HomeMy WebLinkAboutAgenda Statement 1979/04/10 Item 08. CITY OF CHULA VISTA
COUNCIL AGENDA STATEMENT
Item~Vo. $
For meeting of 4/10/79
ITEM TIifLE
SUBMITTED BY
ITEM
Resolution 9s~3 Granting an Extension of Time for the
Construction of Curbs, Gutters, Sidewalks, Cross-Gutters,
and Wheelchair Ramps, Town Centre Area
City Engineer
LANATION (4/5TH'S VOTE REQUIRED YES NO x )
L. R. Hubbard, Jr., contractor for the construction of the Town
Ce tre Area concrete work has requested an extension of his contract
ti e to complete the project. His contract time expired on March 23,
19 9. He had 30 working days to complete the project. The contractor
st tes that the reason for their request is delay due to rainy weather.
Th Engineering staff has reviewed the request for a time extension
an has determined that a total of 14 working days were lost because
of rain. Engineering staff recommends a 14 working day extension
of contract time. The contract, dated January 30, 1979, with the
ap roval of 14 working days will extend the contract completion date
to April 12, 1979.
:fpw/AX-042, AP-011
t Resolution x
EXHIBITS
Ordinance Plat Notification List
er ENVIRONMENTAL DOCUMENT: Attached Submitted on
FINANCIAL IMPACT
N/:
STAFF REICOMMENDATION
pt resolution granting a 14 working day extension of time and
nging contract completion date to April 12, 1979.
BOARD/C0~IMISSION RECOMMENDATION
COUNCIL CTION
q~f 5 3
Office of
JENNIE M FULASZ, CITY CLERK
Date:
To.
~~~..-~
City o~ C~nu.Qa ~Uista
CALIFORNIA
Subject: ( ) Resolution No. ( ) Ordinance No.
You will find enclosed a certified copy of the City Council
document approved at the meeting of
JENNIE M. FULASZ, C?dC
City Clerk
Enclosures
( ) STAR NBwS: P.2ea~e pub.~i/~h ~h,i~s dacumev~t an
anal send c.~ a copy ~atc awc Und~.nance Boa .
( ) RBCORD~R: P.~ecvse necotcd ~a~.d dacumen~ and netwcn -ct ~o u~5 a~ yaws
ea~r.?.i.e~~ canven,~.ence.
276 Fourth Avenue, Chula Vista, CA 92010 (714)575-5041 CC-685 (Rev. 10/77)