HomeMy WebLinkAboutReso 2010-089RESOLUTION NO. 2010-089
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA AUTHORIZING AND DELEGATING THE
CITY ATTORNEY AND DIRECTOR OF PUBLIC WORKS TO
ENTER INTO A COOPERATIVE AGREEMENT WITH THE
STATE OF CALIFORNIA DEPARTMENT OF
TRANSPORTATION REGARDING PRELIMINARY
ENGINEERING DESIGN, ENVIRONMENTAL, AND TRAFFIC
ANALYZING ACTIVITIES ON THE STATE ROUTE 125
FUTURE INTERCHANGES AT ROCK MOUNTAIN AND
OTAY VALLEY ROAD
WHEREAS, the City desires to enter into a Cooperative (COOP) Agreement with State
of California Department of Transportation (Caltrans) for the purpose of conducting preliminary
engineering and traffic analysis, a Project Initiation Document (PID) to determine the geometric
design and right-of--way needed, environmental cleazance, and construction cost estimates for up
to two potential interchanges on SR-125 at Rock Mountain Road and Otay Valley Road; and
WHEREAS, proposed tentative maps show the necessity for the construction of up to two
potential interchanges on SR-125 at Rock Mountain Road and Otay Valley Road to serve future
developments; and
WHEREAS, the preliminary study and design, will determine if it is feasible to construct
the interchanges so close together and/or an additional determination is needed that will waive
this requirement; and
WHEREAS, the approval of the tentative maps is awaiting the decision to construct
either of the two interchanges or just the Rock Mountain Road interchange; and
WHEREAS, the Transportation Development Impact Fee (TDIF) Program for eastern
Chula Vista lists two bridge deck projects across State Route 125 at Rock Mountain Road and at
Otay Valley Road; and
WHEREAS, approval of the tentative maps is awaiting the decision to construct either of
the two interchanges or just the Rock Mountain Road interchange; and
WHEREAS, Califomia Streets and Highways Code Sections 114 and 130 authorize
agencies to enter into a cooperative agreement for performance of work within the State
Highway System (SHS) Right- of-Way; and
WHEREAS, Government Code Section 65086.5 authorizes Caltrans to prepaze the PID
as reimbursed work. It also mandates that Caltrans review and approve the PID developed by
others and be reimbursed for the effort; and
Resolution No. 2010-089
Page 2
WHEREAS, the final agreement will specify the responsibilities of both agencies in
regards to completing the PID as a joint effort between Caltrans and the City of Chula Vista; and
WHEREAS, the total project cost of $300,000 will be funded from the TDIF Program
funds of which up to $236,000 is for Caltrans' cost for preparation of the PID preliminary
engineering while the remaining $64,000 will be for City staff time.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Chula
Vista does hereby authorize and delegate the City Attorney and Director of Public Works to
enter into a Cooperative Agreement with Caltrans regazding preliminary engineering design,
environmental, and traffic analyzing activities on the State Route 125 future interchanges at
Rock Mountain and Otay Valley Road.
Presented by
~~
'chazp,CA. 9 tins
Director of Public Works
Approved as to form by
Attorney
PASSED, APPROVED, and ADOPTED by the City C~duncil of the City of Chula Vista,
California, this 20th day of Apri12010 by the following vote:
AYES: Councilmembers: Bensoussan, Castaneda, Ramirez, Thompson and
Cox
NAYS: Councilmembers: None
ABSENT: Councilmembers: None
ATTEST:
NC (o
Donna R. Norris, MC, rty Clerk
STATE OF CALIFORNIA
COUNTY OF SAN DIEGO
CITY OF CHULA VISTA
Cheryl Cox Ma or
I, Donna R. Norris, City Clerk of Chula Vista, California, do hereby certify that the foregoing
Resolution No. 2010-089 was duly passed, approved, and adopted by the City Council at a
regulaz meeting of the Chula Vista City Council held on the 20th day of April 2010.
Executed this 20th day of April 2010.