HomeMy WebLinkAbout2009/11/17 Item 9TY COUNCIL
STATEMENT
~,~;~ CITY OF
CHULA VISTA
11/17/09, Item
ITEM TITLE: RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA ACCEPTING BIDS AND AWARDING A
CONTRACT FOR THE "AUTO PARK SEWER PUMP STATION
DECOMMISSIONING IN THE CITY OF CHULA VISTA,
CALIFORNIA (SW219D)" PROJECT TO A. B. HASHMI, INC. IN
THE AMOUNT OF $229,050.50 AND AUTHORIZING THE
DII2ECTOR OF PUBLIC WORKS TO EXPEND AVAILABLE
CONTINGENCY FUNDS AS NECESSARY TO COMPLETE THE
PROJECT IN ACCORDANCE WITH QTY STANDARDS
SUBMITTED BY: DIRECTOR OF PUBLIC WORKS
ASSISTANT DIRECT R OF ENG
REVIEWED BY: CITY MANAGE
ASSISTANT CITY ANAGER S-
4/STHS VOTE: YES ^ NO
SUMMARY
On September 16, 2009, the Director of Public Works received seven (7) sealed bids for the
"Auto Park Sewer Pump Station Decommissioning in the City of Chula Vista (SW219D)"
project. The project will decommission an existing Auto Park Sewer Pump Station and connect
the existing sewer that serves the Auto Pazk to a downstream gravity sewer system in the
Crossings Shopping Center parking lot. The proposed action would award a contract for
decommissioning of the Auto Park Sewer Pump Station and authorize the Director of Public
Works to expend available contingency funds, as may be necessary to complete the project in
accordance with City standards.
ENVIRONMENTAL REVIEW
The Environmental Review Coordinator has reviewed the proposed project for compliance with
the California Environmental Quality Act (CEQA) and has determined that the project was
covered in the previously certified Salt Creek Gravity Sewer Interceptor Final Program
Environmental Impact Report (FEIR 01-03). A component of the overall project involving the
actual removal and decommissioning of the existing sewer pump station was not cleazly
addressed in FEIR 01-03 and resulted in the need for further environmental analysis. The
environmental review analyzed all the changed circumstances and the new detailed information
associated with the sewer pump station decommissioning process. The Environmental Review
Coordinator has determined that only minor technical changes or additions to FEIR 01-03 are
necessary and that none of these changes create the conditions requiring the preparation of a
Subsequent or Supplemental EIR pursuant to CEQA Guidelines, Sections 15162 and 15163.
9-1
11/17/09, Item
Page 2 of 3
Therefore, the Environmental Review Coordinator has prepared an addendum pursuant to
Section 15164(a) of the State CEQA Guidelines to this document, Salt Creek Gravity Sewer
Interceptor Final Program Environmental Impact Report (FEIR 01-03).
RECOMMENDATION
Council adopt the resolution.
BOARDS/COMMISSION RECOMMENDATION
Not applicable.
DISCUSSION
On September 16, 2009, the Director of Public Works received seven (7) sealed bids for the
"Auto Park Sewer Pump Station Decommissioning in the City of Chula Vista (SW219D)"
project. The project will decommission the existing Auto Park Sewer Pump Station and connect
the existing sewer that discharges to the pump station to a gravity sewer system in The Crossings
Shopping Center parking lot. The project's location is shown in Attachment 1.
On September 16, 2009, staff received and opened bids from seven (7) contractors:
CONTRACTOR BID AMOUNT
1. A. B. Hashmi, Inc. -Oceanside, CA $ 229,050.50
2. Cass Construction, Inc. - El Cajon, CA $262,939.00
3. RMV Construction, Inc. -San Diego, CA $ 273,504.57
4. Valley Coast Construction, Inc. -San Diego, CA $276,697.00
5. Palm Engineering & Construction Co., Inc. -San Diego, CA $277,000.00
6. MJC Construction, Inc. -National City, CA $304,219.00
7. NEWest Construction Company, Inc. -San Diego, CA $310,325.00
The low bid by A. B. Hashmi, Inc. is $229,050.50, which is $70,949.50 (24%) below the
Engineer's estimate of $300,000. The Engineer's estimate was calculated by the consultant,
Dudek & Associates, and based on average prices for similar types of work completed in the
past. Staff verified the references provided by the contractor and this contractor has also
previously worked for the City. A. B. Hashmi, Inc.'s work record is satisfactory. Staff
recommends awarding a public works contract in the amount of $229,050.50 to A. B. Hashmi,
Inc. of Oceanside, California.
