Loading...
HomeMy WebLinkAboutAgenda Statement 1979/02/20 Item 15CITY OF CHULA VISTA COUNCIL AGENDA STATEMENT Item No." 15 For meeting of 2/20/79 Accepting Bids and Awarding Contract for ITEM TITLE Resolution 9,~0,~ Third Avenue Street Improvements - Phase I E Street to F Street and Appropriating Funds -_ ~ ; SUBMITTED BY Community Developme t Director/City Engineer via Director of Pub is Works ITEM EXPLANATION (4/5TH'S VOTE REQUIRED YES X NO ) BACKGROUND The planning and funding process for the Third Avenue street improvements has been a long and frustrating experience. The project was first proposed for funding through the Economic Development Administration under the Public Works Bill in 1976, but was not funded. The project was then included in the City's Community Development Block Grant program. However, after the change of administration in Washington in 1977, economic development was no longer an eligible activity under the Block Grant program and the project was declared ineligible. Subsequent to that, the project was funded out of City funds (Special Capital Outlay) fora total of $325,000. Due to the increase in the scope of the project, and the effect of inflation to the original estimate, the project was funded with an additional $201,000 of Revenue Sharing funds in fiscal year 78-79. There already have been expenditures to this project totaling $23,424.95. Most of this. has been for the recent temporary overlay of the alleys parallel to Third Avenue between E and F Street ($6,170) and for the change order to the F Street widening project that installed the decorative stamped concrete to the intersection of Third and F ($15,000). This leaves a total unencumbered balance to the project of $502,575.05. CONSTRUCTION BIDS At 11:00 a.m. on January 25, 1979 in the Engineering Conference Room, the City Engineer received sealed bids for Third Avenue Street Improvements, Phase I, E Street to F Street. (continued on page 2) DPB:as f ~/IITTTTA tJ~ h ! tS 1 I J Agreement Resolution X Ordinance Plat Notification List Other Exhibits A & B ENVIRONMENTAL DOCUMENT: Attached Submitted on FINANCIAL IMPACT Please see Financial Summary. (NOTE: Resolution will be prepared subsequent to public hearing on Block Grant, pending decisions made at the hearing.) STAFF RECOMMENDATION Due to the uncertainties associated with combining the redevelopment areas and the size of the tax allocation bond issue, staff is hesitant to recommend Alternate One. Therefore, Alternate Two is recommended. CITY MANAGER RECOMMENDS CONTINUING THIS ITEM TO FEBRUARY 22, 1979. BOARD/COMMISSION RECOMMENDATION (1) The CIP committee recommends that if additional funds are appropriated for this project during this fiscal year, that the funds be appro- priated from the Residential Construction Tax fund. (2) Project Area Committee recommends Alternate One. ~' COUNCIL ACTION 1 ~ _____.. _..__ ~__ .~.- ~ A. '>; 4 r7 r ~t ~' 1. . ~:._a . .. . ,i , ~~ ~ '~`'~ J` ` Form A-113 (Rev. 5/77) Item No.' 15 For meeting of 2/20/79 Page 2 The scope of the project includes: demolition and removal of concrete curbs, side- walks, asphalt pavement, trees, street light, parking meters, and traffic signals and the installation of textured concrete sidewalks and crosswalks, curbs, asphalt pavement, drainage facilities, street lights, architectural concrete walls, land- scaping and irrigation and street furniture. Bids were received from two contractors as follows: 1. T. 6. Penick & Sons, Inc. $690,714.01 2. Daley Corporation $1,069,209 The low bid submitted by T. B. Penick & Sons, Inc. exceeds the engineer's estimate by $159,615.01. This low bid is above the engineer's estimate of $531,099 by 30%. We have reviewed the low bid and find the major area of increased costs between the engineer's estimate and the low bid to be in the following items of work:. traffic controls ($23,560), asphalt concrete ($10,556), drainage system ($18,404), electrical energy and lighting systems ($17,860), ornamental street li hts ($45,402), street furniture ($7,893), and landscaping and irrigation ($29,19 4 . This represents an aggregate increase of $152,869 over the engineer's estimate. The staff and our consultant, Phillips-Reynolds & Associates, have reviewed the bid and find it to be acceptable. Although some of the bid items were well in excess of the engineer's estimate, we do not believe that the City could realize a savings if the project were re-bid. ALTERNATIVE PROJECTS The City has many alternatives to consider in proceeding with this project ranging from award of full contract