HomeMy WebLinkAboutPlanning Comm min 1987/10/28 Tape No: 284
Side l: 0-1245
MINUTES OF A REGULAR BUSINESS MEETING
OF THE CITY PLANNING COMMISSION OF
CHULA VISTA, CALIFORNIA
7:00 p.m. Council Chambers
Wednesday, October 28, 1987 Public Services Building
ROLL CALL
CO~qISSIONERS PRESENT: Chairman Carson,Commissioners Cannon, Casillas
Shipe and Tugenberg
COMMISSIONERS EXCUSED: Commissioners Fuller and Grasser
STAFF PRESENT: Director of Planning Krempl; Principal Planner
Lee; Deputy City Attorney Moore; Senior Civil
Engineer Daoust; Environmental Review
Coordinator Reid; Deputy Director of Public
Works/City Engineer Garibay; Director of Parks
& Recreation Mollinedo; ERDR Consultant
Lettieri; Environmental Consultant Claycomb
PLEDGE OF ALLEGIANCE - SILENT PRAYER
The pledge of allegiance to the flag was led by Chairman Carson and was
followed by a moment of silent prayer.
INTRODUCTORY REMARKS
Chairman Carson reviewed the composition of the Planning Commission, its
responsibilities and the format of the meeting.
ORAL COMMUNICATIONS
None
1. PUBLIC HEARING: PCM-88-13 CONSIDERATION OF DENSITY BONUS FOR
APARTMENTS PROPOSED AT 36-54 WOODLAWN AVENUE T.E.N.
DEVELOPERS
Principal Planner Lee stated the proposed 37-unit apartment project is located
on the west side of Woodlawn Avenue just north of Chula Vista Street. It is
just over 1 acre in size; the building design and layout were approved by the
Design Review Committee in August, 1987. The underlying R-3 zone allows for a
maximum of 31 units on the site; however, under the State-mandated Density
Bonus Program, the City is obligated to grant a minimum density bonus of 25
percent or other incentives of equal economic value. The applicant has
requested a six-unit bonus, or a 19 percent increase over the underlying
zone. The City Ordinance that addresses the State bonus program requires the
developer to provide 20 percent of the total project as affordable-to-low
income ($419 for 1-bedroom; and $523 for a 2-bedroom), and 5 percent of the
pre-density affordable to the moderate income. The rents are restricted for
25 years. The estimated rent structure for the non-restricted units would be
Planning Commission -2- October 28, 1987
$550 for 1-bedroom and $650 for 2 bedrooms. If approved, the project will
provide a total of eight low and moderate income units. Staff's
recommendation is to recommend that Council approve the density bonus.
This being the time and the place as advertised, the public hearing was
opened. No one wishing to speak, the public hearing was closed.
MSUC {Shipe/Casillas) to find the project will have no significant
environmental impact and adopt the Negative Declaration issued on IS-87-47.
MSUC (Shipe/Casillas) to recommend that Council approve the density bonus,
PCM-88-13, for 37 units at 36-54 Woodlawn Avenue.
2. CONSIDERATION OF FINAL EIR-87-1, RANCHO DEL REY SPA-I
Environmental Review Coordinator Reid reported that this Final EIR includes
the transcript of the public hearing held on August 12, as well as written
comments and responses to the comments. He explained that this document is in
two basic volumes: the master EIR on the overall Specific Plan and the
addendum included in that; and within the bounds of the supplemental document
is the addendum which describes the impact of the relocation of the school
site on the property.
Mr. Reid reported the following change in the supplemental document; following
page 4-106, Table 4-F-4 should be deleted and reference made to the Public
Financing Plan.
Mr. Reid called attention to the various alternatives to this project which
are discussed in the two volumes of the EIR.
Dave Claycomb, Westec Services, preparers of the original and the supplemental
EIR's, pointed out that the addendum to the draft EIR was required because, in
response to a request by the elementary school district, the school site was
changed to an area previously designated for residential development, with
former school site being designated for homes. Since there was no change in
the number of housing units, grading, or circulation system, it was deten~ined
there would be no new significant effects for the project and the changes
could be covered in the addendum without recirculating the document for public
review.
Mr. Claycomb pointed out that responses on the issue of traffic were covered
in the response. On the issue of parks, while the project plan identifies the
location, the development of the parks will be covered by a park master plan,
which will detail the issue of lighting, specific buffers and noise barriers
to minimize the effect on adjacent residential areas. In response to the
Sweetwater Union High School District's concern over capacity, it was found
that if planned school facilities, including those in the EastLake development
are built as scheduled, there will be adequate facilities for the demand of
this project.
Planning Commission -3- October 28, 1987
With regard to water, the report notes that additional distribution facilities
will be needed and they will be provided. Also, measures for water
conservation, both during the construction phase of the project and after the
units are in habitation, will be implemented to the maximum extent possible.
The effects on water rates and supply to this project and to the region as a
whole, in the event Colorado River water is eventually cut off, cannot be
determined at this time.
