HomeMy WebLinkAbout2008/11/25 Item 7 CITY COUNCIL AGENDA STATEMENT ~\(f~ CITY OF ~CHULA VISTA 11/25/08, Item i SUBMITTED BY: PlJBLIC HEARING TO CONSIDER WANING DEFECTS IN THE BID RECENED FOR THE "SEWER REHABILITATION PROGRAM-PHASE 2, FISCAL YEAR 2005/2006 TO FISCAL YEAR 2007/2008 VARIOUS LOCATIONS IN THE CITY OF CHULA VISTA, CALIFORNIA (SW250B)" PROJECT PER CITY CHARTER SECTION 1009 RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA VIST A WANING DEFECTS IN THE BID, ACCEPTING BIDS AND AWARDING CONTRACT FOR THE "SEWER REHABILITATION PROGRAM-PHASE 2, FISCAL YEAR 2005/2006 TO FISCAL YEAR 2007 /2008 VARIOUS LOCATIONS IN THE CITY OF CHULA VISTA, CALIFORNIA (SW250B)" PROJECT TO BURTECH PIPELINE, INC. IN THE AMOUNT OF $574,176.50 RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA AUTHORIZING THE TRANSFER OF AVAILABLE SEWER FACILITY REPLACEMENT FUNDS INTO "SEWER REHABILITATION PROGRAM - PHASE 2, FISCAL YEAR 2005/2006 TO FISCAL YEAR 2007/2008 VARIOUS LOCATIONS IN THE CITY OF C~A VISTA (SW250B)" DIRECTOROFENGINEERIN~ DIRECTOR OF PUBLIC WORKS ~r ITEM TITLE: REVIEWED BY: ~ INTERIM CITY MANAGER 7/ 4/5THS VOTE: YES 0 NO [gJ SUMMARY On October 15, 2008, the Director of Engineering received three sealed bids for the "Sewer Rehabilitation Program - Phase 2, Fiscal Year 2005/2006 to Fiscal Year 2007/2008 various locations in the City of Chula Vista (SW250B)" project. The project will replace existing broken sewer mains and laterals, repair cracked sewer lines, and replace asphalt concrete pavement in various locations throughout the City. ENVIRONMENTAL REVIEW The Environmental Review Coordinator has reviewed the proposed project for compliance with the California Environmental Quality Act and has determined that the project qualifies for a Class I categorical exemption pursuant to Section 15301 (Existing Facilities) of the State CEQA 7-1 11/25/08, Item L Page 2 of 4 Guidelines because the project involves repairing and replacing where necessary, existing sewer facilities. Thus, no further environmental review is necessary. RECOMMENDATION Council conduct the public hearing and adopt the resolutions. BOARDS/COMMISSION RECOMMENDATION Not applicable. DISCUSSION On April 15, 2008, City Council awarded the Sewer Rehabilitation Program - Phase I (SW240A) project (Resolution 2008-096) to KTA Construction, Inc. Due to staffing constraints, the annual rehabilitation project was broken into two phases for ease of management. Currently, the Sewer Rehabilitation Program-Phase I is nearing the completion of its contract. For Phase I, eighty- five percent (85%) of the repairs were located within the west side of Chula Vista and the remaining fifteen (15%) percent were located in the east side ofI-805 Freeway. With Phase I nearing completion, staff prepared documents for the construction of Phase 2. Locations for Phase 2 are based on the results of compiled data inspections, including those performed with a closed circuit