HomeMy WebLinkAboutAgenda Statement 1979/06/26 Item 10CITY OF CHULA VISTA
COUNCIL AGENDA STATEMENT
Item No: 10
For meeting of 6/26/79
ITEM TITLE Resolution /d~~o Accepting Public Improvements - Broadway/"L"
Street Traffic Signal
SUBMITTED BY City Engineer
ITEM EXPLANATION (4/5TH'S VOTE REQUIRED YES NO x )
Arrow Electric Company has completed the construction of the traffic
signal system (upgrading of old system) at Broadway/"L" Street in
accordance with contract documents dated February 13, 1979, and as
awarded by Council Resolution 9458, dated January 16, 1979.
The contractor was given a time extension due to delay in receipt
of the signal poles. He did not complete the project until four
days after the end of the time extension and since he has not
submitted information which justifies the additional delay, the
City is withholding $200 ($50/day) in liquidated damages ir.
accordance with the contract.
The final inspection was completed on June 15, 1979, and it is now
appropriate that the City Council accept this project. ~~
~~ a ~ ~ ~ ~~
~~~-79
GRx:nr/Bx-ol8 EXHIBITS
Agreement Resolution x Ordinance Plat Notification List
Other ENVIRONMENTAL DOCUMENT: Attached Submitted on
FINANCIAL IMPACT
The construction contract price was $28,880. The contractor was
assessed $200 in liquidated damages for running four days beyond
the contract time to complete the project. Total cost to the City
was $28,680.
STAFF RECOMMENDATION
Approve resolution.