to the elimination of the project altogether. Several of the alternatives are outlined here with the accompanying financial obligations. ALTERNATIVE #1 - Fund the Entire Pro,7ect Now The total project cost is $758,532 which would require an additional appropri- ation of $255,957. Project Costs: $690,714 Low bid 34,536 5% contingencies 5,000 Utility relocation 28,282 Engineering services (explained on pg.4 ) $758,532 Total project costs -502,575 Remaining unencumbered $255,957 Additional funds required It is proposed that this additional appropriation be loaned to the project from the Residential Construction Tax fund. As of January 31, 1979, there is a total of $301,346 that is unappropriated and available in that account. It is proposed that the loan be repaid to the City through the sale of tax allocation bonds. If the City is successful in combining the Town Centre Redevelopment Project with the Bayfront Redevelopment Project, such a tax allocation bond issue can become a reality some time during fiscal year 79-80. If the legislation in Sacramento combining the projects is not successful, it may be sometime before the tax increment in the Town Centre I redevelopment area is of a sufficient amount to support a tax allocation issue to repay the loan. If the RCT loan is not repaid in the near future, then these RCT funds would not be available to finance other City projects or cost overruns. I tem No . ~ 15 For meeting of 2/20/79 Page 3 Fund a Portion of the Project Now and Complete the ALTERNATIVE #2 - Pro.iect with Block Grant Funds in FY 79-80 Staff has spent a considerable amount of time with the engineering consultant, Phillips-Reynolds & Associates, and with the low bidder, T. B. Penick & Sons, Inc. to determine the most feasible and economical method to reduce the project in such a way that would have the least overall impact now, and at the same time provide for the most economical way to complete the project in the future. With this in mind, several major items can be postponed: 1. Thirty-nine ornamental street lights. Total Savings: $97,858. The pur- chase of the decorative street lights themselves would be eliminated from this contract but all the underground work required for their installation would still be included. This means that the lights can be installed at a later date without requiring excavation. The existing street lights on Third Avenue would remain until the purchase of the decorative lights, and would be tied into the new underground system installed with this con- tract. 2. Street furniture, benches, trash rece tacles and bic cle racks. Total Savin s: 26,273. These items require very little labor to install and are situp y stock items that can be purchased at a later date. 3. Improvements to the intersection at Third and F. Total Savings: $17,410. The Phase I street improvements on Third Avenue were originally intended to be installed from a point just immediately south of the intersection of Third and E to a point just south of the intersection of Third and F. This change order would shorten the project by eliminating the improvements to the intersection of Third and F. 4. Cites pays energy cost during construction. Total savings: $2,000. The specifications for this contract require the contractor to pay the lighting costs for Third Avenue during construction. This change order would simply mean that the energy cost would be paid by the City. Funds for energy costs are already included in the Public Works department budget. Project Costs: $690,714 Low bid -143,541 Deduction by change orders $547,173 Total project costs + 27,359 5% contingencies + 5,000 Utility relocation + 28,282 Engineering services (explained on pg. 4) $607,814 Project costs -502,575 Remaining unencumbered $105,239 Additional funds required If the Council selects this alternative, it will still be necessary to appro- priate sufficient funds for the entire project, i.e. $758,532 which is an additional $255,957. This can be done with the stipulation that once the contract is executed, the Council will exercise its option to reduce the pro- ject by $143,541 with four change orders. The low bidder, T. B. Penick & Sons, Inc. has tentatively agreed to the change orders. It is proposed that the $105,239 in additional funds be loaned to the project from the balance of the Residential Construction Tax fund. As in the first alternative, this loan would be repaid through the sale of a tax allocation bond issue. It is also proposed that the items eliminated from this contract be budgeted as part of the Community Development Block Grant Program for Program Year Five beginning July 1, 1979. This means that the Block Grant projects for ~~~~.