COUNCIL AGENDA STATEMENT
Item g
Meeting Date 6/14/88
ITEM TITLE: Resolution,~~d~ Accepting bids and awarding contract
for "Construction of Central Basin Drainage Channel East and
West of Fifth Avenue between 'F' and 'G' Streets in the .City
of Chula Vista, CA"G~
SUBMITTED BY: Director of Public Works
REVIEWED BY: City Manager (4/5ths Vote: Yes No X )
At 2:00 p.m. on May 11, 1988, in Conference Room 2 in the Public Services
Building, the Director of Public Works received sealed bids for "Construction
of Central Basin Drainage Channel East and West of Fifth Avenue between 'F'
and 'G' Streets in the City of Chula Vista, CA." The project involves removal
and disposal of existing improvements, clearing and grubbing, drainage
control, catch basins, various sizes of pipe, transition structure, chain link
fencing and gate, A.C. berm and Alternate A (reinforced concrete rectangular
channel) and/or Alternate B (10'x4-1/2' reinforced concrete box), and other
miscellaneous work shown on the plans. Funds for this project were budgeted
" FY 1984-85.
ttached is a sketch showing the general location of the work to be
accomplished.
RECOMMENDATION: That Council accept bids and award contract to Commercial
Contractors, Inc. for the construction of Alternate A (reinforced concrete
rectangular channel) in the amount of $218,184.73.
BOARDS/COMMISSIONS RECOMMENDATION: Not applicable.
DISCUSSION:
Bids were received from six contractors as follows:
Alt. A
Reinforced Alt. B
concrete Reinforced
rectangular concrete
Bidder channel box culvert
1. Commercial Contractors, Inc. - San Diego $218,184.73 $251,176.60
2. Carolyn E. Scheidel Contractor - La Mesa 225,968.00 290,396.00
3. Erreca's Inc. - Spring Valley 227,000.00 No bid
4. Stone Construction - Yucca Valley 248,824.00 293,502.00
5. Roca Construction Inc. - Chula Vista 274,853.20 341,280.00
• Sapper Construction Co. - San Diego 299,153.00 354,800.00
/~3 ~ ~~
Page 2, Item 9
. Meeting Date$
Staff bid two alternates on this project, both of which satisfactorily handle
the expected drainage flows. If there had only been a slight difference in
the cost between Alternate A and B, staff would have recommended the
construction of a reinforced concrete box culvert. However, the minor savings
in maintenance costs for a box culvert does not justify the added expenditure
of approximately $33,000 in construction cost. Therefore, staff recommends
that Alternate A (reinforced concrete rectangular channel) be constructed.
The Deputy Director of Public Works/Operations concurs with this
recommendation.
It may be advantageous to cover the channel for use by property owners. Where
feasible, staff will be contacting property owners to see if they want the box
culvert versus the open channel. If so, a change order will be prepared for
the difference in cost between the open channel section and the box culvert
with the property owner paying the difference.
The low bid by Commercial Contractors Inc. for Alternate A is below the
Engineer's estimate of $230,336.00 by $12,151.27 or 5 percent. We have
reviewed the low bid and believe it to be satisfactory and recommend awarding
the contract to Commercial Contractors Inc.
This project is being funded by Community Block Grant Funds and included in
e specification documents are goals for meeting the City of Chula Vista
firmative Action Program. The pre-award conference was held with the
ontractor on Friday, May 20 to review his employment and contracting plan for
meeting the goals in this program. Staff believes the contractor has made a
satisfactory effort for meeting the Affirmative Action Program of the City of
Chula Vista.
The Department of Housing and Urban Development has reviewed this contractor's
eligibility to perform the work. We have received assurances that this
contractor is eligible.
Attached is a copy of the Contractor's disclosure statement.
FINANCIAL STATEMENT:
Funds ReQUired for Construction
a. Contract Amount $218,184.73
b. Contingencies (approx. 5~) 10,866.42
Total Funds Required for Construction $229,051.15
Funds Available for Construction
a. Central Drainage Basin Channel $229,051.15 /3 CF`.~~
~SCAL IMPACT: None.
WPC 3776E
the City Council of
Chula Vista, Ca 'fornia
Dated ~
--
~~~ ~j
~~
• CIN OF
CHULA VISTA
DEPARTMENT OF PUBLIC WORKS
ENGINEERING DIVISION
September 14, 1988
File # AO-043
Commercial Contractors, Inc.
P.O. Box 23076
San Diego, CA 92123
Attention: Mr. Bill Zondorak
CENTRAL BASIN DRAINAGE CHANNEL - CHANGE ORDER NO. 1
Enclosed is a fully executed copy of change order no. 1 for the
Central Basin Drainage Channel project.
We appreciate your cooperation. If you have any questions
regarding this matter please call Mr. Roberto Saucedo of my staff
• at 6~/~~3.~I /1 /~~
(L\CONTRACTS\CHNGODR.DOC.)
cc: City Clerk (Resolution No. 13609)
Lyman Christopher (P.O. 185923)
Tomme Lutz, Project Inspector
•
/~~G~j~~
276 FOURTH AVENUE/CHULA VISTA, CALIFORNIA 92010/(619) 691-5021
Enclosure
R
• CHANGE IN CONTRACT
ORDER N0. One
DATE: August 16, 1988
FILE: AO-0043
CONTRACT: Central Basin Drainage Channel East and West of
Fifth Avenue Between "F" and "G" Streets
CONTRACTOR: Commercial Contractors, Inc.
