HomeMy WebLinkAboutAgenda Statement 1988/04/05 Item 12• COUNCIL AGENDA STATEMENT
• Item 1'
Meeting Date 4/5/88
ITEM TITLE: Resolution/~yy~ Accepting contract work, traffic signal
installations at Hilltop Drive/Quint rd Street and Orange
Avenue/Second Avenue in the City of Ch a Vista
SUBMITTED BY: Director of Public Works ~~'"
REVIEWED BY: City Managers ~ ~ (4/5ths Vote: Yes No X )
~~
On November 17, 1987, the City Council by Resolution No. 13337, awarded a
contract for traffic signal installations at Hilltop Drive/Quintard Street and
Orange Avenue/Second Avenue to Steiny and Company, Inc. the work is now
completed.
RECOMMENDATION: That Council approve a resolution accepting the contract
work.
BOARDS/COMMISSIONS RECOMMENDATION: Not applicable.
DISCUSSION:
• Steiny and Company, Inc. completed the installation of the traffic signals at
the Hilltop Drive/Quintard Street and Orange Avenue/Second Avenue intersection
on March 7, 1988. A final inspection was made on March 11, 1988, and all work
was found to be completed in accordance with the contract plans and
specifications and to the satisfaction of the City Engineer.
FINANCIAL STATEMENT:
Budgeted Amount - Construction
Authorized Expenditure - Construction
Steiny & Company, Inc.
($74,945.00 original contract + contingencies)
Purchase of equipment by City
Final Expenditure
Steiny & Company, Inc.
Purchase of equipment by City
$129,200.00
$82,440.00
12,089.50
$94,529.50
$74,945.00
12,089.50
$87,034.50
•
•
•
Balance of Authorized Construction Expenditure
($94,529.50 minus $87,034.50)
Balance of Budgeted Construction Funds
($129,200.00 minus $87,034.50)
Page 2, Item 1 2
Meeting Date~57$$-
$7,495.00
$42,165.50
Staff time from point of inception to February 25, 1988
$9,504.89 x 2.238 (full cost recovery factor) $21,271.94
FISCAL IMPACT: In addition to construction cost summarized above, the City
will maintain the traffic signals.
RS:fp/BR015, BR018
WPC 3654E