~J~ Item No. •'15 For meeting of 2/20/79 Page 4 the next three years which the City Council has previously considered and tentatively approved would be changed somewhat. Essentially, the Block Grant funds tentatively earmarked for the Third Avenue street improvements from F to G in fiscal year 80-81 would be moved up to fiscal year 79-80 and used to complete the improvements from E to F. This would mean that a project slated for fiscal year 79-80 would be postponed to fiscal year 80-81. It is proposed that the drainage project at Third and Parkway be the project that is delayed for one year. This also means that the total amount of funds earmarked for the street improvements from F to G would be reduced by approximately $150,000. ALTERNATIVE #3 - Reject Bids and Redesi n the Project to Reduce Costs The thrust behind the Third Avenue Street improvements is to enhance the pedestrian environment and encourage a stimulation of the retail trade. A pleasant shopping environment is crucial to the rebirth of the retail commercial element in the Town Centre, and the design of the amenities in this project is essential to accomplishing the intended environment. The amenities, however, are only a portion of the total cost for this project. There are many "traditional" public improvements that also need to be constructed (e.g. storm drain, updated and modernized traffic signal, and a modernized underground electrical system to replace the existing system which is in poor condition). In addition, the soils conditions within the Third Avenue area are very expansive which require that certain expensive measures be taken to protect the decorative concrete that is proposed. These traditional public improvements amount to a significant por- tion of the total project, and if the amenities are to be constructed in any form, it will be necessary to include these traditional public works elements Nonetheless, it would be possible to redesign the project and reduce the cost somewhat. The net result, however, may not be a cost savings. There would be additional consulting fees for engineers and landscape architects for redesign, plus the project would have to be delayed for a minimum of one year. The delay is necessitated by the time it would take to redesign the project, and because o.f the effort to schedule the construction to avoid the rainy season and the holiday shopping season. The twelve month delay may add a considerable amount to the construction cost through inflation alone. The inflation factor in the road construction industry in a recent twelve month period was over 35%. Therefore, a significant reduction in the project scope may not realize any reduction in project costs in today's dollars. ADDITIONAL ENGINEERING SERVICE FEES The City entered into a contract with Phillips-Reynolds Engineering, Inc. on October 12, 1976 to prepare the engineering plans and specifications for the "Town Centre Sidewalk and Alley Improvements." This was a project that was submitted to the Economic Development Administration for funding under the Public Works Bill. The project included not only the improvements to Third Avenue from E to G Streets but also improvements and/or utility undergrounding in eleven alleys. The estimated cost for the street and alley improvements at that time was in excess of $400,000. The scope of work as defined was, of course, used as the basis of negotiations for the consulting services, and the consulting contract of $43,000 amounted to less than 10% of the construction estimate. Subsequent to entering into the contract with Phillips-Reynolds Engineering, Inc., the Redevelopment Agency adopted the Town Centre Design Manual. The criteria for the design of improvements in the project area as set forth in the Design Manual drastically changed the scope of the project as well as the design approach. The project was no longer a typical street rehabilitation project, but a multi-disciplined design project consisting of master planning of architectural and landscaping treatments. The major item not included in the original scope was the development of a project Master Plan. The Master Plan called for the development of an architectural landscape feature with consideration for handling of pedestrian vehicular traffic, including minimizing the loss of on-street parking. The details within the Master Plan included the alternates for street lights, retaining walls, trellises, crosswalk and