television camera. From these data inspections, a list of sewer mains in need of the rehabilitation was recommended. Certain sections of pipe are cracked and need to be replaced, repaired or relined to prevent groundwater infiltration or leaching of raw sewage into the ground. Also, a number of the sewer access manholes were identified by the Public Works Department as requiring replacement. The general scope of the project involves the replacement of existing broken sewer mains and laterals, the installation of pipe lining to repair cracked sewer lines, the replacement of sewer access holes, trenching, and asphalt concrete pavement. This annual project will include all labor, material, equipment, tools, transportation, mobilization, control of sewage flows, traffic control, removal and disposal of existing improvements, protection and restoration of existing improvements, and other miscellaneous work necessary for the project. The locations and types of work to be done for Phase 2 of the annual Sewer Rehabilitation program are detailed in Tables A through C (Attachment I). The method used for the rehabilitation of the City's sewer mains and laterals employs a cure in placement procedure. This method is a specialty liner designed to seal connections on lined pipe less than 24 inches in diameter. It is a fiberglass laminate fully impregnated with an ultra violet curing resin which is installed using equipment that inflates and pushes the liner into the connection, leaving a 2 to 3-inch brim in the main pipe. Installed from inside the main pipeline after lateral reopening, it provides a watertight seal at the connection. It also stops infiltration of ground water, which can cause overloading of treatroent plants and ex-filtration of sewer water into the ground. On October 15, 2008, the Director of Engineering received three bids for the "Sewer Rehabilitation Program - Phase 2, Fiscal Year 2005/2006 to Fiscal Year 2007/2008 various locations in the City of Chula Vista (SW250B)" project. All proposals were contingent upon a base bid and one additional alternate bid to rehabilitate five manholes (located at Harnden Dr., E St./Landis Ave., 2 on Otay Lakes Rd. west ofSt. Claire Dr, ReislinglChardonnay Terrace). Staff 7-2 .. 11/25/08, Item~ Page 3 of 4 carefully analyzed the three bids submitted and determined that while all three bids contained minor errors, the apparent low bidder's mathematical error favors the City's interest and was not significant. Burtech Pipeline, Inc., the apparent low bidder, submitted a letter acknowledging its $220.50 mathematical error, agreed to their submitted value (Attachment 2) and will honor the lump sum bid price as submitted. Tonight's action will award the contract contingent upon the submitted total base bid price. The bids from the three contractors are: CONTRACTOR TOTAL Burtech Pipeline, Inc. - Encinitas, CA $574,176.50 Southwest Civil Contracting, Inc. - San Marcos, CA $715,094.00 MJC Construction - Chula Vista, CA $949,945.00 The low bid by Burtech Pipeline, Inc. of $574,176.50 is $63,878.50 (10%) below the Engineer's estimate of $638,075. The Engineer's estimate was based on average prices for similar types of work completed during the last two years. Staff believes this action would benefit the City in the form of saving the City more than $141,000. This Contractor has done previous work for the City and all work was found to be satisfactory. All references checked were verified and references confirmed that the Contractor's work has been satisfactory. The Contractor's License Number is 718202 and is current and active. After reviewing the low bid, staff recommends awarding a $574,176.50 contract to Burtech Pipeline, Inc. of Encinitas, California. The locations of the proposed work are located throughout the City. Fifty-eight percent (58%) of the repairs are located within the west side of Chula Vista and the remaining forty-two (42%) percent are located in the east side ofI-805 Freeway (Attachment 3). Approval of this resolution will authorize an inter-project transfer and authorize City staff to expend all available funds and increase the value of the contract as necessary due to unforeseen circumstances. Unforeseen circumstances may cause an increase in quantities beyond what was anticipated during the preparation of the project specifications. Due to the age of the City streets in the western part of the City, "unforeseen circumstances" may occur during the removal of the existing sewer mains and excavation occurring within the street. Field conditions could also differ from the proposed improvement plans and specifications. As a result, additional material may be required to rehabilitate the project site, which could lead to possible "Change Orders" to the contract. This is a typical situation with all sewer rehabilitation projects built in this area. According to City Council Policy No. 574-01, if a change order exceeds the cumulative contract change order aggregate amount allowable to be approved by the Director of Public Works Operations, City Council approval is required. Under said City Council Policy the amount would be $43,192.36. However, approval of tonight's resolution will increase the Director of Public Works Operations' authority to approve change orders as necessary up to the contingency amount of $64,000. If this money is not used during construction, the unexpended funds will be redistributed back to the appropriate original funding source. Wage Statement The contractors who bid on this project were not required to pay prevailing wages to persons employed by them for the work performed under this project. A "Notice to Contractors" was sent to various trade publications in order to encourage disadvantaged businesses to bid on the proj ect. 7-3 11/25/08, Item~ Page 4 of 4 Disclosure Statement Attached is a copy of the Contractor's Disclosure