Loading...
HomeMy WebLinkAboutAgenda Statement 1986/12/16 Item 13'~ COUNCIL AGENDA STATEMENT Item 13 Meeting Date 12/16/86 ITEM TITLE: Resolution /~~.~ ~ Accepting contract work, street light installation on Third Avenue from "L" Street to Hermosa Avenue and authorizing the transfer of funds betwee Gas Tax projects SUBMITTED BY: Director of Public Works/City Engineer REVIEWED BY: City Manager (4/5ths Vote: Yes No X Undergrounding of all utilities on Third Avenue between "L" Street and Hermosa Avenue was approved by the County of San Diego and City of Chula Vista prior to the Montgomery area annexation. The removal of the wooden power poles, which were used to support street lights, required that a new, uniform lighting system be installed to illuminate the street. The City awarded two contracts to replace the street lights on Third Avenue from "L" Street to Hermosa Avenue. The first contract was awarded to Maco Electric Services and exter~ied from "L" Street to Palomar Street. The second contract was awarded to Bonita Electric and extended from Palomar Street to Hermosa Avenue. Both contractors have now completed their respective work. RECOMMENDATION: That Council adopt a resolution: 1. Accepting the contract work, street light installation on Third Avenue from "L" Street to Hermosa Avenue. 2. Authorizing the transfer of $1,153 from the fund balance of Phase II to Phase I of the project. BOARDS/COMMISSIONS RECOMMENDATION: Not applicable. DISCUSSION: Prior to the Montgomery area annexation, the County of San Diego initiated a utility undergrounding project. In conjunction with this project, the County appropriated $60,000 to cover its cost to replace the street lights that were on the wooden utility poles being removed. After the annexation, the County transferred the $60,000 to the City for installation of the new street light system. The $60,000, however, only covered the cost of installing 24 lights and standards on Third Avenue from "L" Street to Palomar Street. The installation of the street lights was therefore separated into two phases. Phase I was for the "L" Street to Palomar Street portion and Phase II was for the Palomar Street to Hermosa Avenue portion. Page 2, Item 13 Meeting Date~Jl~jfl6 Phase I was awarded to Maco Services, Inc. by Council Resolution No. 12536 dated June 17, 1986. The contract amount was for $55,555 and had a completion date of August 26, 1986. Three change orders were subsequently approved increasing the contract amount by $4,550 and extending the completion date by 15 days to September 18, 1986. The contract had estimated the length of conduit needed for the project to be about 3,500 LF. The actual length of condo+it installed was 3,679 linear feet, increasing the contract by $1,047.15 (179 LF x $5,85/LF). Thus, the contract amount increased by $5,597.15 ($4,550 + $1,047.15) to a total of $61,152.15. The change orders were as follows: Change Order No. Reason Extension Amount Time 1 Installation of meter pedestals $3,500 10 days 2 Re-excavate conflicting foundation 100 0 3 Install 1351.E of rigid conduit 950 5 Maco Services, Inc., was unable to complete their work within the contract time due to an overhead conflict with energized SDG&E lines. The utility company was unable to remove these lines due to delays in the conversion of the private services by several affected property owners. Since the conversion district was under the County of San Diego jurisdiction, we had no control on the timing of its completion. We agreed, however, with the contractor to provide him five days to complete his work after SDG&E removed the conflicting lines. All other work has now been completed to the satisfaction of the City Engineer and we recommend acceptance of the contract work. Phase II was awarded to Bonita Electric by Council Resolution No. 12669 dated August 12, 1986. The contract amount was for $66,221.31 and had a completion date of October 16, 1986. An extension of contract time of 20 working days was granted by Council on October 14, 1986 by Resolution No. 12771. The completion date was extended to November 14, 1986. Bonita Electric, however, experienced the same delay problem as Maco Services, Inc. due to the difficulty in getting all property owners in the conversion district to covert their private service laterals. Both contractors were unable to erect the street lights standards until SDG&E was able to remove the conflicting overhead lines. Bonita Electric has now completed all their work to the satisfaction of the City Engineer and we recommend acceptance of the contract work. The final cost for Phase I was $1,152.15 over the authorized expenditure due to an increase in the actual conduit installed and three change orders. Fortunately, the final cost for Phase II of the project was $9,430.98 less than the authorized expenditure (see Fiscal Impact). We, therefore, recommend that Council authorize the transfer of $1,152.15 from the fund balance of Phase II (Account 250-2501-GT214) to Phase I (Account 250-2501-GT206) to cover the deficit. Page 3, Item 13 Meeting Date 1~7~6 FISCAL IMPACT: Phase I - Third Avenue, "L" Street to Palomar Street, Maco Services, Inc., Contractor Authorized Expenditures (Account 250-2501-GT206) $60,000.00 Original contract cost $55,555.00 Final contract cost 61,152.15 61,152.15 Balance of Authorized Expenditures ($ 1,152.15) Phase II - Third Avenue, Palomar Street to Hermosa Avenue, Bonita Electric, Contractor Authorized Expenditure (Account 250-2501-GT214) $66,221.31 Original contract cost $60,201.21 Final contract cost 56,790.33 56,790.33 Balance of Authorized Expenditures $9,430.98 A transfer of $1,153 will be made from Phase II (GT214) to Phase I (GT206) to cover the deficit for its contract as shown above. RS/mag WPC 2501E y the City Council of Chula Vista, California Dated