sidewalk treatment, land- scaping layout, street tree selection, and a design of a drainage system to provide for ~svs Item No . ~ 15 For meeting of 2/20/79 Page 5 the development of intersection and crosswalk nodes. Other considerations were given to a sound system, electrical power system, public telephones, and automatic irrigation system. Once this Master Plan was adopted in March of 1977, the con- sultant was instructed to proceed with design. Additional expenses were incurred by the consultant thereafter because of a re-evaluation of the street light selection and a re-evaluation of the bus stop locations. In addition, the Third Avenue street improvements were divided into two phases (E Street to F Street, and F Street to G Street), and the alley improvements were divided into three phases (certain alleys were grouped together for bidding and construction purposes). Due to the significant expansion in the scope of the project, and due to the re- evaluations during the design phase and the continuous reviews of the project by the Project Area Committee and the Design Review Board, the consultant was required to perform extra work not contracted for. Now the consultant is requesting compensation fora portion of that additional work. Exhibit "A" is a summary of the extra work performed and the amount which the consultant is requesting compensation. Essentially, the consultant is requesting full reimbursement for all additional subcontracted fees (per our agreement, that would be cost plus 15%), plus compensation for one-half of the extra work performed by the consultant. This amounts to a total claim of $28,281.82. Exhibit "B" is an itemized explanation of the extra work performed by the consultant. The total consulting fee for this project would then total $71,281.82 ($43,000 ori- ginal contract plus $28,281.82 additional charges). Staff feels that the additional charges claimed by the consultant are reasonable. If you consider the total estimated construction costs for the street improvements from E to G and all of the eleven alley improvements, the $71,282 consulting fee amounts to approximately 5 or 6% of the total construction cost.. It is, therefore, recommended that the consultant be compensated an additional $28,281.82. However, the City Engineering staff feels that the con- struction plans for the alleys not yet out to bid require some additional work by the consultant. They, therefore, recommend that 25% of the additional compensation be withheld until the alley plans are completed to the satisfaction of the City Engineer. FINANCIAL SUMMARY ALTERNATIVE ONE: 1. Requires additional appropriation of $255,957. Appropriate $255,957 from the Residential Construction Tax fund as a loan to the Third Avenue construction fund and authorize expenditure of $28,282 from account number 621-6211-5201 and auth- orize expenditure of $22,7,675 from account number 621-6211-5569. 2. Additional appropriations are recommended as a loan to the project to be repaid through a tax allocation bond issue. 3. Recommended source: Residential Construction Tax fund. ALTERNATIVE TWO: 1. Requires an additional appropriation of $255,957 which would be reduced to $105,239 through the execution of four change orders. Appropriate $255,957 from the Residential Construction Tax fund as a loan to the Third Avenue construction fund and authorize expenditure of $28,282 from account number 67_1-6211-5201 and auth- orize expenditure of $227,675 from account number 621-6211-5569. 2. Additional appropriations are recommended as a loan to the project to be repaid through a tax allocation bond issue. 3. Recommended source: Residential Construction Tax fund. 4. Recommended that $150,000 of CDBG funds be budgeted to FY 79-80 to complete project. 9~~ PHILLIPS-REYNOLDS ENGINEERING, INC. CIVIL ENGINEERING-LAND SURVEYING ITEM Phillips Reynolds Services Addendum No. 1 Consultant Fees + 15~ San Lo Aerial Surveys Huxley Clemons Colbourn Utility Consultants Parctec Other Charges + 15% CITY OF CHULA VISTA. TOWN CENTRE PROJECT SUMMARY OF EXTRA IrbRK AGREEMENT ACTUAL $28,632.75 1,076.25 $29,709.00 $48,928.75 DIFFERENCE CLAIM 3,381.00 3,381.00 3,800.00 16,535.40 3,850.00 1,794.00 -0- 7,890.01 2,260.00 2,362.54 $43,000.00 $80,891.70 (50% of difference) $19,219.75 $ 9,609.87 -0- 12,735.40 [2,056.00] 7,890.01 102.54 $37,891.70 -0- 12,735.40 [2,056.00] 7,890.01 102.54 $28,281.82 71 NORTH FOURTH AVENUE • CHULA VISTA, CA 92010 • PHONE 426-5400 ~ I -" ~ ~ 1 SOS __ PHILLIPS-REYNOLDS ENGINEERING, INC. ~ - CIVIL ENGINEERING-LAND SURVEYING February 7, 1979 Job No. 3333 CITY OF CHULA VISTA TOWN CENTRE PROJECT BREAKD04JN ENGINEERING SERVICES: Survey Crew 3-Man: 19.5 hrs @ $67.50/hr $ 1,316.25 Survey Crew 2-Man: 105.5 hrs @ $47.50/hr 5,011.25 Survey Supervisor: 2.0 hrs @ $22.50/hr 45.00 EDM Equipment• 17.5 hrs @ $17.50/hr 306.25 Principal: 51.25 hrs @ $30.00 1,537,50 Office Engineering: 1,072.0 hrs @ $25.00/hr 26,800.00 Engineering Aid & Drafting: 795.0 hrs @ $17.50/hr 13,912.50 Total Services ......................... $ 48,928.75 EXHIBIT ~ 71 NORTH FOURTH AVENUE • CHULA VISTA, CA 92010 • PHONE 426-5400 ,~0~ Possible Fundin4 Sources 1. Block Grant: Not available until July 1, 1979. 