Statement (Attachment 4). DECISION MAKER CONFLICT Staff has reviewed the decision contemplated by this action and has determined that the decision concerns repairs, replacement, or maintenance of existing streets, water, sewer, storm drainage or similar facilities and, therefore, there is not a material financial effect of the decision on the property holdings of the City Council Members pursuant to California Code of Regulations Sections I 8704.2(b)(2) and 18705.2(b)(1). FISCAL IMPACT Sufficient Sewer Facility Replacement funds were previously appropriated under Fiscal Year 2007/2008 and Fiscal Year 2008/2009 Capital Improvement Program (CIP) budgets for sewer rehabilitation projects. It is proposed that these funds be combined and transferred into the "Sewer Rehabilitation Program - Phase 2 Fiscal Year 2005/2006 to Fiscal Year 2007/08 various locations in the City of Chula Vista (SW250B)" project to perform the required work. FUNDS REOUIRED FOR CONSTRUCTION A. Contract Amount $574,176.50 B. Contingencies (approximately 11%) $64,000.00 C. Staff Costs from the contract amount: Design Staff (10%) $57,222.00 Construction Inspection (15%) $86,126.50 TOTAL $ 781,525.00 FUNDS AVAILABLE FOR CONSTRUCTION Available Balance: A. Sewer Facility Replacement funds FY 2007/2008 (SW250) $653,125 Inter-Project Transfers to SW250: Sewer Facility Replacement funds FY 2008/2009 (SW255) $128,400 TOTAL $ 781,525.00 Upon completion of the project, the improvements will reqUITe only routine City sewer maintenance. ATTACHMENTS 1. Table A through Table C of work to be done 2. Burtech Pipeline, Inc. letter 3. Plats of work locations to be done 4. Disclosure Statement from Burtech Pipeline, Inc. Prepared by: Paten San Pedro, Engineering Department M:\General Services\GS Administration\Council Agenda\SW250B\SW250B Al13 Sewer Rehab ProgramREV2.doc 7-4 TABLE A (SEWER REHABILIATION PROGRAM, FY '05/'06 TO FY '07/'08 SW-250B) SEWER SEGMENTS TO BE REPAIRED/LATERAL CONNECTIONS TO BE REPAIRED, PROTRUDING LATERALS TO BE CUT AND JOINTS LATERALS TO BE WRAPPED WITH ROOT BARRIER -.J I U1 P LATERAL WYE NUMBER LATERAL WYE - P L SIZE FOOTAGE FROM TO CONNECTIONS OF CONNECTIONS I A LOCATION OF TOBE M.H. M.H. DEPTH TOBE SECTIONS TOBE DESCRIPTIONS P T PIPE REPLACED # # (fl) WRAPPED TOBE RE-OPENED E S (fl) W/ROOT REPAIRED AFTER BARRIER RE.L1NING Spot Repeir. 220' @: 15.0' - 24.0', 59' - 128'; 184'. 196',242' - 248', . 272'- 292', 375'- 384', 387' - 393', 208 I 409'.415',490'.505',513'.519', \6 l MADRONA 8" 220' 5303 53\7 10.0' 26 \7 32 563' . 583', 591' . 603', STREET VCP 608' . 614', 621' . 627', 631' - 637', 638' . 644', 647' - 653'; 26 - Lateral Repairs; 32 - Lntcrnl Rc-open; 275' - Roal Burrier; 665' - Rc-lining Spot Repair - 129' @ : 33' - 39', 662 ARTHUR 8" 42' .106', 111'- 117', 120' - 130:, 17 2 \29' 3069 2986 7 5 8 9 134'.150',154' -160',197' - 212'; AVENUE VCP 225' - 231': S-La!eral Repairs; 9-Lntcral Re-open; 75'-Root Barrier; 3IZt-Rc-line Spot Repeir. 