Loading...
HomeMy WebLinkAboutAgenda Statement 1980/12/09 Item 9 COUNCIL AGENDA STATEMENT Itent 9 ' Meeting Date 12-9-80 ITEM TITLE: Resolution !P33l1'Extending the contract for the installation of street lights on Third and Fourth Avenues until .May 1, 1981 SUBMITTED BY,: City Engineer Odtl (4/5ths Vote: Yes No~J The installation of the strerr'li9hts on Third Avenue (between "H" and "I" Streets) and on Fourth Avenue (between "F" and "G" Streets) was supposed to be complete by December 1, 1980 (in accordance with contract extension - resolution 10307). However, SDG&E has informed the City that the underground electrical service for the street lights on Third Avenue will not be energized until April 15, 1981. Therefore it is necessary to extend this contract to allow the contractor time to make the electrical connections after the service points are energized. It is my RECOMMENDATION: That Council approve an extension of this contract until May 1, 1981. BOARD/COMMISSIONS RECOMMENDATION: N/A DISCUSSION: The contract for installation of City owned street lights on Third and Fourth Avenues was awarded to Perry Electric in July 1980. The lights are being installed in conjunction with utility undergrounding on those streets. The original SDG&E underground conversion project schedule called for energizing of the underground service points in October 1980. The contract completion date, including a time extension requested by Perry Electric due to a delay in receipt of material, ran through December 1, 1980. SDG&E has recently informed the City that the underground service points on Third Avenue next to the County Court facility will not be energized until April 15,1981. This delay is due to problems associated with Court construction and reorganization efforts at SDG&E. Perry Electric has completed the installation of all conduit, poles, and luminaires. The only work remaining is to connect the system to the new power source to be provided by SDG&E. I believe there is adequate justification to extend the contract time limit. The contractor has virtually completed his work and now must wait several months for SDG&E to provide the power source. The normal contract procedure is to withhold 10 percent of the contract amount until 35 days after acceptance of the work by City Council. To follow the normal procedure in this case, I believe, would be unfair and may place the City in a position of owing the contractor extra funds. The contractor and I agree that the best solution would be to pay the contractor his entire amount due less $500 which is the estimated cost of move-in to make the electrical connection. The Council would not accept the contract until May 1981 after the lights have been tested and are operating. The City is. adequately protected since we will not release the bonds for performance and material and labor until 35 days after the work is officially accepted by City Council. FINANCIAL IMPACT: The City will hold $500 of the contract cost of $32,647 until the project has been completed. There will be no additional cost to the City due to this contract extension. JPL:GRH:nr/BR-003 Form A-113 (Rev. 11/79) )0"331 EXHIBITS Agreement_____ Resolution~ Ordinance_____ Plat_____ Notification List Other ENVIRONMENTAL DOCUMENT: Attached Submitted on a.. .A;6.Ji..1 ", ~ ~- r by the City Council ?f Chula Vista, California Dated /~-?"i'o