2. Revenue Sharing: ~rJould reguire a public hearing if more than $131,920 is expended on this project. Total unencumbered and available as of 1/31/79: $388,660. 3. Gas Tax: Portions of this project are eligible for gas tax funding - the storm drain ($61,550) and traffic signal ($23,650). Total unencumbered and available $278,594. However, there are overruns anticipated for current gas tax projects. 4. Residential Construction Tax:. Total unencumbered and available as of 1/31/79: $301,346. CIP Committee recommends use of RCT funds. Several funding alternatives using Block Grant funds are attached. The use of Block Grant funds necessitates a special bid package to meet Block Grant regulations. O PROJECT PROS CONS Let action of 2/20/79 stand - I 1. Avoids rebidding portion of 1. No absolute certainty that loan will . no change orders • 2. project. Avoids phasing of project. 2. be repaid in near future. Loan from RCT would nearly deplete • 3. Avoids rewriting of Block RCT fund. Grant. Rebid light standards and street II 1. Provides for financing por- 1. 4Ji11 actually increase project costs . furniture - contractor to purchase tion of project with Block 825) Grant ($147 2. by $23,694. Would require time and expense of and install , rebidding, preparation of plans, Estimated cost of rebid items 3 specs, etc. two hasing of project uires R . , p eq lights $121,552 (current bid price) prime contractors, administration of furniture 26,273 (current bid price) two contracts, longer construction $147,825 4. period. Block Grant application must be re- compares to $124,131 that is saved by written. eliminating these items from current 5. No certainty of bid prices. contract. III. City purchase street lights and 1. Provides for financing por- ith Block t 1. Would require time and expense of preparation of plans and rebidding street furniture and contract for w tion of projec 810) Grant ($96 , specs, etc. their installation 2 . , Savings of $27,321. 2. Requires phasing of project, two Estimated cost of rebid items . prime contractors, administration of er construction l n t g o s, two contrac Purchase light standards. $59,400 period. Install light standards 11,137 3. Block Grant application must be re- purchase furniture 26,273 written. '. $96,810 4. No certainty of bid prices. cor~pares to $124,131 savings i f these itEm~ are removed from existing contract. Savings is $27,321. Page 1 of 2 p •-- PROJECT PRns CONS jIV. City purchase street lights and street furniture and install .Estimated costs of rebid Pu~~chase light standards $59,400 Purchase furniture 26,273 Install light standards City forces $85,673 compares to $124,131 savings if re- moved from existing bid. Savings is $38,458. 1. Provides for financing por- tion of project with Block Grant ($85,673). 2. Savings of $38,458. 1. Would require time and expense of rebidding, preparation of specs, etc. Block Grant procedures require com- petitive bid. 2. Block Grant application must be re- written. 3. No certainty of bid prices. 4. Requires 4/5th's vote of City Council for City forces to perform work. 5. City forces have never performed this type of work on this scale. 6. Would remove City forces from other projects and maintenance function including traffic signal maintenance. Page 2 of 2 • ~m No. CA 102 7 -~ 6 6' CERTIFICATE OF CITY FINANCE OFFICER Certification of Unappropriated Balance I HEREBY CERTIFY that the money required for the appropriation of funds for the purpose set forth in the attached resolution is available in the Treasury, or is anticipated to come into the Treasury, and is otherwise unappropriated. Amount $ 255,957.00 Fund Residential Construction Tax Purpose Street Improvements Third Avenue, E to F Street Bidder T.B. Penick & Sons $222,675.00 621 6211 5569 ~ ~~ ~_.~ / ~ ~~ 28,282.00 621 6211 5201 _ ~ `' Finance Officer The City of Chula Vista Bate 3/5/79 By Certification of Unencumbered Balance ~C HEREBY CERTIFY that the indebtedness and oblici- ation to be incurred. by the contract or agreement auth6r- ized by t?