HomeMy WebLinkAboutAgenda statement 1982/01/12 Item 11COUNCIL AGENDA STATEMENT
Item 11
Meeting Date 1/12/82
ITEM TIT E: Resolution~p'~jC~ Authorizing the Granting of an Easement for
Underground Electrical Lines Located in Memorial Park
SUBMITTE BY: Community Development Director (4/5ths Vote: Yes No X )
In Ja uary 1980, the Redevelopment Agency adopted Resolution No. 230 stating a desire
to la dscape and improve the eastern portion of Memorial Park fronting on Third
Avenu The landscaping plan has been finalized, but to complete the park enhancement
progr m a plan for the conversion of overhead utilities has been prepared. Also,
this lan (Attachment I) will aid in the removal of overhead utilities within the
Town entre Focus Area 4vithoutrequiring any expensive undergrounding. Therefore, it
is my
RECOMMENDATION: That the Council
Adopt the attached resolution granting an easement which is necessary to convert over-
head lectric lines located within Memorial Park.
/COMMISSIONS RECOMMENDATION:
DISCUSSION:
Not applicable.
The fu ds and easement document will be submitted to the San Diego Gas & Electric
Compan Once the utility company receives those items, the park conversion, a four
to six week construction project, can be scheduled. In this conversion, the electrical
servic route for the Memorial Bowl will be changed from overhead lines situated on
Landis Avenue to an underground route from the Senior Center building. This will allow
the re oval of the poles on Landis Avenue which are in the Focus Area. It is antici-
pated hat the overhead lines within Memorial Park and the Town Centre Focus Area will
all be removed by the first of April by SDG&E and Pacific Telephone.
To dat the Memorial Park project has been allocated $90,979.35 of Block Grant funds,
and $1 1,192 of Redevelopment Agency funds. Of these amounts, $1,681.70 in Block
Grants and $22,646.30 of Agency funds are available for this project.
FINANC AL IMPACT:
$ 4,500 - Cost of removing existing overhead facilities in Memorial Park
(pay to San Diego Gas & Electric Company)
3,300 - 400 amp, load service center, conductor and other materials
2,000 - Labor (City forces)
200 - Contingencies
-, ~.~~.~~~~ d,_~:._vw.~~ts..
$ 0,000 TOTAL COST """'-'"' " ~~.`~~~~n~~.M
PRB:AK :ah ,, . __,...__,..._.. _.
Form A-113 (Rev. 11/79)