HomeMy WebLinkAboutAgenda Statement 1988/10/25 Item 15
COUNCIL AGENDA STATEMENT
.
ITEM TITLE:
I tern 15
Meeting Date 10/25/88
Resol uti on/3 toZ 3 Appropri ati ng addi ti onal funds to
reimburse Otay Water District for costs associated with water
facilities for EastLake Asses:;~ District 85-2
Director of Public Work~ 1~
City Manager( (4/5ths Vote: Yes~No_
SUBMITTED BY:
REVIEWED BY:
BACKGROUND:
On December 17, 1985, the City Council approved an agreement between the Ci ty
and Otay Water District for installation, conveyance, maintenance and
operation of water facilities within EastLake Assessment District No. 85-2.
The water facil ities were constructed by pub1 ic works contracts under the
procedures of the "Municipal Improvement Act of 1913." Construction of the
water facilities were financed through the sale of "1915 Act" bonds.
The agreement stipulated that upon completion of the installation of the
.facilities, Otay Water District will own, operate and maintain said
mprovement facilities. The agreement further stipulated that:
1. All the improvements shall be installed and completed in accordance with
plans and specifications approved by Otay Water District.
2. Otay Water District shall be authorized to inspect all work and to reject
any work or improvement that does not meet requirements of the plans and
specifi cati ons.
3. Otay Water District shall be reimbursed for all costs incurred for
inspecting, rejecting or accepting the said improvements.
4. City shall assure that all contracts awarded shall provide for warranties
or guarantees whi ch shall protect Otay Water Di stri ct for any defects
discovered within a period of one year following final acceptance of the
work by Otay Water District.
The City awarded four separate contracts for water facilities within EastLake
Assessment District 85-2 as follows:
1. EastLake Business Center
2. 20-inch offsite water main
3. 5 million gallon steel reservoir
4. 980 zone pump station
. b the City C>xJnsil of
Chula Vi:;tJ, C~,:ifornia
Dated
./
Page 2, Item 15
Meeting Date 10/25/88
1 through 3 on August 25, 1987,
Water District has not accepted
is operational and is being
~he City accepted the contract work for items
and item 4 on October 13, 1987. To date Otay
the water facilities although the system
maintained by Otay Water District.
There are a number of deficiencies that still need to be corrected before Otay
Water Di stri ct wi 11 accept the system. The defi ci enci es are items that were
not included in the original plans but are necessary to bring the system to
their standards. These items should have been on the original plans and are a
1 egi timate cost of the assessment di stri ct. In the process of Otay Water
District correcting the deficiencies and operating and maintaining the system,
the cost of doi ng so has exceeded funds appropri ated in EastLake Assessment
District 85-2 for this purpose. As of September 15, 1988, Otay Water District
has incurred a deficit which needs to be reimbursed by the Assessment
District. Otay Water District has estimated it will cost $15,000 to complete
the work required to bring the system up to their standards. They have agreed
to accept $15,000 for thi s work and to accept the system for full operati ons
and responsibility.
RECOMMENDATION: Ci ty Counci 1 appropri ate funds from the EastLake Assessment
Di stri ct 85-2 Improvement fund in the amount of $111 ,000 to reimburse Otay
Water District.
~ISCUSSION:
~n accordance with the agreement entered into between the City and Otay Water
Di stri ct for water faci 1 iti es withi n EastLake Assessment Di stri ct 85-2, Otay
Water District is entitled to reimbursement for the following items of work:
1. Cost of provi di ng the automati c control panel for the 980 zone pump
station. This item was purposely deleted from the original plans and
specifications because it was the only way to acquire the equipment
required by the Water District. The automatic controls cost the District
$25,872.
2. Cost of correcting 5 punch list items which were not included in the
original plans and specifications. These deficiencies had to be corrected
for operation safety and security of the pump station. These items are
estimated to cost $15,000 and are as follows:
a.
b.
c.
d.
. e.
Access guard on the exterior wall of the pump station.
Access into the radiator shroud for cleaning.
Installation of diffusers on air release and vacuum values of pump
barrels.
Extension of oil tank drain piping.
Installation of a 6-inch pressure relief valve on the suction header.
-'
~.
e.
.
Page 3, Item 15
Meeting Date 10/25/88
Cost overruns on six Otay Water District work orders (1473, 1485, 1653,
1701, 1702 and 1703). These cost overruns are due to inspection and staff
charges for correcting the various deficiencies so that the system can be
accepted by the Water District.
Work Orders 1473,1485 and 1701 are chargeable to the 980 zone pump
station. Work Orders 1653, 1702 and 1703 are for the EastLake Business
Center, 20-inch offsite water main and the 5 mg steel tank reservoir,
respectively. Work Order 1687 shown in the District's summary is not for
thi s project.
As of September 15, 1988, the charges to these work orders are as foll ows:
Work Otay Water Deposits Current
Order District Charges Received Deficit
1473 $ 16,638 -0- ($16,638)
1485 $ 2,119 -0- ($ 2,119)
1653 $ 26,087 $ 15,637 ($10,450)
1701 $103,239 $ 76,000 ($27,239)
1702 $ 26,974 $ 22,465 ($ 4,509)
1703 $ 70,621 $ 58,547 ($12,074)
Totals $242,678 $) 72 ,649 ($70,029)
EastLake Development Company is also responsible for charges reimbursable
to Otay Water District. This includes charges accrued to work order 1653
after the date of acceptance of the work by the City Council on August 25,
1987. EastLake must also pay for the installation of a second surge tank
at the zone 980 pump station. These costs are separate from and in
addi ti on to costs to be reimbursed by AD 85-2. The estimate of these
charges are:
Work Order 1653
Second Surge Tank
Tota 1
$ 110
$60,000
$60 , 11 0
5. There has been an intermittent problem with the buried telemetry cable
between the pump station and steel tank reservoir. The cost of correcting
this deficiency is the responsibility of the contractor. At this date,
the cost cannot be determined.
The Assessment District's financial responsibility for the cost overruns are
as follows:
Automatic Control Panel
Five Punch List Items
Work Order Cost Overrun
To ta 1
$ 25,872
$ 15,000
$ 70,029
$11 0 ,901
,_/'
Page 4, Item 15
~ Meeting Date 10/25/88
Funds are avail abl e to reimburse these expenses from the EastLake Assessment
District 85-2 Improvement Fund. Payment of these funds will not increase the
current assessments being paid by the EastLake property owners.
FISCAL IMPACT: The cost of the water facilities are funded from "1915 Act"
bonds which were sold to specifically finance this project. The cost of
maintaining these facilities will be paid for by Otay Water District once the
improvements are accepted into their maintained system.
KJG: nr/
WPC 3905E
.
.