HomeMy WebLinkAboutAgenda Statement 1979/01/09 Item 08CITY OF CHULA VISTA
COUNCIL AGENDA STATEMENT
Item No. 8
For meeting of 1/9 /79
ITEM TITLE Resolution 9 ~J-Granting a 28-day Extension of Contract to Complete the Civic
Center Renovation Project
SUBMITTED BY Director of Building and Housing
ITEM EXPLANATION
(4/5TH'S VOTE REQUIRED YES N0~)
From November 10 through November 17 and November 22 through November 30, 1978 and December 1,
1978 and December 16 through December 27, 1978 unusual rain, wet and muddy jobsite prevented
the contractor from performing work on the exterior of the building, resulting in a delay in
completion of the project.
Robert G. Fisher Company is requesting a 28 day extension of their contract. With the 64
day extension granted by the City Council on March 14, 1978 and the 10 days granted on
March 11, 1978, this 28 day extension will extend the completion date to and until February 8,
1979.
1. Original contract completion date October 23, 1978
2. 64 day extension changed completion date to December 26, 1978
3. 10 day extension changed completion date to January 9, 1979
4. Requested 28 day extension will change completion date to February 8, 1979
The 28 day extension requested has been confirmed by Al O'Day, the City's Project
Representative as being ,justifiable.
EJG:br
Agreement
Resolution X
EXHIBITS
Ordinance
Plat Notification List
Other ENVIRONMENTAL DOCUMENT: Attached Submitted on
FINANCIAL IMPACT
STAFF RECOMMENDATION
N.A.
Approve resolution granting extension of contract to complete the Civic Center renovation
project.