HomeMy WebLinkAboutAgenda Statement 1979/10/09 Item 14:.- _ _ CITY OF CHULA VISTA COUfVC I L AGENDA STATEMEiVT Item No. 14 For meeting of 10/9/79 ITEM TITLE Resolution ~7~~ Approving Change Order No. 6, Third Avenue Improvements, "E" Street to "F" Street Phase One SUBMITTED BY City Engineer ITEM EXPLANATION (4/5TH'S VOTE REQUIRED YES NO ) Dan Pass, Senior Planner, in his official capacity as staff advisor to the Town Centre Design Review Board, brought to the Engineering Department°s attention that the Review Board.'s intent was that the wood trellises on Third Avenue have full 3" x 5" lath hangers on 8" centers entirely across the beams. The renderings of the proposed street improvements approved by the Review Board shows the trellises with full. lath hangers. The architect informs us that is was his intention that the hangers be continuous across the trellis work. The details on the approved construction plans, from an engineering viewpoint, does not show that the hangers are to be continuous. The contractor, T. B. Penick and Sons, states that they did not bid the prof ect for continuo us 3" x 5" lath hangers and until it was brought to the attention of Engineering, our inspection staff was confident that the trellises were being constructed correctly, according to plans. Engineering staff has obtained a price of $2,968.00 from T. B. Penick and Sons with 3" x 6" continuous lath hangers. Because of the misunderstanding, the contractor has agreed to provide the labor without charge to the City but wants the City to provide the additional materials. This amount is available in the contingency fund previously authorized for expenditure by the City Council. i,rin:nr~tily-uus >,con~cinuea on supplemental page, EXHIBITS Agreement Resolution x Ordinance Plat Notification List Other ENVIRONMENTAL DOCUMENT: Attached Submitted on FINANCIAL IMPACT Authorized expenditure $758,532.00 Original Contract Amount 690,714.00 Contract Amount through Change Order No. 5 688,613.31 Amount of Change Order No. 6 2,968.00 Contract Amount Through Change Order No. 6 $691,581.31 STAFF RECOMMENDATION Adopt resolution approving Change Order No. 6 increasing the contract amount to $691,581.31. BOARD/COMMISSION RECOMMENDATION COUNCIL ACTION ~~9~ ~ ,: ,r i ~ Dat~.d lp ~~ "~~ Form A-113 (Rev. 5/77) Agenda Item No. 14 For P~ieeting of 10/9/79 Supplemental Page Two T. B. Penick and Sons states that if the City Council approves Change Order No. h that the work will be completed by the contract date of October 2~, 1979. The contractor did have available a sufficient number of extra 3" x ~" lath hangers to place continuous hangers on the trellis at the bus stop on the northeast corner of Third Avenue and "F" Street. Slides are available showing the trellis with continuous hangers and one of the trellises constructed in accordance with the plans. I am recommending that this Change Order be approved to conform with the design concept and approval of the Town Centre Desig n Review Board, ~~~~