~ie attached resolution can be incurred without the violation. of any of the provisions of the Charter of the City of_ Chula Vista, or the Constitution or the laws of_ the State of California, that sufficient monies have been appropriated for the purpose of said contract, that sufficient. monies to meet the obligations of the contract are actually in the. Treasury, or are anticipated to come into the Treasury to the credit of the appropriation from which the same are to be drawn, and that said monies now actually in the Treasury, together with the monies antic- ipated to came into the Treasury, to the credit of said appropriation are otherwise unencumbered. Amount Not to Exceed S Finance Officer The City of_ Chula Vista Date By Fund Dept./Activity Purpose Bidder Certificate No. r • CHANGE IPJ CONTRACT Y ' -~ ~; ORDER N0. Third Avenue Street Improvemerits~r DATE "E" Street to "F" Street, V J ~' ~~ Phase One CONTRACT T. B. Penick and Sons, Inc. CONTRACTOR 5-A November 21, 1979 JOB AN003 The following .change shall be made to increase the contract dated March 19. 1979 , between the City of Chula Vista and T. B. Penick"& Sons, Inc. , Contractor. REMARKS AND DETAILS: Modify Change Order Pd o.5 to reflect actual c.rees placed in storage at Rohr Park as directed by the City Landscape Architect. Change Order No. 5 was based on the deletion of five (5) 24" box trees and one (1) 30" box tree. The actual deletion was three (3) 24" box trees and two (2) 30" box trees. The proper amount of credit is therefore $275.00, not $400.00 as per Change Order No. 5. Difference to be added - $125.00. ORIGINAL CONTRACT PRICE $ 690,714.01 Previous Change Order Nos. $ 867.30 Revised Total. Contract Price $ 691,,581.31 This Change Order No. 5-A $ 125.00 It is agreed by the undersigned that all extra work shall be performed and materials furnished in accordance with the original contract and in accordance with the statement, if any, attached hereto. TOTAL CONTRACT $ 691,706.31 APPROVED BY: .John P. Lippitt d" ACCEPTED BY: ~ ORDERED BY: T. B. Penick & Sons, Inch Kenne~,~3~. Golf;kamp THOMAS L . Y~;N pR~SID~l`1T " ~PW-E-4 4 ~ - ~S O S ~ 50.5 . r ORDER NO. 7 CHANGE IP1 CONTRACT Third Avenue Street Improvements, Phase 1, "E" St. to "F" St•CONTRACT T. B. Penick and Sons, Inc.CONTRACTOR DATE December 11, 1979 JOB AIJ-003 The following change shall be made to increase the contract dated March 19, 1979 , between the City of Chula Vista and T. B. Penick and Sons, Inc. , Contractor. REMARKS AND DETAILS: TOTAL $849.23 ORIGINAL CONTRACT PRICE $ 690,714.01 Previous Change Order Nos. $ 992.30 Revised Total. Contract Price $ 691,706.31 This Change Order No. _7 $ 849.23 It is agreed by the undersigned that all extra work shall be performed and materials furnished in accordance with the original contract and in accordance with the statement, if any, attached hereto. TOTAL CONTRACT $ 692,555.54 APPROVED BY: ACCEPTED BY. ORDERED BY: o n Lippitt C'ty Engineer T. B enick & c By: ~ Kenneth J Goldk p S Civ' r PW-E-44 Replacement of Plant Material destroyed by vandalism during. Yuletime Parade. $371.00 Repair of Traffic Signal Telemetry System at the Intersection of Third Avenue and "F" Street, Conduit not shown on plans and only 6" below pavement surface. $478.23 SoS ~~/ CHANGE IP7 CONTRACT Third Avenue Street Improvements Phase One, "E" Street to "F" Street CONTRACT T. B. Penick and Sons, Inc. CONTRACTOR ORDER NO. SIX DATE October 10, 1979 JOB aN-003 The following .change shall be made to increase the contract dated March 19, 1979 , between the City of Chula Vista and T. B. Penick and Sons, Inc. , Contractor. REMARKS AND DETAILS; Construct .seven wood trellises with full 3" x 6" lath hangers running continuously across the beams on 8" centers. Contractor to furnish all labor and City is to pay for redwood material, detailing and submersion of the redwood in woodlife for a period of 4 minutes. Lump Sum Payment $2,968.00 ORIGINAL CONTRACT PRICE Previous Change Order Nos. Revised Total. Contract Price "~~"~ $ 690,714.01 / $ - 2,100.70 ,, $ 688,613.31 ~ This Change Order No. 6 $ 2,968.00 It is agreed by the undersigned that all extra work shall be performed and materials furnished in accordance with the original contract and in accordance with the statement, if any, attached hereto. TOTAL CONTRACT $ 691,581.31 APPROVED BY: ACCEPTED BY: ORDERED BY: City Council Resolutio No. 799 d ted 10 9 79 T. B. enick and Son B c. Kenn th J. Goldkamp S eer PW-E-44 %~ G' -~~ sus- ,