HomeMy WebLinkAboutAgenda Statement 1981/09/22 Item 16
COUNCIL AGENDA STATEMENT
Item ~ 1 ~
/ Meeting Date A~-~2-81
ITEM TITLE: Resolution 106.3, Approving extension of time, Chula
Vista Transit Cent r
SUBMITTED BY: City Engineer ~v (4/5ths Vote: Yes Nom)
Dyno Construction has reque ted a time extension to the contract
for the construction of the transit center at Woodlawn Avenue/"H"
Street. The contractor is unable to finish the project by the
original completion date of September 24, 1981 due to
circumstances beyond his control. A time extension of 2.3 working
days will change the contract com pletion date to October 27, 1981
and give the contractor sufficient time to finish this project.
It is my
RECOMMENDATION: That Council approve the resolution granting a
23 day time extension to Dyno Construction, changing the contract
completion date to October 27, 1981.
BOARD/COMMISSION RECOMMENDATION: Not applicable.
DISCUSSION:
Dyno Construction was awarded the contract dated June 15, 1981,
by Resolution No. 10464 far the construction of the Chula Vista
Transit Center at Woodlawn Avenue/"H" Street. The contract
required that work commence no later than June 30, 1981 and
allowed 60 working days to complete the project (last day is
September 24, 1981).
Attached is a listing of chronological events for the period from
May 5, 1981 to September 8, 1981. A major delay was encountered
by the contractor at the start of the project because the
controller for the signal at Woodlawn Avenue/"H" Street built by
MTDB was in the wrong place and needed to be relocated. On June
1, the City sent a letter to MTDB requesting that this controller
be relocated. MTDB was very hesistant to agree to the
relocation and requested that the City redesign the landscaping
on the island to accommodate the misplaced controller. The
Landscape Architect and City Engineer considered a redesign and
decided that it would have a significant negative aesthetic
impact on the transit center and reaffirmed the City's request
that MTDB relocate the controller.
It should be noted that the staff at MTDB was very busy during
this time (June-July) with last minute preparations for the
startup of trolley service on July 26 and I am sure that the
controller relocation was a low priority item for them. The
Form A-113 (Rev. 11/79)
Page 2, Item 16
Meeting Date 9-22-81
controller was finally relocated on August 3, 1981. Prior to
that date, the contractor was able to do some minor work such as
the installation of irrigation piping but none of the major work
such as planters, tree wells and pavers.
Once the contractor got started, a second conflict was
encountered causing additional delay. The underground conduit
for lighting and telephone installed by MTDB was not located in
the area specified on the plans and was struck by the
contractor's equipment. This necessitated repair and rerouting
of the cond uit by others and was finally resolved on September
8, 1981. As of September 24th, the contractor will have had only
30 days that he could perform work on contract items that could
be scheduled around the conflicts. Ordinarily, the contract
would have been extended those 30 working days, but Dyno
Construction has prepared the attached bar graph showing that
work can be completed by October 27, 1981. The Engineering
staff, in reviewing the problem s encountered, believes that a 23
working day extension of time to October 27, 1981 is justified
and recommends approval.
The shelters and kiosks furnished by the City were received on
September 14, 1981 and are available for assembly and setting by
the contractor when appropriate.
FISCAL IMPACT.: None
GRH:fpw/DS030
C~afed _-~ ~/
~- ~a ~~ y
~~
TRANSIT CENTER
WOODLAWN & "H"
Chronological Listing of Events.
Received Bids May 5, 1981
Awarded Contract May 19, 1981
Letter to MTDB - Dick Weaver - June 1, 1981
Requesting relocation of traffic
signal controller
Contract Executed June 15, 1981
Preconstruction Meeting - Controller June 23, 1981
discussed
Letter from Dyno - Completion time Rece ived 5-30-8I
depended on controller relocation -
possible mid-July
Dyno informed to determine extra July 2, 1981
move-in cost for crosswalk
Letter from Dyno - Cost to move in July 8, 1981
early - Set crosswalk pavers
Phone message to schedule extra move-in July 9, 1981
wor k
Inspectors Lag - City forces prepared July 10, 1981
crosswalk concrete to receive pavers.
Contractor for MTDB did not construct
per plan
Inspectors Log - Began placing brick July 15, 1981
pavers
Inspectors Log - Irrigation work started. July 17, 1981
Placement of brick pavers in crosswalk
completed .
Inspectors Log - Began irrigation and ,July 20, 1981
drinking fountain work.
Inspectors Log - Began ripping soil for July 21, 1981
moisture thru
July 22, 1981
Inspectors Log - Select Electric did not July 24, 1981
sho w to move controller
Inspectors Log - Select Electric began July 27, 1981
work
Inspectors Log - Select Electric still July 28, 1981
working
Inspectors Log - Controller relocated Augu st 3, 1981
Inspectors Log - Contractor ex periencing Augu st 7, 1981
difficulty with existing soil - Dyno thru
called in soil engineer. Change in Augu st 13, 1981
work procedure approved.
Inspectors Log - Started layout for Augu st 14, 1981
planter wells
Inspectors Log - Control staking being Augu st 17, 1981
set thru
_,/0~3~ Augu st 18, 1981
3
4 ~ y
Inspectors Log - Working on irrigation August 19, 1981
system,
Inspectors Log - Irrigation Work. Began August 20, 1981
excavatin g tree wells
Inspectors Log - Contractor hit conduits August 21, 1981
in holes
Phoned - Ca lled MTDB for Dick Weaver August 21, 1981
Inspectors Log - No work by Dyno August 21, 1981
thru
August 26, 1981
Letter from Dyno - Stop Work Notice - August 24, 1981
Because o f conf lict with underground
electrica l and telephone
Phone Calls to MTDB - Requesting August 24, 1981
markout - August 2 8, 1981
Inspectors Log - Pacific Telephone August 27, 1981
fixed the ir conduit
Inspectors Log - MTDB marking out August 28, 1981
U.G. "As- Builts"
Inspectors Log - Mark out completed August 31, 1981
Inspectors Log - Contractor on site September 2, 1981
working
Inspectors Log - Excavating tree wells September 3, 1981
Inspectors Log - Contractor Laying out September 4, 1981
curbing
Inspectors Log - Contractor working September 8, 1981
Letter from Dyno requesting time September 9, 1981
extension
io63y
4