Mr. Reid pointed out that the comments on the draft EIR were grouped into
areas and a response provided for each area, rather than responding
individually to each comment. He recommended that the Planning Commission
proceed with the public hearing on the project before taking action on the
final EIR.
3. PUBLIC HEARING: CONSIDERATION OF THE ADOPTION OF THE GENERAL DEVELOPMENT
PLAN, SECTION PLANNING AREA (SPA) PLAN (PCM-87-6),
PUBLIC FACILITIES PLAN AND FINANCING ANALYSIS,
DEVELOPMENT AGREEMENT, DESIGN GUIDELINES AND DEVELOPMENT
REGULATION FOR RANCHO DEL REY SPA-I - RANCHO DEL REY
PARTNERSHIP
Planning Consultant Lettieri advised that the E1 Rancho del Rey Specific Plan,
approved in November 1985, set the framework for this SPA Plan. He displayed
plats showing the area covered by the Specific Plan, north and south of East
"H" Street between 1-805 and Otay Lakes Road, and the area included in the
SPA-I plan which is located northerly of East "H" Street and encompasses most
of the major natural features within the Specific Plan area. Included in the
framework set by the Specific Plan are maximum densities, identification of
physical features, and facilities that are important to serve future
development.
Mr. Lettieri highlighted the following objectives of the Specific Plan: First,
protection of natural land form, in this case, Rice Canyon; second,
establishment of an effective pattern of circulation, both internal and
outside of the project area; third, provision of adequate police, fire, parks,
recreation, and other municipal services; and fourth promotion of a well
designed project.
This project covers 808 acres and includes 2,201 dwelling units, an employment
park and other public facilities; this is a little more than half the total
dwelling units in the Specific Plan. A graphic was displayed showing the
location of the different residential types, ranging from residential estates
at 2 du/acre, to traditional units at 5 du/acre, smaller detached units at 7
du/acre, townhomes at 12 du/acre and apartment units at 15-17 du/acre. This
mix of residential types is an important objective of the Specific Plan. The
units are sited throughout the project to take advantage of views to the
canyon and offsite, as well as exposure to the recreational resources.
Planning Commission -4- October 28, 1987
The Specific Plan provides for transfer of density from one neighborhood to
another. A graphic showing where density was decreased and increased was
displayed. These transfers resulted in a decrease in grading of one million
cubic yards, and also provided for additional lower cost housing.
Mr. Lettieri pointed out that a second important aspect of the plan is parks,
recreation, and open space. The project includes 273 acres of open space, 205
of which are Rice Canyon. In addition, there are a number of community
facilities, including YMCA site and proposed church site or some other
facility, such as a day-care center. In addition to the natural open space
there are three developed park areas; a neighborhood park, approximately 5-1/2
acres in size, between two residential neighborhoods; the East "H" Street
Park, which is encumbered by the SDG&E easement and which may include a
library and fire station within the total 16 acre area; and a long community
park of 34 acres. 20 acres of which is developable and will be used for
recreational purposes. In addition, there is a small staging area adjacent to
the loop road which will provide pedestrian and equestrian access and parking
to the trails traversing the canyon.
Another major element of the project is the employment park adjacent to East
"H" Street. For grading and other aesthetic reasons, this has been reduced to
84.5 acres. The primary use being proposed is light industrial, with some
office use and with limited retail commercial in certain areas on the west
side.
Mr. Lettieri discussed the Public Facilities Financing Plan as it relates to
development of public facilities to serve this project in direct relationship,
but also in indirect relationship as it relates to regional improvements. He
also discussed the Development Agreement which ties the provision of roads and
other public improvements to the development of the project. He called
attention to the detailed set of guidelines which will bridge the gap between
this plan and the subdivision or site plans for each stage of development,
including the employment park.
Mr. Lettieri concluded with the staff recommendation for approval of the
project as set forth in the staff report.
The public hearing was opened.
Ken Baumgartner, representing Rancho del Rey Partnership, requested that he be
allowed to address the Commission again at the next meeting to respond to any
issues raised in the public hearing or to questions of the Commission. He
also requested permission to make a 15-minute presentation, with slides,
during this hearing.
Mr. Baumgartner displayed aerial photos of the area with the project
boundaries and road system overlaid on the photo. He discussed the community
structure built into the plan with the full range of residential densities,
the location of the dwelling units on the ridges to take advantage of offsite
views and views with the canyons, which will provide opportunity for
Planning Commission -5- October 28, 1987
delightful neighborhoods. The loop road also provides views into the open
space canyon areas. The canyons provide a buffer between the employment area
and the residential areas. The apartment units will be built adjacent to "H"
Street and provide walking access to the college, the shopping center to be
constructed to the north, and to public transit.
The public benefits include the widening of "H" Street to six lanes in the
first stage of development, earlier than required by traffic reports. Otay
Lakes Road will be widened to four lanes and the necessary signal lights
installed.
The employment park will provide an economic benefit to the city, and the
residents will generate additional sales tax revenue through shopping at the
nearby centers.
