Loading...
HomeMy WebLinkAboutAgenda Statement 1987/09/01 Item 5COUNCIL AGENDA STATEMENT • Item 5 Meeting Date 9/1/87 ITEM TITLE: Resolution~,3~~-~ Approving extension of contract time for the traffic signal modifications at Third Avenue/"E" Street and Fourth Avenue/"E" StreetG~ SUBMITTED BY: Director of Public Works/City Engineer REVIEWED BY: City Manage (4/5ths Vote: Yes No X ) On June 23, 1987, the City Council by Resolution No. 13094 approved awarded a contract for the traffic signal modifications at Third Avenue/"E" Street and Fourth Avenue/"E" Street to Select Electric, Inc. The contract expires on September 16, 1987. The contractor has notified us of a material delivery delay problem and has requested a contract time extension of 20 working days (see letter dated August 17, 1987). We concur with the contractor's request. RECOMMENDATION: That Council adopt a resolution approving extension of contract time to October 20, 1987. • BOARDS/COMMISSIONS RECOMMENDATION: Not applicable. DISCUSSION: Select Electric, Inc. has requested a contract time extension of 20 working days due to a material delivery delay problem. Their supplier, Coast Electric Company, advised Select Electric that the sole source of the type G pedestrian signals will not be ready to ship the material until the week of September 25, 1987 (see letter dated August 13, 1987). Select Electric is continuing work of the project and will require about 10 to 15 working days to complete the installations once the pedestrian signals are received. Staff, therefore, recommends that the 20 working day extension they requested be approved. The contractor has worked diligently and is expected to complete the project within the time extension period. FISCAL IMPACT: None. RS/mag:BR016/BR017 WPC 3130E !~ the Clty COU11C11 Of • Chufa Vis ,California Dated