HomeMy WebLinkAboutAgenda Statement 1979/02/06 Item 08' CITY OF CHULA VISTA
COUNCIL AGENDA STATEMENT Item No. 8
For meeting of 2/6/79
ITEM TITLE Resolution 9~ ~) Granting a 10 Day Extension of Contract to Complete the Civic
Center Renovation Project
SUBMITTED BY Director of Building and Housing
ITEM EXPLANATION (4/5TH'S VOTE RE UIRED YES. NO X )
From January 5, 1979 through January 19, 1979 unusual rain, wet and muddy job site prevented
the contractor from performing work on the exterior of the building, resulting in a delay
of completion of the total project.
Robert G. Fisher Company is requesting a 10 day extension of their contract. With the 64
day extension granted by the City Council on P1arch 14, 1978, the 10 days granted on April
11, 1978, the 28 days granted on January 1, 1979 and this 10 day extension will extend the
completion date to and until February 14, 1979.
1. Original contract completion date October 23, 1978
2. 64 day extension changed completion date to December 26 ,1978
3. 10 day extension changed completion date to January 5, 1979
4. 28 day extension changed completion date to February 4, 1979
5. Requested 10 day extension will change completion date to February 14, 1979
The 10 day extension requested has been confirmed by Al O'Day, the City's Project
Representative, as being justifiable.
EJG:br
tXNlli115 --
Agreement Resolution X Ordinance Plat Notification List
Other ENVIRONMENTAL DOCUMENT: Attached Submitted on
FINANCIAL IMPACT
None
STAFF RECOMMENDATION
Approve resolution granting extension of contract to complete the Civic Center renovation
project.