ITEM TITLE: Resol ution /0;1.'1'1 Accepting public improvements, Street
Overlay progam~1980-81 - Various Streets within City of
Chula Vista
SUBMITTED BY: Ci ty Eng ineer ~ · . (4/5ths Vote: Yes_ N01L-)
Daley Corporation has completed the construction of the Street Overlay
Program 1980-81 - Various Streets within City of Chula Vista,
California. It is my
RECOMMENDATION: That Council adopt resolution accepting the public
improvements.
BOARD/COMMISSION RECOMMENDATION: Not applicable.
DISCUSSION:
Daley Corporation has completed the overlay of various streets within
the 1980-81 Street Overlay Program. All work was done in accordance
with the contract documents awarded August 12, 1980, by Resolution
10237. The contract is dated September 8, 1980.
A final inspection was made September 24, 1980 and all work was
completed to the satisfaction of the City Engineer. There is a tonnage
overrun of 100.16 tons or 6 percent of the contract quantity which
amounts to $3,359.72.
FISCAL IMPACT:
Authorized expenditure - $57,000
Contract amount - $51,891.50
Final construction cost - $55,251.22
DMH:fpw/A0020
tlf'f'--<-I J~ ~
by the City Council of
Chula Vista, California
Dated /tJ-/4 -ro
/02-9 </
Form A-113 (Rev. 11/79)
EXHIBITS
Agreement_ Resolution X Ordinance Plat.'X Notification List
Other
ENVIRONMENTAL DOCUMENT: Attached
Submitted on
I
I
I
I
I
i
. .