HomeMy WebLinkAboutAgenda Statement 1987/09/08 Item 8CITY COUNCIL AGENDA STATEMENT
• Item g
Meeting Date 9/8/87
ITEM TITLE: RESOLUTION ~~~ Ad6 tin the Record of Decision and the
P 9
Supplemental EIS for the Telegraph Canyon Flood Control
Project
SUBMITTED BY: Community Development Director
REVIEWED BY: City Manage (4/5ths Vote: YES_NO X )
In January, 1986 Council adopted the Final Environmental Impact Statement (FEIS)
prepared by the U.S. Army Corps of Engineers for the Telegraph Canyon Flood
Control Project. A supplement to the FEIS was adopted by the Corps in March,
1987 to reflect a proposed realignment of the drainage channel for the project.
The City has budgeted $1,184,000 in Community Development Block Grant (CDBG)
funds to be applied as part of the City's participation in the project. Prior
to securing the release of the CDBG funds by the U.S. Department of Housing
and Urban Development (HUD), the City must adopt the complete environmental
assessment of the project.
RECOMMENDATION: That the Council adopt the Record of Decision and the
Supplemental EIS for the Telegraph Conyon Flood Control Project.
• BOARDS/COMMISSIONS RECOMMENDATION: The EIS Record of Decision and Supplemental
EIS have been approved by the Army Corps of Engineers.
DISCUSSION:
HUD Rules and Regulations require that, for any CDBG funded project which may
have a significant impact on the environment, an EIS must be adopted by the
funded agency prior to the release of funds.
The lead agency for the Telegraph Canyon Creek Flood Control Project is the
U.S. Army Corps of Engineers, who prepared the EIS and adopted it in July,
1983. The City has assisted in development of the EIS and Council certified
the Final EIS for the project in January, 1986.
A supplemental EIS for the project has been prepared and adopted by the Army
Corps to reflect a change in alignment for the drainage channel. The supple-
mental EIS is attached. As originally proposed, the drainage channel would
have split several private land parcels, preventing public right-of-way access.
The realigned channel more closely follows property boundaries and prevents
lot splits and relocation of current site occupants. The Army Corps, in the
supplemental EIS, concludes that no significant impacts on the human or physical
environment occur as a result of the realigned channel.
The new area to be impacted by the project, as a result of the channel realign-
ment, is an urbanized area between Arizona Street and Moss Street stretching
• from approximately 200 feet east of Broadway to approximately 200 feet east
Page 2, Item 8
Meeting Date 9/8/87
• of Industrial Boulevard. The new channel will lie up to 300 feet south of
the existing channel. Dirt excavated from the new channel will be used to
fill in the existing creekbed that will no longer be used.
A Record of Decision has been prepared and approved by the Army Corps and it
details the program of monitoring and implementing the mitigation measures
identified in the EIS. The Record of Decision is also attached.
FISCAL IMPACT: With approval of this item the City can request release of
$1,184,000 in CDBG funds to be applied to the Telegraph Canyon Flood Control
Project.
• y the City Council of
Chula Vista, Ca)ifornia
Dated
•
~ !~',~"