Disclosure Statement
A copy of the Contractor's Disclosure Statement is attached herewith (Attachment 2).
9-2
11/17/09, Item
Page 3 of 3
Wade Statement
The contractors who bid on this project were not required to pay prevailing wages to persons
employed by them for the work performed under this project. No special minority or women-
owned business requirements were necessary as part of the bid. However, a "Notice to
Contractors" was sent to various trade publications in order to encourage disadvantaged
businesses to bid on the project.
DECISION MAKER CONFLICT
Staff has reviewed the property holdings of the City Council and has found no property holdings
within 500 feet of the boundaries of the property that is the subject of this action.
CURRENT FISCAL IMPACT:
FUNDS REQUIRED FOR CONSTRUCTION
A. Contract Amount $229,050.50
B. Contingencies (approximately 10%) $30,000.00
C. Staff Costs (Inspection) $20,000.00
TOTAL $279,050.50
Sufficient Trunk Sewer Funds are in the SW219 project account to complete construction.
ONGOING FISCAL IMPACT:
Upon completion of the decommissioning project, savings will be realized in utility and pump
station maintenance costs, and the new gravity sewer system will only require routine City sewer
maintenance.
ATTACHMENTS
1. Location Map
2. Disclosure Statement
Prepared by.' Kirk Ammerman, Principal Civil Engineer, Paibdic Wanks -Engineering, L L-03-09, 5.'25 pm
M:IEngineerlAGENDAICAS20091lL-17-091SW219DAlL3 Award /l-L7-09.dac
9-3
ATTACHMENT l
w
4
w
z
r
0
z
o ~ No scA~E
805 C0
~~
`~~
~~
MAIN ST
-AUTO PARK DR
~~`J _ - _ OJgY RIVER
~ - - -- -
' PROJECT
- ', LOCATION
LOCATION MAP
9-4
P,TTACHMfNT ~
City of Chula Vista Disclosure Statement
Pursuant to Council Policy 101-01, prior to any action upon matters that will require discretionary action
by the Council, Planning Commission and all other official bodies of the City, a statement of disclosure of
certain ownership or financial interests, payments, or campaign contributions for a City of Chula Vista
election must be filed. The following information must be disclosed:
1. List the names of all persons having a financial interest in the property that is the subject of the
application or the contract e.g.; owner, applicant, contractor, subcontractor, material supplier.
1~1-h Ike N-~CS M Ma - ~~ 4 Sc2.
~h~R kkM~NM~ - ~-~
2. If any person* identified pursuant to (I) above is a corporation or partnership; list the names of all
individuals with a $2000 investment in the business (corporation/partnership) entity.
Pc H4MR+~ N~KS N M 1
3. If any person* identified pursuant to (1) above is anon-profit organization or trust, list the names
of any person serving as director of the non-profit organization or as trustee or beneficiary or
trustor of the trust.
N ~-~
4. Please identify eveq' person, including any agents, employees, consultants, or independent
contractors you have assigned to represent you before the City in this matter.
N~~:1A N-PC~HMi - (~C-~
5. Has any person* associated with this contract had any financial dealings with an official** of the
City of Chula Vista as it relates to this contract within the past 12 months? Yes No /
35
M:\General $en•ices\Desi~nl41I ProjectslSNgs\~'?19\5~~'?19 Auto Park Sewer\Spec Doc~SW?19 Auto Park Sewer Pump Swoon
Decom.Revised.doc
9-5
If Yes, briefly describe the nature of the financial interest the of&cia]** may have in this contract.
6. Have you made a contribution of more than $250 within the past twelve (12) months to a current
member of the Chula Vista Cit}' Council? No / yes _ If yes; which Council member?
Have you provided more than $340 (or an item of equivalent value) to an official** of the City
of Chula Vista in the past twelve (12) months? (This includes being a source of income, money to
retire a legal debt; gift loan, etc.) Yes _ No /
If Yes, which official** and what was the nature of item provided?
Date: ~ ~ 1 b~ J~ 1 +^" ` ^
Signatur of Contractor/Applicant
(~ . R . 41-!X5 w~ r ,~~c .
Print or type name of Contractor/Applicant
Person is defined as: any individual, firm, co-partnership; joint venture, association, social club,
fraternal organization; corporation; estate, trust receiver, syndicate, any other county, cit)',
municipality, district, or other political subdivision, -or any other croup or combination acting as
a unit.
