HomeMy WebLinkAboutAgenda Statement 1979/02/13 Item 10CITY OF CHULA VISTA
COUNCIL AGENDA STATEMENT
Item No. 10
For meeting of 2/13/79
ITEM TITLE Resolution ! Y` / ~ Granting a 75-day Extension for the Installation
of Traffic Signals on Telegraph Canyon Road at Paseo del Rey and
at Brandywine Avenue
SUBMITTED BY City Engineer: via Director of Public Works ~ ~;
v
ITEM EXPLANATION
(4/5TH'S VOTE REQUIRED YES NO x )
On December 19, 1978, the City Council granted an extension to
February 15, 1979, of the contract with Perry Electric Company to
install traffic signals on Telegraph Canyon Road at Paseo del Rey
and at Brandywine Avenue. The signals are being built in conjunction
with improvements to Telegraph Canyon Road being constructed by
Gersten Company as part of El Rancho del Rey No. 5 and the signals
cannot be completed until the road work is finished. Due to delays
from material and construction problems and inclement weather, completion
of the roadway is now scheduled for March 1979.
It is trierefore recommended that a 75-day extension be granted to
Perry Electric (last day May 1, 1979) to complete this project.
GRH:nr/BR-002
rviirnrTn
tJ~ ty 1151 I J
Agreement Resolution x Ordinance Plat Notification List
Other ENVIRONMENTAL DOCUMENT: Attached Submitted on
FINANCIAL IMPACT
None
STAFF RECOMMENDATION
Approve resolution.
BOARD/COMMISSION RECOMMENDATION
COUNCIL ACTION