190' @ : 42' - 54'; 81' - 87', 93' - 114', 124' - 130', 73 EAST 136' . 151', 186'. 192', 222' ~ 231', 8" 241' . 268', 272' . 302', \8 3 QUEEN ANNE VCP \90' 5716 57\7 8 12 \3 . 16 305' . 323', 340' - 352', 356' - DRIVE 374', 385' - 395'; 12 - Laternl Repairs; 16 - Loteral Rc-open; 230 I _ Rool Barrier; 400' - Re- lining ):> ~ () ::r: s: m ~ 1- TABLE A (SEWER REHABILIATION PROGRAM, FY '05/'06 TO FY '07/'08 SW-250B) SEWER SEGMENTS TO BE REPAIRED/LATERAL CONNECTIONS TO BE REPAIRED, PROTRUDING LATERALS TO BE CUT AND JOINTS LATERALS TO BE WRAPPED WITH ROOT BARRIER P LATERAL WYE NUMBER LATERAL WYE - P FOOTAGE CONNECTIONS CONNECTIONS I L SIZE TOBE FROM TO DEPTH TOBE OF TOBE P A LOCATION OF REPLACED M.H. M.H. (ft) WRAPPED SECTIONS RE-OPENED DESCRIPTIONS T PIPE # # TOBE E S (ft) W/ROOT REPAIRED AFTER BARRIER RE-L1NING Spot Repair - )3' @ : 8' - 14'; 19 4 1147 OCELOT 8" 33' 6589 6590 6 2 3 10 121' -127', 250' - 271'; 2 - Lute,.1 AVENUE VCP Repairs; 10 - Lntcral Rc-open; 105' Root Barrier; 300' - Re-lining SpotRep.ir - 51' @ : 27' - 39', 122' - 128', 160' - 172', 20 5 53 SHASTA 8" 51' 2862 2876 6 8 5 10 243' - 249', 2B7' - 301' ...... STREET PVC 8 - Lateral repair; 10 - Lateral re- I open, I05'.Root Burrier; m . 310'-Re-lining Spo'Rcp.ir - 18' @ : 152'- 158', 1403 OCALA 8" 167' - 174', 18B' - 195', 23 7 COURT VCP 18' 6751 6752 6 1 3 6 I w Lateral repair; 6 - Lateral re.. open, 95'.Root Burrier; 200'-Re-lining SpotRepair - 21' @ : 20' - 29', 662 MINOT 8" 191' - 197', 214' - 230', 24 8 AVE VCP 21 ' 3388 3300 6 2 3 7 2 - Lateral repair; 7 - Loteml re- open, 11S'.Rool Barrier; . 250'-Rc-lining TABLE A (SEWER REHABILIATION PROGRAM, FY '05/'06 TO FY '07/'08 SW-250B) SEWER SEGMENTS TO BE REPAlREDILATERAL CONNECTIONS TO BE REPAIRED, PROTRUDING LATERALS TO BE CUT AND JOINTS LATERALS TO BE WRAPPED WITH ROOT BARRIER -l I -l P LATERAL WYE NUMBER LATERAL WYE- P L SIZE FOOTAGE FROM TO CONNECTIONS OF CONNECTIONS I A LOCATION OF TO BE M.H. M.H. DEPTH TOBE SECTIONS TOBE DESCRIPTIONS P T PIPE REPLACED # # (ft) WRAPPED TO BE RE-OPENED E S (ft) W/ROOT REPAIRED AFTER BARRIER RE-L1NING 560 MARINA PARKWAY SpotRepnir. IS' @ : 73' - 82', 25 9 (California 1011 IS' 4180 4140 12' 0 2 0 88' - 94' ; 0 ~ Lateral repair; Yacht YCP 0 . Lateral rc~open. 6O'-Root Marina) Barrier; 20S'-Rc-lining 560 MARINA PARKWAY SpotRcpair - 18' @ : 8' - 14', 26 9 (California 10" 18' 4140 4105 \2' 0 3 0 69' - 75', 165' - 17t' ; 0 - L,te,nl Yacht YCP repair; 0 - Lateral Te-open, GO'-Root Marina) Bnrrier; 185'-Rc-lining 560 MARINA PARKWAY SpotRcpuir - 6' @ : 160' - 166';' 27 9 (California 10" 6' 4101 4072 12' 0 I 0 o - Lateral repair; 0 - Luternl rc- Yacht VCP open, 60' -Root Barrier; 170' .Re. Marina) lining 3681 BONITA SpotRepair-24'@: 4'- 10\ 8" 29'-35',49'-55',195'-20t'; 28 10 VERDE VCP 24' 7628 7625 9 0 4 3 0- Lateral repair; 3 - Loteral rc- DRNE . open, 7S'.Root Burrier; 260'-Re- lining TABLE A (SEWER REHAB ILlATION PROGRAM, IT '05/'06 TO FY '07/'08 