** Official includes; but is not limited to: Mayor, Council member; Planning Commissioner,
Member of a board. commission, or committee of the City, employee, or staff members.
16
M:\General Sen•ices\Desi~nl411 Projects\SwSg219\SW?19 Auto Park SewerlSpec Doc\5\~'?19 Auto Park Ser~~cr Pump Station
Decom.Re~•ised.doc
9-6
RESOLUTION NO.2009-
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA ACCEPTING BIDS AND AWARDING A
CONTRACT FOR THE "AUTO PARK SEWER PUMP
STATION DECOMMISSIONING IN THE CITY OF CHULA
VISTA, CALIFORNIA (SW219D)" PROJECT TO
A. B. HASHMI, INC. IN THE AMOUNT OF $229,050.50; AND
AUTHORIZING THE DIRECTOR OF PUBLIC WORKS TO
EXPEND AVAILABLE CONTINGENCY FUNDS AS
NECESSARY TO COMPLETE THE PROJECT IN
ACCORDANCE WITH CITY STANDARDS
WHEREAS, on September 16, 2009, the Director of Public Works received seven (7)
sealed bids for the "Auto Park Sewer Pump Station Decommissioning in the City of Chula Vista
(SW-219D)" project; and
WHEREAS, the project will decommission an existing Auto Park Sewer Pump Station
and connect the existing sewer that serves the Auto Park to a downstream gravity sewer system
in the Crossings Shopping Center parking lot; and
WHEREAS, the project will include all labor, material, equipment, tools, transportation,
mobilization, control of sewage flow, install root barrier, traffic control, removal and disposal of
existing improvements, protection and restoration of existing improvements, and other
miscellaneous work necessary for the project; and
WHEREAS, on July 17, 2001, the Chula Vista City Council approved Resolution No.
2001-218 certifying the Final Environmental Impact Report (FEIR) and adopting the Findings of
Fact and the Mitigation and Monitoring Program for the Salt Creek Gravity Interceptor Sewer;
and
WHEREAS, on Mazch 27, 2009, the California Regional Water Quality Control Board
(RWQCB) issued Clean Water Act Water Quality Certification No. 08C-053 for the work in and
adjacent to the earthen drainage channel; and
WHEREAS, the California Department of Fish and Game issued Streambed Alteration
Agreement Notification #1600-2008-0250-RS for this project; and
WHEREAS on September 16, 2009, staff received bids from seven (7) contractors as
follows:
CONTRACTOR BID AMOUNT
1. A. B. Hashmi, Inc. - Oceanside, CA $ 229,050.50
2. Cass Construction, Inc. - EI Ca on, CA $262,939.00
3. RMV Construction, Inc. - San Diego, CA $ 273,504.57
4. Valle Coast Construction, Inc. - San Die o, CA $276,697.00
5. Palm Engineering & Construction Co., Inc. -San Diego, CA $277,000.00
6. MJC Construction, Inc. -National City, CA $304,219.00
7. NEWest Construction Com an ,Inc. -San Die o, CA $310,325.00
9-7
WHEREAS, the low bid by A. B. Hashmi, Inc. is $229,050.50, which is $70,949.50
(24%) below the Engineer's estimate of $300,000; and
WHEREAS, staff verified the references provided by the contractor and this contractor
has also previously worked for the City and their work record is satisfactory; and
WHEREAS, this resolution will increase the Director of Public Works Operations
authority to approve change orders as necessary to complete the project without returning to
Council, thus saving staff cost and construction time; and
WHEREAS, sufficient funds were previously appropriated under Fiscal Year 2007/2008
and Fiscal Year 2008/2009 Capital Improvement Program (CIP) budgets for this projects.
NOW, THEREFORE BE IT RESOLVED, that the City Council of the City Chula Vista
does hereby accept bids; award a contract for the "Auto Park Sewer Pump Station
Decommissioning in the City of Chula Vista, California (SW219D)" Project to A. B. Hashmi,
Inc. in the amount of two hundred twenty-nine thousand fifty dollars and fifty cents
($229,050.50); and authorize the Director of Public Works to expend available contingency
funds as necessary to complete the project in accordance with City standards.
Presented by Approved as to form by
Richard A. Hopkins
Director of Public Works
G "
Bart Miesfe
City Attorney
s-a