HomeMy WebLinkAboutReso 2009-259RESOLUTION NO. 2009-259
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA AWARDING A CONTRACT FOR THE
DEVELOPMENT OF BIKEWAY MASTER PLAN UPDATE TO
KTU+A IN AN AMOUNT NOT TO EXCEED $149,685
WHEREAS, in order to receive State and regional funding for bicycle improvements, the
City needs to have a Bikeway Master Plan approved within the past five years. Council
approved the last Bikeway Master (Plan) on January 19, 2005; and
WHEREAS, the City has received a $150,000 Transportation Development Act (TDA)
grant from the San Diego Association of Governments (SANDAG) and has appropriated an
additional $50,000 in TransNet funds to fund the prepazation of an update to the plan. These
funds were appropriated by Council as part of the Fiscal Year 2009/2010 Capital Improvement
Program (CIP) project STL-351; and
WHEREAS, City staff advertised the project on June 19, 2009, distributed a Request for
Proposals for Development of a Bikeway Master Plan and conducted a Consultant selection
process in accordance with Section 2.56.110 of the Chula Vista Municipal Code. Four proposals
were received, and all four proposals met the City's minimum qualifications; and
WHEREAS, on August 21, 2009, the City's selection panel (Panel) interviewed the four
firms that submitted proposals. The following are the results of the interview process:
Firm Final Cost Proposal
Rank
KTU+A, San Diego, Califomia 1 $149,685
Alta Planning + Design, San Diego, California 2 $148,145
Rick Engineering Company, San Diego, California 3 $167,310
Darnell & Associates, San Diego, California 4 $149,850
WHEREAS; three of the four firms, including KTU+A, submitted cost proposals below
the $150,000 allocated by SANDAG; and
WHEREAS, based on their extensive experience in prepazing similar plans in the San
Diego region, the qualifications of their key staff members, and their understanding of bikeway
issues in Chula Vista, the Panel has determined that KTU+A is the most qualified firm to prepaze
the Bikeway Master Plan.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Chula
Vista does hereby award a contract for "Bikeway Master Plan Update (STL351)" to KTU+A in
an amount not to exceed $149,685.
Resolution No. 2009-259
Page 2
Presented by
Approved as to form by
Richazd A. opl B . Miesfg)
Director of Public orks City Attorn
PASSED, APPROVED, and ADOPTED by the City Council of the City of Chula Vista,
California, this 3rd day of November 2009 by the following vote:
AYES: Councilmembers: Bensoussan, Castaneda, Ramirez, Thompson and
Cox
NAYS:
ABSENT:
ATTEST:
0
Donna R. Norris, M ,City Clerk
STATE OF CALIFORNIA
COUNTY OF SAN DIEGO
CITY OF CHULA VISTA
Cheryl Cox, May
I, Donna R. Noms, City Clerk of Chula Vista, California, do hereby certify that the foregoing
Resolution No. 2009-259 was duly passed, approved, and adopted by the City Council at a
regular meeting of the Chula Vista City Council held on the 3rd day of November 2009.
Executed this 3rd day of November 2009.
Councilmembers: None
Councilmembers: None
,~~ ~,,~~
Donna R. Norris, CMC, City Clerk