HomeMy WebLinkAboutAgenda Statement 1979/12/04 Item 09CITY OF CHULA VISTA
COUNCIL AGENDA STATEMENT Item No. 9
For meeting of 12/4/79
ITEM TITLE Resolution ~~'~j / Accepting Bids and Awarding Contract
for the Construction of the Park way Community Center
and Appropriat~i~n/g,~~Funds
SUBMITTED BY City Eng ineer l~~'l/ Director of Parks & Recreation
ITEM EXPLANATION
(4/5TH'S VOTE REQUIRED YES x NO )
The City Council at its meeting on August 7, ].979, rejected
bids for this project. The two bids received on June 7?,
1979, were from Haas & Sons and Fritz A. Nachant, Inc. for
$559,847.00 and $535,000.00 respectively. On the advice of
the architect (see attached letter dat~ad 7uly 30, 1979) City
staff recommended to the City Council that the previous bids
be rejected and that the plans be modified as recommended by
the architect and the project readvertised for bids. We
modified the plans as recommended and readvertised for bids
on October 14, 1979.
At 2:00 p.m. on November 14, 1979, in Conference Room 3, the
City Engineer received sealed bids Eor the Construction of
Park way Community Center, Chula Vista, California. The
scope of the work included the construction of a new framed
building complete with heating, ventilating and air
conditioning system, plumbing system, electrical system,
fixtures, and equipment. The bid also included an alternate
which was intended to reduce the cost of the total project.
The alternate deleted the installation of metal roofing and
provided instead for the installation of composition
shingles as specified in the special provisions.
SLH:nr/JP-004 (continued on supplemental page)
r~n~rnrrn
tltli I l:t 1 ~ J
Agreement Resolution x Ordinance_ Plat_ Notification List_
Other Letter ENVIRONMENTAL DOCUMENT: Attached Submitted on
FINANCIAL IMPACT
Upon completion of the project, the City will assume
responsibility for facility maintenance.
STAFF RECOMMENDATION
Please see supplemental page three.
BOARD/COMMISSION RECOMMENDATION
COUNCIL ACTION ,~ + -'
i;'J ~.:~ .:. l t.ii O.c
~L:°"; CE ' ~i lo;Z~, Lb'.~ii J~rj1
~ ~ Deice /~ -'~-
Agenda Item No. 9
For Meeting of 12/4/79
Supplemental Page Two
Bids were received from four contractors as follows:
CONTRACTOR
John B. Reid
Construction Inc.
A. E. Norcross Inc
BASIC BID
$5"39,000.00
5586,921.00
DEDUCT
(ALT. 1)
$7.9,000.00
$29,000.00
BASIC BID
IPdCLUDING
ALT. 1
$510,000.00
S557,921.00
Fritz A. Nachant Inc. S62A,861.00 $20,395.00 $608,466.00
Raymond A. Whitwer $532,350.00 521,000.00 $61.1,350.00
The low bid submitted by John B. Reid Construction Inc. for
the basic bid is above the architect's estimate of 5470,000
by $69,000 or 14.7.
In retrospect City would have been better off accepting the
previous bids and awarding the contract to the low bidder.
With the continuing problems of increased construction costs
at a spiraling rate, it appears that the best course of
action now is to award the contract to the lowest bidder and
proceed with the project. I recommend the bid be awarded to
John B. Reid Construction Inc. in the amount of
S539,OOn.00. The architect concurs with this
recommendation.
FINANCIAL STATEMENT:
Unencumbered Funds Available
(Project Account X516--5160-SBA-02) $371,360.00
Contract Amount Basic Bid $539,000.00
5~ Contingencies $ ?6,950.00
Total F,stimated
Construction Cost $555,950.00
Additional Funds Required
to be Appropriated $194,590.00
Unencumbered funds are available from the following sources
for the additional. appropriation - General Fund, Park
Acquisition and Development Fund, Residential.. Construction
Fund, and Federal Revenue Sharing.
~~~
Agenda Item No. 9
For Meeting of 12/4/79
Supplemental Page Three
Staff recommends appropriating 5194,590 from the Park
Acquisition and Development Fund which will leave an
unencumbered balance of approximately $143,000.
STAFF RECOMMENDATION:
L City Council appropriate "x194,590.00 from the
unappropriated balance of Park Acquisition and
Development Fund to account 615-6150-SBA-02, Park Way
Community Center Construction.
2. City Council authorize the expenditure of S539,000 from
account q,15-5150-SBA-07. for construction of the
project.
3. City Council
John B. Reid
$539,000 for
Center.
accept the bids and award the contract to
Construction Inc. in the amount of
the construction of the Park Way Community
/ ~ '"
~ ~
~ ~ THOMAS ~VILLIAMSON, ARCHITECT
[8[9 Fifth Avenue
San Diego, CA gz[o[
X7[4) 234-z6o2
July 30, 1975
Mr. Emerson Hall
Parks and Recreation Dept.
