1. PUBLIC HEARING: PCM-89-2 Consideration of a proposed precise
plan within the IL-P zone for Otay Rio Business
Park - Otay Rio Business Park (Continued)
OTHER BUSINESS
DIRECTOR'S REPORT
COMMISSION COMMENTS
ADJOURNMENT AT p.m. to the Regular Business Meeting of November 9, 1988
at 7:00 p.m. in the Council Chambers
City Planning Commission
Agenda Item for Meeting of October 26, 1988 Page 1
1. PUBLIC HEARING: PCM-89-2 - Consideration of a proposed precise plan
within the IL-P zone for Otay Rio Business Park - Otay
Rio Business Park {Continued)
A. BACKGROUND
On July 28, 1987 the City Council granted a request for a general plan
amendment, rezone and subdivision of 211 acres for industrial uses, for the
project known as Otay Rio Business Park located in the extreme southeast
corner of the City. The project site is bounded on the east by Otay Valley
Road and on the north by the Otay River. Approximately 132 acres were
designated IL-P limited industrial, with certain support commercial uses as
provided in the zoning ordinance upon approval of a master conditional use
permit. The applicant has now submitted a precise plan to establish planning
and design standards for development within the IL-P zone.
An Environmental Impact Report was prepared for the project and was
certified by the Planning Commission on June 24, 1987. The Environmental
Review Coordinator has determined that no additional environmental review is
required for the proposed precise plan at this time.
B. RECOMMENDATION
1. Based on the findings contained in Section D of this report, adopt a
motion to approve the proposed precise plan for Otay Rio Business
Park subject to the following conditions of approval:
a. The typical road section for Otay Valley Road shown on page 11
shall be revised to conform to that approved for the tentative
subdivision map (Tract 87-6).
b. The second paragraph of page 1 discussing environmental
regulation shall be revised to state that individual projects
that are in substantial conformance with the Precise Plan may
proceed with site plan and building design review and/or other
discretionary actions with supplemental environmental
documentation, as determined by the Environmental Review
Coordinator.
c. The text which discusses project identity signs (la. page 31) of
the precise plan guidelines shall be revised to eliminate total
permitted aggregate sign area of 3 square feet of sign area for
each lineal foot of building frontage.
d. Revise the second paragraph of page 20 discussing revegetation
and fencing of lot 83 to delete the timing of the revegetation
to future residential development.
City Planning Commission
Agenda Item for Meeting of October 26, 1988 Page 2
C. ANALYSIS
The proposed precise plan guidelines submitted by Otay Rio Business Park
were developed through continued consultation with planning staff. The
precise plan text was written to provide development and design guidelines and
serve as an informational document to prospective tenants within the
industrial park.
The project guidelines, land uses, circulation, landscape and design
standards are generally self explanatory. Some aspects of the guidelines
which should be highlighted include: the potential for development of
commercial support uses through approval of a master conditional use permit,
areas to be included in an open space maintenance district, setbacks and
buffers, and architectural and site design guidelines.
Commercial Support Uses
Within the IL-P zone, specified commercial uses would be permitted to
occur in the vicinity of the northeast corner of the project (lot 3) subject
to approval of a master conditional use permit. Those uses are intended as
support facilities for the surrounding industrial park and are discussed on
page 6 of the Precise Plan. The development standards specified for a support
commercial project would be required in addition to design review approval and
conditions of approval of the CUP. Proposed setbacks and buffers reflect the
proximity of lot 3 to Otay Valley Road and the Otay River.
Open Space Maintenance District
Otay Rio Business Park contains approximately 73 acres of land designated
for inclusion in an open space maintenance district. The majority of the
southern portion of the project is to be revegetated and fenced to prevent
future erosion. The timing of revegetation is controlled by the agreement for
public improvements to be negotiated with the City. A riparian habitat area
designated in the northwest corner of the project would also be maintained in
the same district, as would designated 3:1 slopes along the frontage for Otay
Valley Road. The Precise Plan includes extensive discussion of landscape
standards to be applied to these areas through the landscape master plan, as a
component of the developers responsibilities in forming the Open Space
District.
Setbacks and Buffers
The setbacks and landscape buffers to be applied by the Precise Plan
(pages 9-12) reflect the project's visual exposure to the Otay River and Otay
Valley Road. Additional landscape buffers would be provided on the western
project boundary for the lots between the riparian open space and the southern
open space area. Standards are provided through the Master Landscape Plan,
(p. 15-22).
