HomeMy WebLinkAboutAgenda Statement 1981/09/15 Item 7.: ,~ COUNCIL AGENDA STATEMENT
Item 7
Meeting Date 9-15-81
ITEM TITLE: Resolution ~ D 6~Accepting public improvements - construction of
streets, sidewalks, ramps and curb improvements in the Feaster,
Mueller and Vista Square area
SUBMITTED BY: City Engineer (4/5ths Vote: Yes No x )
Dyno Construction, Inc. has completed the construction of the streets,
sidewalks, ramps and curb improvements in the Feaster, Mueller and Vista
Square area. It is my
RECOMMENDATION: That Council adopt resolution accepting the public improvements.
BOARD/COMMISSION RECOMMENDATION: Not applicable.
DISCUSSION:
Dyno Construction, Inc. has completed all work in accordance with the contract
documents dated May 8, 1981 and awarded by Resolution 10436. A final
inspection was made on August 21, 1981. All work was found to be completed
in accordance with the contract documents and approved revisions and to the
satisfaction of the City Engineer.
FINANCIAL STATEMENT:
Authorized Expenditure $124,000.00
Original Contract Amount 110,095.06
Approved C.0.#1 - Sidewalks 5th Ave. 2,300.00
Approved C.O.#2 - Add driveway
Casselman and Fifth Ave. 443,25
Estimated cost to purchase replacement trees 1,500.00
Total Approved Contract $114,338.31
Final Construction Cost with C.0. 111,338.93
Cost of 44 Replacement Trees 950.40
Total Actual Construction Cost $112,289.53
Authorized Expenditure Balance 11,710.67
FISCAL IMPACT: City will assume maintenance of the public improvements.