HomeMy WebLinkAboutAgenda Statement 1974/08/13 Item 22
AGENDA ITEM NO. [22 ]
CHULA VISTA CITY COUNCIL MEETING OF: August 13, 1974
ITEM TITLE: Resolution - Granting Extension of Time for Remodeling Chlorine
Room at Memorial Park
INITIATED BY: Director of Public Works/City EngineerE
BACKGROUND
R. W. Kurtz, contractor for the remodeling of the chlorine room at
Memorial Park, by his letter dated July 30, 1974, has requested a
12-day extension of contract time. The contract completion date is
July 31, 1974.
Ever since award of the contract, the contractor has had difficulty in
getting a firm commitment for the delivery date of the doors as speci-
fied. His supplier, Ekstrom Industries, indicates that if there are
no shipping or transit delays the doors should be available by August
12, 1974.
The City Council, by Resolution 7378, approved a change order to the
contract for remodeling the chlorine room, adding the installation of
a chlorine scale. The contractor, in his letter, has indicated that he
should have the chlorine scale installed on or about August 9, 1974.
The Department of Public Works has investigated his request and feels
that the contractor cannot complete the work by August 12, 1974. It
is requested that a 3D-day extension of time be approved. The 3D-day
extension of time will extend the contract completion date to August
30, 1974.
ATIACHED:
Resolution [~
Ordinance [ ]
Agreement [ ]
Plat [ ]
See EXHIBITS [xl NO.1
Financial Statement:
N.A.
Commission-Board Recommendation:
N.A.
~artment Head Recommendation:
Recommend approval of 3D-day extension of time, changing the contract
completion date to August 30, 1974.
City Manager Recommendation:
Concur
'lf7~ JC