City Planning Commission
Agenda Item for Meeting of October 26, 1988 Page 3
Architectural and Site Design Guidelines
The guidelines for architecture are general and do not prescribe any
specific theme or style (p. 24-29). The stated intent is to ensure
consistency in design throughout the park and to give a well maintained
appearance. For example, building design policy guidelines are structured to
limit height, bulk, and building mass. Building standards include the
prohibition of florescent or garish colors and prescribe at least two types of
building texture or materials. Outdoor storage is limited to 20% of the total
gross floor area with specified exceptions. Any specific proposals for
development are subject to Design Review approval.
Signs
The proposed sign program allows each business a ground sign up to 50 sq.
ft. (maximum) and a wall sign up to 50 sq. ft. (maximum) for an aggregate
total of 100 sq. ft. Based on these restrictions, the added provision of
allowing for 3 sq. ft. of sign area for each lineal foot of building area
represents a potential conflict and, therefore, is recommended to be deleted.
In summary, the proposed precise plan document provides a framework for
specific evaluation of individual projects while providing a generalized users
guide for approaching development within the park. It is staff's
recommendation to approve the document as conditioned.
D. FINDINGS
The subject property, or the neighborhood or area in which the property is
located is unique by virtue of topography, 9eolo§ical characteristic, access,
configuration, traffic circulation or some social or historic situation
requiring special handling of the development on a precise plan basis.
The 211-acre project area exhibits extremes in topography ranging from
steep slopes to level flood plain, requiring implementation of design policies
to ensure sensitive treatment of unique property features through the proposed
setbacks, buffers; landscaping and open space maintenance areas defined
through the precise plan.
The property or area to which the P modifying district is applied is an
area adjacent and contiguous to a zone allowing different land uses and the
development of a precise plan will allow the area so designated to coexist
between land usages which might otherwise be incompatible.
The project area is situated between the floodplain and floodway zoned
regions of the Otay River Valley and residential planned areas within the
boundaries of the City of San Diego. The precise plan is required to maintain
a harmonious balance between widely divergent land uses.
City Planning Commission
Agenda Item for Meeting of October 26, 1988 Page 4
The basic or underlying zone regulations do not allow the property owner
and/or the City appropriate control or flexibility needed to achieve an
efficient and proper relationship among the uses allowed in the adjacent
zones.
The blending of commercial support uses within the project area in
conjunction with adjacent industrial, residential, and open space areas is
more consistently applied through guidelines for land uses developed for the
proposed precise plan.
WPC 5539P
Appendix C
CITY OF CHULA VISTA
DISCLOSURE STATE~NT
APPLICANT'S STATEMENT OF DISCLOSURE OF CERTAIN OWNERSHIP INTERESTS ON ALL APPLICATIONS
IWHICH WILL REQUIRE DISCRETIONARY ACTION ON THE PART OF THE CITY COUNCIL, PLJ~NNING
~COMMiSSION AND ALL OTHER OFFICIAL BODIES.
The following information must be disclosed:
1. List the names of all persons having a financial interest in the application.
Otaly Rio Business Park, A Joint Venture
Otas Rio Business Park I, A Joint Venture
List the names of all persons having any ownership interest in the property involved.
The Chillingworth Corporation DcKA Investments, LTD.
Amalgamated Citrus Growers, Inc.
Liebau Investments, LTD.
2. If any person identified pursuant to {1) above is a corporation or partnership, list
the names of all individuals owning more than 10% of the shares in the corporation
or owning any partnership interest in the partnership.
The Chillingworth Corporation- S.C. Chillingworth
Amalgamated Citrus Growers, Inc. - B.J. Holmes
Liebau Investments, LTD. - F.J. Liebau DcKA Investments, LTD. - B.J. Holmes
3. If any person identified pursuant to (1) above is a non-profit organization or a
trust, list the names of any person serving as director of the non-profit
organization or as trustee or beneficiary or trustor of the trust.
4. Have you had more than $250 worth of business transacted with any member of City
staff, Boards, Commissions, Con~nittees and Council within the past twelve months?
Yes No X If yes, please indicate person{s)
IPerson i~efi~ed as: "Any individual, firm, copartnership, joint venture, association, i
social cmuD, traternal organization, corporation, estate, trust, receiver, syndicate,
this and any other county, city and county, city, municipality, district or other
political subdivision, or any other group or combination acting as a unit."
(NOTE: Attach additional pages as necessary.) Otay Rio Business Park
Tha ChilllnFn~qrth ~nrnnr~tinn ~/~/88
Sign~t_'~h~ ~_~apP¥icant/date
WPC 0701P Robert H. McCrarv. Jr. "~\
A-110 Pti ..... J
n[ or [ype name of applicant