City of Chula Vista
P.0. Box 1087
Chula Vista, Ca 92012
Dear Emerson:
I zm writing with reference to the proposals submitted to
the c__ty on du^e 27; 1979, £or the construction of the new
community center on Park Way designed by this firm. In my
opinion the two bids received from Haas & Sons and Fritz A.
Nachant, Inc., for $559,847.00 and $635,000.00, respectively,
should be rejected as too costly, the contract documents changed
to incorporate certain cost-saving Features described below
and the job should be put out to bid a second time. If the
,job were rebid at a time of less construction activity allowing
more contractors to participate, the proposals should be more
competitive to the advantage of the city.
Since the time that this project was awarded to this firm in
1978, the San Diego region and its construction indus+,ry has
suffered an inordinate rate of inflation. We originally felt
that the budget of under $400,000.00 was realistic and this
figure was born out by a cost estimate prepared by Architects
and Contractors Estimating Service in December, 1978. A post
bid review of the costs inrolved has indicated that the effect
of the year's ~.rflation has indeed carried the anticipated cost
well over $400,000.00. I would currently estimate, considering
the recent inflationax^,/ surges that an acceptable cost range
For this project, utilizing the cost-saving measures listed -
below would be between $440,000.00 and $490,000.00.
There foLows a list of changes we intend to make to the
contract documents as a result of our meeting ~Jrith members of
the city staff on Jul;f 17, 1979. We believe that these mea.~ures
will reduce the construction cost by between $45,300 and $52,800.
1. Change the General Conditions to clarify city's role in
directinb constriction.
<• Incorporate Part I of Standard Specifications for Public
Works Construction for the General Conditions of the Ameri-
can Institute of Architects.
~~ ~~~ y
page 2 ;~
3. Identify all governmental forms to be executed by the
contractor, indicating that the filling out of any addi-
tional forms will be compensated by change orders.
4. Specify that retention of payments will be on a line-item
basis by sub trades as work is approved by the city instead
o£ for the entire job.
5. Specify that the contractor does not have to start construc-
tion for 60 days from date of executing contract with the
city and that the contract time for completion starts
when construction starts.
6. Substitute inorganic wall coating for fiberglass panels
• at the lower portion of the walls of the new gymnsaium.
7. Substitute words "WIC quality" for"WIC Certified Compliance
Grade Stamp" in millwork specifications.
8. Add additional manufacturers to specificaticns Per metal
roofing as part of base bid.
9. Substitute composition shingles for metal roofing as an
alternate.
10. Substitute narrow stile for medium stile at entrance doors.
11. Change clerestory windows so that only upper four-foot
portion is openable.
12. Change manufacturer of clerestory window controls to
Muschong Metal and P4anufacturing Co.
13. Eliminate locks on cabinet drawers and doors.
14. Omit Vi-Tex underlayment at vinyl asbestos tile.
15. Substitute textured finish for smooth for gypsum board.
16. Include Korok as acceptable manufacturer for basketball
backstop.
17. Clarify specifications as to controls to be furnished by
contractor for heating equipment.
18. Clarify costs for utility ser•rices to be paid by contractor.
We are ready to make any changes that the city may approve to
the contract documents in order that the project may be put
out to bid again.
t
TTW:djl
~~
Form No. F-229
12/73 r y
CERTIFICATE OF CITY/DIRECTOR OF FINANCE
Certification of Unappropriated Balance
I HEREBY CERTIFY that the money required for the
appropriation of funds for the purpose set forth in the attached
resolution is available in the Treasury, or is anticipated to
come into the Treasury, and is otherwise unappropriated.
Amount S 194,590.00 Fund Park Acquisition & Development Fund
purpose Construction of Park Way Community Center
aidaer J.B. Reid Construction, Inc.
', %'~
:: j ~'
616 6160 SBA 02 y l `- -_--~-~
Director of Finance
The City of Chula Vista
Date 11/30/79 By
Certification of Unencumbered Balance
I HEREBY CERTIFY that the indebtedness and obligation
to be incurred by the contract or agreement authorized by the
attached resolution can be incurred without the violation of any
of the provisions of the Charter of the City of Chula Vista, or
the Constitution or the laws of the State of California, that
sufficient monies have been appropriated for the purpose of said
contract, that sufficient monies to meet the obligations of the
contract are actually in the Treasury, or are anticipated to come
into the Treasury to the credit of the appropriation from which
the same are to be drawn, and that said monies now actually in
the Treasury, together with the monies anticipated to come into
the Treasury, to the credit of said appropriation are otherwise
unencumbered.
Amount Not to Exceed $ 565,950.00
616 6160 SBA 02
Date 11/30/79
tate ar s ec
Funa Bond Act Project 1
By
-,
Director of Finance -
The City of Chula Vista '=
Dept./Activity State Bond Act
purpose Construction of Park Way Community Center
Biaaer J.B. Reid Construction, Inc.
certificate No. 46
~~