AGENDA "ITEM NO. [ 9 ]
CHULA VISTA CITY COUNCIL MEETING OF: September 10, 1974
ITEM TITLE: Resolution - Granting Extension of Time, Gas Tax Project #163,
Bay Boulevard between "L" and Palomar Streets
INITIATED BY:
Director of Public Works/City Engineer jJJ rJ
BACKGROUND
Wilco Construction Company, by their letter dated August 28, 1974,
requests an additional 20 working days extension of time on the contract
due to strike conditions.
The contract completion date is September 12, 1974.
The Division of Engineering agrees that the requested extension of time
is justified.
The extension of time, if approved, will extend the contract completion
date to October 10, 1974.
ATTACHED:
Resolution [X]
Ordinance [ ]
Agreement [ ]
Plat [ ]
See EXHIBITS ~] No. 1
Financial Statement:
N.A.
Commission-Board Recommendation:
N.A.
Department Head Recommendation:
Recommend approval of 20 working days extension of time, making the
contract completion date October 10, 1974.
City Manager Recommendation:
Concur