Grading for the employment park will occur in the first phase of the program,
so conceivably construction could begin on that site early in the development
of the project. It is anticipated the employment park will generate 5,000
jobs when fully occupied.
In response to a question from Commissioner Shipe, Mr. Baumgartner elaborated
on the system of trails connecting residential areas, park lands, open space
canyons and the employment park. The loop road will provide bike lanes
throughout the project.
Keith Hammon, 1457 Summit Drive, confirmed his objections to having the
ballfield placed directly behind the Eucalyptus Ridge housing complex.
Mr. Lettieri expressed the need for ballfields in the City, and the size and
shape of this park make it the most suitable for that use. No other sites
within Rancho del Rey were suitable.
Director of Parks and Recreation Mollinedo affirmed the need for ballfields in
the community and pointed out that plans are very general at the present
time. Detailed plans will be prepared in the future and at that time the City
would welcome participation and input from interested residents in an attempt
to lessen any impact the project might have.
Robert Stinson, 1469 Summit Drive, expressed the opinion that the project in
general was well thought out and well planned, but he, too, objected to the
location of the ballfields and would desire their relocation. If that cannot
be done he would like to be involved and have input into the park master plan.
George Rodway, 1459 Summit Drive, expressed the opinion that preserving Rice
Canyon should not involve filling it in as proposed for the park, and that the
ballfields should not be located there.
Director of Planning Krempl advised that the Commission should consider agenda
items 4 and 5 before entertaining a motion with regard to the development plan.
Planning Commission -6- October 28, 1987
4. CONSIDERATION OF CEQA FINDINGS, EIR-87-1, RANCHO DEL REY SPA-I
5. STATEMENT OF OVERRIDING CONSIDERATIONS - RANCHO DEL REY SPA I
Environmental Review Coordinator Reid advised that because the EIR concludes
that there would be one potentially significant impact to the environment due
to the development of the project, CEQA findings are required. Of the impacts
evaluated in the EIR, there are four which were potentially significant but
which have been mitigated to a level less than significant. Those are: the
land form aesthetics issues, hydrology and water quality, traffic circulation
and access, and noise. The one remaining impact that is significant is the
impact on the biological resources on the property. This is a very sensitive
site and there are substantial areas of development which will affect
sensitive species.
It is, therefore, necessary to adopt a Statement of Overriding Considerations
if the Planning Commission wishes to approve the project.
The staff report included a draft statement, but Mr. Reid felt there are other
goals in the Specific Plan which are being implemented by the project which
would warrant inclusion in the statement also. He indicated the statement
will be revised for the Commission by next week.
MSUC (Cannon/Tugenberg) to continue agenda items 2, 3, 4, and 5 to the next
meeting.
6. PUBLIC HEARING: PCA-88-1 CONSIDERATION OF AN AMENDMENT TO THE
MUNICIPAL CODE TO EXEMPT SERVICE STATIONS ON SCENIC
CORRIDORS FROM STATE PRICE SIGN LOCATIONAL REQUIREMENTS
- CITY INITIATED
Principal Planner Lee stated that after completion of the Shell Service
Station in the new Terra Nova Plaza Center, the State's Weights and Measures
Division of California cited Shell for failing to have a price sign visible
from both sides of "H" Street. In researching this, it was found that State
Law requires pricing to be identified from a public road whereas the overall
sign program, which includes pricing, for this Center is actually located on
the loop road which is a private road system internal to the Center. In
reviewing the State Law, staff was able to find a section which provides for
exemptions to the State Law where stations are located along scenic routes so
designated on the General Plan. Therefore, in August 1987, an urgency
ordinance was sent directly to the Council and enacted. That ordinance is
valid for 90 days. The hearing process required for a permanent ordinance is
before the Commission tonight. Staff requests a recommendation to Council for
adoption of the new ordinance per Exhibit A which establishes the exemption
for the Terra Nova Center. Areas could be added in the future if this problem
arises along other scenic routes. It is staff's opinion that the sign program
in the Terra Nova Center is excellent and people can easily see the pricing
for that station as they enter the Center.
Planning Commission -7- October 28, 1987
This being the time and the place as advertised, the public hearing was
opened. No one wishing to speak, the public hearing was closed.
MSUC (Tugenberg/Casillas) to recommend City Council amend the Municipal Code
to exempt service stations located along specified scenic corridors from State
price sign locational requirements as shown on Exhibit A.
DIRECTOR'S REPORT
Director Krempl commented that the workshop of November ll is cancelled since
it is a holiday when meetings cannot be held. There will be, therefore, no
workshop in November. It is expected that there will be a workshop dinner
meeting in December and unless there are objections that would be a joint
meeting with the Resource Conservation Commission. That body has expressed
some concern with respect to how their recommendations are viewed by the
Planning Commission and whether good communication exists between the two
bodies. For that reason, we believe it would be good to sit down with them
and have some dialogue.
ADJOURNMENT AT 8:42 p.m. to the Regular Business Meeting of November 4, 1987
at 7:00 p.m. in the Council Chambers.
Ruth M. SmitH, Secretary
Planning Commission
WPC 4468P