HomeMy WebLinkAboutAgenda Statement 1981/09/22 Item 16 COUNCIL AGENDA STATEMENT Item ~ 1 ~ / Meeting Date A~-~2-81 ITEM TITLE: Resolution 106.3, Approving extension of time, Chula Vista Transit Cent r SUBMITTED BY: City Engineer ~v (4/5ths Vote: Yes Nom) Dyno Construction has reque ted a time extension to the contract for the construction of the transit center at Woodlawn Avenue/"H" Street. The contractor is unable to finish the project by the original completion date of September 24, 1981 due to circumstances beyond his control. A time extension of 2.3 working days will change the contract com pletion date to October 27, 1981 and give the contractor sufficient time to finish this project. It is my RECOMMENDATION: That Council approve the resolution granting a 23 day time extension to Dyno Construction, changing the contract completion date to October 27, 1981. BOARD/COMMISSION RECOMMENDATION: Not applicable. DISCUSSION: Dyno Construction was awarded the contract dated June 15, 1981, by Resolution No. 10464 far the construction of the Chula Vista Transit Center at Woodlawn Avenue/"H" Street. The contract required that work commence no later than June 30, 1981 and allowed 60 working days to complete the project (last day is September 24, 1981). Attached is a listing of chronological events for the period from May 5, 1981 to September 8, 1981. A major delay was encountered by the contractor at the start of the project because the controller for the signal at Woodlawn Avenue/"H" Street built by MTDB was in the wrong place and needed to be relocated. On June 1, the City sent a letter to MTDB requesting that this controller be relocated. MTDB was very hesistant to agree to the relocation and requested that the City redesign the landscaping on the island to accommodate the misplaced controller. The Landscape Architect and City Engineer considered a redesign and decided that it would have a significant negative aesthetic impact on the transit center and reaffirmed the City's request that MTDB relocate the controller. It should be noted that the staff at MTDB was very busy during this time (June-July) with last minute preparations for the startup of trolley service on July 26 and I am sure that the controller relocation was a low priority item for them. The Form A-113 (Rev. 11/79) Page 2, Item 16 Meeting Date 9-22-81 controller was finally relocated on August 3, 1981. Prior to that date, the contractor was able to do some minor work such as the installation of irrigation piping but none of the major work such as planters, tree wells and pavers. Once the contractor got started, a second conflict was encountered causing additional delay. The underground conduit for lighting and telephone installed by MTDB was not located in the area specified on the plans and was struck by the contractor's equipment. This necessitated repair and rerouting of the cond uit by others and was finally resolved on September 8, 1981. As of September 24th, the contractor will have had only 30 days that he could perform work on contract items that could be scheduled around the conflicts. Ordinarily, the contract would have been extended those 30 working days, but Dyno Construction has prepared the attached bar graph showing that work can be completed by October 27, 1981. The Engineering staff, in reviewing the problem s encountered, believes that a 23 working day extension of time to October 27, 1981 is justified and recommends approval. The shelters and kiosks furnished by the City were received on September 14, 1981 and are available for assembly and setting by the contractor when appropriate. FISCAL IMPACT.: None GRH:fpw/DS030 C~afed _-~ ~/ ~- ~a ~~ y ~~ TRANSIT CENTER WOODLAWN & "H" Chronological Listing of Events. Received Bids May 5, 1981 Awarded Contract May 19, 1981 Letter to MTDB - Dick Weaver - June 1, 1981 Requesting relocation of traffic signal controller Contract Executed June 15, 1981 Preconstruction Meeting - Controller June 23, 1981 discussed Letter from Dyno - Completion time Rece ived 5-30-8I depended on controller relocation - possible mid-July Dyno informed to determine extra July 2, 1981 move-in cost for crosswalk Letter from Dyno - Cost to move in July 8, 1981 early - Set crosswalk pavers Phone message to schedule extra move-in July 9, 1981 wor k Inspectors Lag - City forces prepared July 10, 1981 crosswalk concrete to receive pavers. Contractor for MTDB did not construct per plan Inspectors Log - Began placing brick July 15, 1981 pavers Inspectors Log - Irrigation work started. July 17, 1981 Placement of brick pavers in crosswalk completed . Inspectors Log - Began irrigation and ,July 20, 1981 drinking fountain work. Inspectors Log - Began ripping soil for July 21, 1981 moisture thru July 22, 1981 Inspectors Log - Select Electric did not July 24, 1981 sho w to move controller Inspectors Log - Select Electric began July 27, 1981 work Inspectors Log - Select Electric still July 28, 1981 working Inspectors Log - Controller relocated Augu st 3, 1981 Inspectors Log - Contractor ex periencing Augu st 7, 1981 difficulty with existing soil - Dyno thru called in soil engineer. Change in Augu st 13, 1981 work procedure approved. Inspectors Log - Started layout for Augu st 14, 1981 planter wells Inspectors Log - Control staking being Augu st 17, 1981 set thru _,/0~3~ Augu st 18, 1981 3 4 ~ y Inspectors Log - Working on irrigation August 19, 1981 system, Inspectors Log - Irrigation Work. Began August 20, 1981 excavatin g tree wells Inspectors Log - Contractor hit conduits August 21, 1981 in holes Phoned - Ca lled MTDB for Dick Weaver August 21, 1981 Inspectors Log - No work by Dyno August 21, 1981 thru August 26, 1981 Letter from Dyno - Stop Work Notice - August 24, 1981 Because o f conf lict with underground electrica l and telephone Phone Calls to MTDB - Requesting August 24, 1981 markout - August 2 8, 1981 Inspectors Log - Pacific Telephone August 27, 1981 fixed the ir conduit Inspectors Log - MTDB marking out August 28, 1981 U.G. "As- Builts" Inspectors Log - Mark out completed August 31, 1981 Inspectors Log - Contractor on site September 2, 1981 working Inspectors Log - Excavating tree wells September 3, 1981 Inspectors Log - Contractor Laying out September 4, 1981 curbing Inspectors Log - Contractor working September 8, 1981 Letter from Dyno requesting time September 9, 1981 extension io63y 4