SW-250B) SEWER SEGMENTS TO BE REPAIRED/LATERAL CONNECTIONS TO BE REPAIRED, PROTRUDING LATERALS TO BE CUT AND JOINTS LATERALS TO BE WRAPPED WITH ROOT BARRIER -.J 1 co P LATERAL WYE NUMBER LATERAL WYE . P L SIZE FOOTAGE FROM T.O CONNECTIONS OF CONNECTIONS I TOBE DEPTH TOBE TOBE P A LOCATION OF REPLACED M.H. M.H. (ft) WRAPPED SECTIONS RE.OPENED DESCRIPTIONS T PIPE # # TO BE E S (ft) W/ROOT REPAIRED AFTER BARRIER RE.L1NING 3649 BONITA SpoIRepair-6'@: 174'-180'; 29 10 VERDE 8' 6 7624 7625 9 0 ] 5 o - Lateral repair; 5 - Lateral fe. VCP open, 7S'-Root Burrier; 228'-Re~ DRIVE lining APPROX. TOTAL FOOTAGE REPAIR APPROX, 692 ft TOTAL LATERAL TO BE REPAIRED 56 TOTAL 3,910 ft (8") RE-LINE (10") 39 ft TOTAL LATERALS TO BE RE-OPENED 99 . -..J I <D TABLE B (SEWER REHABILITATION PROGRAM, FY '05/'06 TO FY '07'/08 SW-250B) SEWER PIPES TO BE LINED / LATERALS TO BE RE-OPENED p P 2002 J L SIZE OF FOOTAGE TO FROM TOM.H. DEPTH THOMAS A LOCATION BE LINED LATERALS TO BE RE-OPENED P T PIPE (ft) M.H. # # (ft) BROS. E S PAGE 16 I 208 MADRONA 8"VCP 665 5303 5317 10 1310-A6 32 STREET 17 2 662 ARTHUR 8"VCP 312 3069 2986 7 3010 - E7 9 AVENUE 18 3 73 EAST QUEEN 8"VCP 400 5716 5717 8 1330 - ElF 2 16 ANNE DIUVE 19 4 1147 OCELOT 8"VCP 300 6589 6590 6 1330 - Gl 10 AVENUE 20 5 53 SHASTA 8"VCP 310 2862 2876 6 1310 - B7 10 STREET TELEGRAPH 21 6 CANYON RD 15"RCP 600 4144 4154 15 1331-Al 0 (East of Paseo Ladera ) TELEGRAPH 22 6 CANYON ROAD 15"RCP 280 4069 4120 t5 1331-Al 0 (West of Heritage Road) TABLE B (SEWER REHABILITATION PROGRAM, FY '05/'06 TO FY '07'/08 SW-250B) SEWER PIPES TO BE LINED / LATERALS TO BE RE-OPENED -.J I P P 2002 L FOOTAGE TO I A LOCATION SIZE OF BE LINED FROM TOM.H. DEPTH THOMAS LATERALS TO BE RE-OPENED P T PIPE (It) M.H. # # (It) BROS. E S PAGE 23 7 14030CALA 8"YCr 200 6751 6752 6 1330 - G3 7 COURT 24 8 662 MINOT AVE 8"YCP 250 3388 3300 6 1310-C5 7 560 MARINA PARKWAY 25 9 (California Yacht 10"VCP 205 4180 4140 12 1329 - II 0 Marina) 560 MARINA PARKWAY 26 9 (California Yacht lo"vcr 185 4140 4105 12 1329-II 0 Marina) 560 MARINA PARKWAY 27 9 (California Yacht 10" VCP 170 4072 4101 12 1329 - II 0 Marina) . 28 10 3681 BONITA 8"vcr 260 7628 7625 9 1310-G3 3 VERDE DRIVE ~ o TABLE B (SEWER REHABILIT A nON PROGRAM, FY '051'06 TO FY '07'/08 SW-250B) SEWER PIPES TO BE LINED 1 LATERALS TO BE RE-OPENED -./ I ~ ~ P P 2002 I L SIZE OF FOOTAGE TO FROM TOM.H. DEPTH THOMAS P A LOCATION PIPE BE LINED M.H. # # (ft) BROS. LATERALS TO BE RE-OPENED T (ft) E S PAGE 29 10 3649 BONITA 8"VCP 228 7624 7625 9 1310-03 5 VERDE DRIVE NlA 13 FIRST AVE 8"VCP 130 5647 5648 6 1330-DZ 6 SOUTH OF NAPLES N/A 13 FIRST AVE 8"VCP 255 5648 5649 9 1330-DZ 8 SOUTH OF NAPLES N/A 13 FIRST AVE 8"VCP 135 5649 5654 9 1330-DZ 2 SOUTH OF NAPLES N/A 13 FIRST AVE 8"VCP 330 5654 5665 8 1330-E3 9 SOUTH OF NAPLES N/A 13 FIRST AVE 8"VCP 335 5665 5663 8 1330-E3 7 SOUTH OF NAPLES FIRST AVE N/A 13 SOUTH OF 8"VCP 145 5726 5727 7 1330-E3 5 OXFORD TABLE B (SEWER REHABILITATION PROGRAM, FY '05/'06 TO FY '07'/08 SW-250B) SEWER PIPES TO BE LINED 1 LATERALS TO BE RE-OPENED -..J I ~ P P 2002 L FOOT AGE TO I A LOCATION SIZE OF BE LINED FROM TOM.H. DEPTH THOMAS LATERALS TO BE RE-OPENED P T PIPE (ft) M.H. # # (ft) BROS. E S PAGE FIRST AYE N/A 13 SOUTH OF 8"YCP 135 5727 5728 7 1330-E3 5 OXFORD . FIRST AYE N/A 13 SOUTH OF 8"VCP 350 5728 5576 8 1330-E3 7 OXFORD FIRST AYE N/A 13 SOUTH OF 8"YCP 60 5776 5775 8.5 1330-E3 0 OXFORD FIRST A VB N/A 13 SOffi'H OF 8"YCP 95 5775 5803 8.5 1330-E3 2 OXFORD . FIRST AVE N/A 13 SOUTH OF 8"YCP 315 5783 5779 6.5 1330-E3 4 OXFORD APPROXDdATETOTAL 5270 FT FOOTAGE 8-INCII LATERALS TO BE RE-OPENED APPRO~ATETOTAL 154 FOOTAGE IO-INCH 560 FT APPROX~ATETOTAL 880 FT FOOTAGE IS-INCH "" TABLE C (SEWER REHABILITATION PROGRAM, FY '05/'06 TO FY '07'/08 SW-250B) SEWER TO BE REMOYED AND INSTALLATION OF NEW MANHOLE WITH LINING 2~ .." t'" SIZE OF MANHOLE THOMAS BROS. LATERALS TO BE ~O ~ LOCATION PIPE ID# .DEPTH (ft) PAGE RE-OPENED . Mt'" "" ll:IM ,. 1 , 11 304 Surrey Dr 8"YCP 765 7.0 1310 G-4 0 2 11 314 Surrey Dr 8"YCP ; 834 7.0 1310 G-4 0 , , 3 11 324 Surrey Dr 8"YCP 841 7.5 1310 G-4 0 -,,'-'" -,._--,. '-'-"~'---i- 4 11 331 Surrey Dr 8"YCP 867 11.0 1310 G-4 0 . '....-.."..----- '.m.___.".____c_ . ...'.._------..-, ._-~--_.~...._-,- ""-"'0-_-'_'"'' -.I I 5 12 343 Surrey Dr 8"YCP 933 7.0 1310 G-4 0 ~ w - .-,--.------, 6 12 351 Surrey Dr 8"YCP 940 7.0 1310 G-4 0 -".........-.....-,--.. 7 12 356 Corral Ct 8"YCP 1038 11.0 1310 G-4 0 . -. ._-~_.__._-__,..__ ..__~____ _.J__.__ ..._._.....~,_._._---._._..--- 8 12 806 Corral Ct 8"YCP 849 8.5 1310 G-4 0 -. __"m._'.__..._._..__......._ ---r-'" --------------.- ...__._____u..._.__ __no ____.............'''__.____,_. ..... .____.,_____.._____..._..._....___ '--"-'-....-..---.'- 8 NEW SEWER MANHOLE LATERALS TO BE RE-OPENED 0 WITH LINING TABLE D (SEWER REHABILITATION PROGRAM, FY '051'06 TO FY '07'/08, SW-250B) IF ADDITIONAL FUNDING IS AVAILABLE SEWER MANHOLES TO BE REMOVED AND INSTALLATION OF NEW MANHOLE WITH LINING ~ o t"' t<l THOMAS BROS. PAGE LATERALS TO BE RE- OPENED SIZE OF ; MANHOLE # PIPE LOCATION __ _._L_._._..___._-:.____..____.__~____.~_____~.___ 1 2133 HAMDEN DR 8"VCP 2153 1310 B-5 1330 E-5 1330 D-4 4 OTAY LAKES ROAD 13IOB-6 8"VCP 7352 5 INTERSECTION OF 566 REISLING 1 CHARDONNAY 13 10 B-6 8"VCP 310 5 NEW MANHOLE mSTALLATION LATERALS TO BE RE-OPENED o o o o o o ATTACHMENT' ~c ~\)RTEC~ Is,;} " ;)~~ genet.ll en<il5F;''"'11n<r c;onlr.ldor ~",;;; I)/PEL \ll~ ....... · <',' . ()ctober 22,200S City of chuia'Vista. . Public Services Buildirig 276fourthAv~ue,' ., , ChulaVista, CA". ....,... Attention: .PotenSaiIr~clro ... .... ...... Deparn:n~t of Engin,eering, Design., .'.-,. '. . '.' .:" Re. Sewe~Reh~biijtatio.nPrograni,.,Phase 2 . '0' DeaTMr. San'Pec4'o: " . .. . ," . ,,-, ," . -- - . ',.- '-' " ',,' " ,'., ":"- "-, , '. ",,-.:, .-, ".' .-' -':' . -' ,"' After.reviewing the. bid Jo.i the .above-ll1entioned project we subn1itted.on October 15, iOOS;'we found a little errbr onltem)PaxtJ) amounting to .