The following change shall be made to increase the contract dated
August 1, 1988, between the City of Chula Vista and Commerical
Contractors, Inc., Contractor.
REMARKS AND DETAILS: Change in plans and specifications
requested by the City at an agreed cost (shown below) to cover
the open channel between stations 0+00 and 0+87.02 (West of Fifth
Avenue) and between Stations 0+80 +/- (East of Fifth Avenue).
I - West of Fifth Avenue (J. E. Whittingham's property)
a) delete item 16 -
• 87 LF of 10'x5' Reinforced Rectanguler Channel
at $ 207.59/LF = - $ 18,060.33
b) Add item 22 -
87 LF of 10'x4.5' RCB per RSD D-76 at $ 325.29
(original bid of $ 286.00/LF plus $ 3,417.82 per
letter dated 28, July 88) _ + $ 28,299.82
Subtotal I = + $ 10,239.49
II. East of Fifth Avenue (D.B. Stanley's property)
a) Revise bid item 15
Subtract 80 LF of 10'x5'4" Reinforced Rectangular
Channel at $ 208.50/LF = - $ 16,680.00
b) Add item 23
80 LF of 10'x4.5' RCB per RSD D-76 at $326.86
(original bid of $ 286.00/LF plus $3268.80 per letter
dated 28, July 88) _ + $ 26,148.80
c) add item 24
Remove block wall and place fill to level ground
at lump sum of $ 1808.
• Subtotal II + $ 11,276.80
Total Net Change + $ 21,516.29
/ ~~~. 4
•
ORIGINAL CONTRACT PRICE $ 218,184.73
Previous Change Order Nos. $ - 0 -
Revised Total Contract Price $ 218,184.73
This Change Order No. 1 $ 21,516.29
It is agreed by the undersigned that all extra work shall be
performed and materials labor and equipment furnished in
accordance with the original contract and in accordance with the
statement, if any, attached hereto. Contract shall be extended
60 working days to provide sufficient time for the completion of
the work.
TOTAL CONTRACT
APPROVED BY:
$ 239,701.02
ORDERED BY:
~bIRECTOR OF PUBLIC COMMERCIAL CONTRACTORS D,~. DIR. OF
. WORKS INCORPORATED PUBLIC WORKS/
CITY ENGINEER
(L\CONTRACT\CHNGODRI.DOC)
.,
,.
~~~ /~
~~~~
• CITY OF
CHULA VISTA
DEPARTMENT OF PUBLIC WORKS
ENGINEERING DIVISION
October 14, 1988
File # AO-043
Commercial Contractors, Inc.
P.O. Box 23076
San Diego, CA 92123
Attention: Mr. Bill Zondorak
CENTRAL BASIN DRAINAGE CHANNEL - CHANGE ORDER NO. 2
Enclosed is a fully executed copy of change order no. 2 for the
Central Basin Drainage Channel project.
We appreciate your cooperation. If you have any questions
regarding this matter please call Mr. Roberto Saucedo of my staff
at 691-5023.
• /A
~ //~^
KENNETH J. GOLDKAMP
SENIOR CIVIL ENGINEER
RS:ljr
Enclosure
(L\CONTRACTS\CHNGODR.DOC.)
cc: City Clerk (Resolution No. 13609)
Lyman Christopher (P.O. 185923)
Tomme Lutz, Project Inspector
•
276 FOURTH AVENUE/CHULA VISTA, CALIFORNIA 92010/(619) 691-5021
~.
! ~, ...,
• CHANGE IN CONTRACT
ORDER NO. Two
DATE: September 29, 1988
FILE: AO-043
CONTRACT: Central Basin Drainage Channel East and West of
Fifth Avenue between F and G Streets
CONTRACTOR: Commercial Contractor's Inc.
The following change shall be made to increase the contract dated
August 1, 1988, between the City of Chula Vista and Commercial
Contractors, Inc., Contractor.
REMARKS AND DETAILS: Change in plans and specifications
requested by the City of Chula Vista at our agreed cost:
1. Place 1 1/2" rock in areas over excavated due to poor
subgrade material at an agreed unit cost of
$22.42/cubic yard. Amount placed totaled 126.34 tons
of 1 1/2" rock, or 90.5 cubic yards (126.34 tons/1.4
cubic yards/ton). Total cost for this work amounts to
$ 2,029.00 ($22.42/CY x 90.5 CY).
• The agreed price of $2,029.00 is considered to be full
cost for furnishing all tools, labor, material and
equipment for doing the above work and no additional
compensation will be due.
ORIGINAL CONTRACT PRICE $ 218,184.73
Previous Change Order Nos. $ 1
Revised Total Contract Price $ 239,701.02
This Change Order No. 2 $ 2029.00
It is agreed by the undersigned that all extra work shall be
performed and materials furnished in accordance with the
original contract and in accordance with the statement, if any,
attached hereto.
TOTAL CONTRACT
$ 241 30.02
A~ ROVED B~: ` ~f2SL~p~ED~w ~/ ORDERED~~Y:
• DIRECTOR OF PUBLIC COMMERCIAL CONTRACTORS ~. DIR. OF
WORKS INCORPORATED PUBLIC WORKS/
CITY ENGINEER
(L\CONTRACT\CHNGODIO.DOC)