Construction
B o. Kenneth Go amp
n' i
John P. Lippitt,
Cit Engineer ~~ `i~ .
~~
,
Y
PW-E-44
~96~~
t
Item Approx. Qty, Description Price Total
Additions:
2. 9,116 S.F. 4" Air Placed Concrete 2.50 22,790.00
or Portland Cement
Concrete Paving Rein-
forced with 6"x6" 10/10
ga. W.W.M.
10. Lump Sum Grading 2,246.00 2,246.00
Sub-Total, Additions 25,036.00
Total, Net Addition $11,318.00
By this Change Order the time extension of 26 days is approved,
extending the completion date until December 6, 1979.
~~5'~
CHANNEL TYO/CqL SECT/ON
.C~3ElN~ CONSTiQG/GTE,O
~~
DRAWN BY
-~_._. ~W ____
OA7E
- - - ~~ ~~5=79- -
CHANNEL TYP/cAL SECT/D/V
AS P.4'OP0,5'E,O 8Y C/~A/VGE
O~POE~ ~ /
T I T l E
P~OPOS EO Cf~•4NGE O~OE•~P /N TY~/GqL SECT/ON OF
EAST NAPLES ST. D~f'A/N,L1 GE CHANNEL