HomeMy WebLinkAboutReso 1979-96065/21/79
RESOLUTION NO. 9606
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA
VISTA APPROVING PLANS, SPECIFICATIONS, AND COST
ESTIMATE FOR THAT CERTAIN ASSESSMEPdT DISTRICT KNOWN
AS THE WALNUT AVENUE 1911 ACT ASSESSP4ENT DISTRICT
79-1 - FROM 192 FEET NORTHERLY OF PALONIAR STREET
TO 735.5 FEET NORTHERLY
The City Council of the City of Chula Vista does hereby
resolve as follows:
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Chula Vista that the plans, drawings, typical cross-
sections, profiles and specifications submitted by the City
Engineer and filed in the office of the City Engineer and the
City Clerk as Drawing No. 78-242D for the construction of curbs,
gutters, sidewalks, driveways, street paving, sewer facilities,
a street light and relocation of water facilities be, and the
same are hereby approved and adopted as the official plans,
drawings, typical cross-sections, profiles and specifications
for said work and improvement.
BE IT FURTHER RESOLVED that the City Council does
hereby waive payments in advance of incidental expenses by the
Contractor,
Presented by
,.
hn P. Lippitt, C t Engineer
ADOPTED AND APPROVE
CHULA VISTA, CALIFORNIA, this
by the following vote, to-wit:
Approved as to form by
George Lindberg, City Attor~
D by the CITY COUNCIL of the CITY OF
22nd day of May , 197_2,
AYES: Councilmen Scott, Cox, E~dahl, Hyde Gillow
NAYES: Councilmen None
ABSENT: Councilmen None
!~ "~~
;'
ATTES~ C~,c.l' C / -,(/~-C~-'~~i~~-,
~ Deputy City Clerk
STAT~/OF CALIFORNIA)
COUNTY OF SAN DIEGO) ss.
CITY OF CHULA VISTA)
• '»
Mayor of the City of Chula Vista
I- City Clerk of the
City of Chula Vista, California, DO HEREBY CERTIFY that the above is
a full, true and correct copy of Resolution No. , and that the
same has not been amended or repealed. DATED
City Clerk
1 ~~
~~ ,'WALNUT AVENUE 1911 ACT IMPROVEMENT
DISTRICT COS^1 ESTIMATE
I. Construction of Improvements
Item
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Total
Quantity
Grading and Excavation L. S..
Asphalt Concrete Pavement 420 Tons
Crushed Rock Base 1,760 Tons
3-1/2" P.C.C. Sidewalk 3,475 Sq. Ft.
6" P.C.C. Curb & Gutter 780 L.F.
5-1/2" P.C.C. Driveway Approaches 3,257 Sq. Ft.
Street Light 1 ea.
Copper Water .Pipe - Building 20 L.F.
Supply 3/4" to 1"
3" Force Main Sewer Laterals 270 L.F.
4" PVC Sewer Laterals 60 L.F.
Force Main Sewer Lateral Cleanout 8 ea.
and Cap
Unit
Price
7,500.00
23.00
10.00
2.00
10.00
2.50
2,000.00
25.00
25.00
18.00
50.00
Cost
7,500
9,660
17,600
6,950
7,800
8,142
2,000
500
6,750
1,080
400
Adjust rlannoles 2 ea. 300.00 600
• Curb Outlet
5-1/2" P.C.C. Alley Apron
3-1/2" P.C.C. Sidewalk Ramps
II. Incidental Expenses
1 ea. 75.00 75
300 Sq. Ft. 2.50 750
198 Sq. Ft. 3.00 594
Subtotal =70,401
10~ Contingencies (approx) = 7,099
Estimated Construction Cost 77,500
1. ~~Iater Service Relocation/Adjustment 728
2. Engineering 6,500
3. Title Reports 400
4. Inspection 4,000
5. Sale of Bonds, Publishing, etc. 6,900
(= lOg of Construction Cost without contingencies)
6. Force rdain Purchase 2 000
~p~
Estimated Incidental Expenses= 20,528
Total Estimated Cost =$98,028