COUNCIL AGENDA STATEMENT
Item 6
Meeting Date 9/1/87
ITEM TITLE:
SUBMITTED BY:
REVIEWED BY:
Resolution /~oz~ ~ Accepting bids and awarding contract
for traffic signal modifications on Bonita Road at I-805
southbound ramps, island reconstruction and restriping of the
traffic lanes in the City of Chula Vista, California and
appropriating $57,000 from the General Fund to cover the above
construction contract amount in f 1 as a loan
Director of Public Works/City ngineer
City ManagerQ/
(4/5ths Vote: Yes X No
At 2:00 p.m. on August 19, 1987, i n Conference Room 5 of the Publ i c Services
Building, the city Engineer received sealed bids for traffic signal
modifications at Bonita Road/I-805 southbound ramps and island reconstruction
and providing for double left turn lanes for southbound on-ramp. Bids were
received from two (2) electrical contractors to modify the intersection.
RECOMMENDATION: That Council accept the bids and award the contract to
Steiny and Company i n the amount of $113, 217 and appropriate $57,000 from the
General Fund.
BOARDS/COMMISSIONS RECOMMENDATION: Not applicable.
DISCUSSION:
On June 23, 1987, Council entered into a cooperative agreement with CalTrans
for the installation of traffic signals and roadwork at the intersection of
Bonita Road and Interstate route 805. Chula Vista agreed to administer the
contract and invoice Cal Trans for 50~ of the total cost less the cost Cal Trans
expended for design. Upon completion of the project an accounting will be
completed and CalTrans and Chula Vista will be responsible for 50~ of the
total cost including construction and staff costs. National City has agreed
to pay $30,000 to Chula Vista.
Bids were received from two contractors as follows:
1. Steiny and Company - San Diego
2. M.C.R. Electric - Imperial Beach
$113,217
117,801
The low bid by Steiny and Company was slightly above the Cal Trans estimate of
$112,000. We have reviewed the low bid and believe it to be satisfactory and
recommend awarding the contract to Steiny and Company.
•
Page 2, Item 6
• Meeting Date 9/ /87
Since we do not expect to receive the $30,000 from National City or the State
of California share until after the project is awarded we need to appropriate
additional funds of $57,000 to cover the full contract amount.
When we receive the funds from National City and the State of California, the
General Fund will be reimbursed the $57,000.
FINANCIAL STATEMENT:
Total Funds Needed:
Contract Amount $113,217
Contingencies (5%) 5,660
Chula Vista Staff 3,000
$121,877
Amount Already Funded -65,000
Additional Amount Required $ 56,877
•
Total Project Cost $170,277
CalTrans Share (50°~) 85,140
National City Share 30,000
City Contribution $ 55,140
City will receive at a later date
from CalTrans and National City __66_740
FISCAL IMPACT: Routine maintenance and energy cost to be paid by CalTrans.
CalTrans bills us for our share.
MJD:nr/