$220.5Q. in the City's favor.. . VI e,wouldlike to l~t you kllow;thatBl1l:tech PipeIiIie,Inc. takes full responsibility" of this .. . . error and we.assuretheCity that we will hOlior the Lump Sum bid p;rice of$ 574,17650 . we submitted: We.'have partnered in severs,i jobs in the past and we would like .to '. .c,ontinue this good working . relationship with the City, we hope this will not. alter. the.': decisibnof the CitY to: award theprojectt()tls, . . , . . . . " . . -. - " '. : ,'. ;" . ' . ,,' MOre powerto.theCity ofChula Vista and we lo,ok forward to start thisjob with you. . . - .~ .'. . , . . , ,.' . . . ..' .' -,."',' . . .' Burtech Pipeline, Inc.', 102$ecohd Street, E;ncinitas,CA92024 'Tel (760) 634-2822 , Fax (760) 634-2415. Uc. # 718202" "7-15 1#" .' 'I" I.,O CPipe#J7; Plat 2) 662 ARJ..fI()R AVENUE MH # 3069 to MH # 2986 "';;'r-' . s"VGl',"" , \ "1 ,,'.j i '., ...... . Unit Cost in . '. H~m Description Qty Unit Unit Price inWords Figures Total . ,. .... Lump 1. Removal and Disposal I <;even#IJnd l'ecJ pjfhj Vallo"" 'i50.CO 750. CI:J Sum 2. Trench Shoring 165 Lineal One 06/ (ar /.(b Ic'05.O::> Feel , ~ t"iF-4 u.rrrS ( ~ 3. Television Taped lnspeclion 312 Lineal On.t Ddl/et/ al1u/ /..so 47.50 (CerY) Feel ^ <IJ ~:lfJ.5n Lineal Oruz Hunolreol . . 4. Sewer Main 129 ThlrfLj fll]h-f /38.00 17, ~OJ.Co Feel 5. Sewer Laleml's WYE {TEE 5 Each It :Fd4-"'I~~\:fJo/lars J {l!6 ,cJD J 2,{Oo .00 ... ,-..- ,. . 6. Sewer Late,al Pipe 10 Lineal . c;eu.-t (l+Lf FI~ Feel Qal( c< K.. 75.00 7!Jo.Od 7. Pipe Lining Sewer Main 312 Lineal ~1 r1Lt-'TWb Pd 11a.1d 9,QgY'dD , Feel 3~. cJ<l 8. Re-openingLaleml 9 Each 0Yll-- ti~. ~l Kflj ~fllx . 1(P~c{ /, '-/-';-&.OD 9. Traffic Control & 1 Lump FIJt. 1-1 ().rie1red Do /lCfr'J 9V .00 .5:0, (XJ Protection and Restoration Sum ~ -..J I ~ cr> SUBTOTAL PART 0: # 19/ ~ Y).5o S M :\General Services\Design\SW-250\PHASE 2\SW250B _ SpecsPhase2.rev5e.doc 8" VCP SWR - 665' SPOT REPAIRS (A/HI SJOJ to MH/5J17) LA TERAL DESCRIPl1CJNS SECTION tGCA nON LENGTH 15.0' 24.0' 9.0' 59.0' - t28,0' 69.0' r84.0' - 196.0' 1 o' 242.0' - 2'f.B..O' 6.0' 272..0' - 292.0' 20.0' 375.0' - 384.0' 9.0' 387.0 39.J.0 5.0 409.0' - 415.0' 6.0' 490.0' - 5as.O' 15.0 SrJ.o' - 519.0' 6.0' 56300' - 583.0' 20.0' 591.0' - SOJ.O' 12..0' 608.0' - 6r4.0' 6.0 627.0' - 627.0' 6.0' 631.0' - 637.0' 6.0' 6sao' 6+4.0' 6.0' 6"'7.0' - 653.0' 6.0' ~iRO -- ^,Ij sr --- ORA WN BY: PO TF:N G. SAN PEDRO DATE: SHEET 1 04-25-08 OF 14 SHTS. 777LE: -3 ATTACHMENT *MADRONA ST o ROOTS I NT OEFCCT -I ROOTS IN TH~ JOINTS k LA ~AL J ROOTS AND LA TE1i'Al. DEffCT , ROOTS AND LA~AL OEFfCT 5 CRACK AT 7H. JOINTS & LA TFRAl. 1 ROOTS IN THE JOfNTS 2 DEFfe71 L41FRAl. 1 CRACK AND LA TERAL DEFECT .. DEFECl1'-E LA JFRALS 1 ROOTS IN THE LA 1E'RAL 2 R T5 IN TH LA 7ERAL 2 ROOTS. AND LA TeRAL DEFter o Roars IN 7HE JOINT o ROOrs IN TH. JOINT o ROOTS iN THE JOINT o ROOrs IN THE JOINTS o ROOTS IN THE JOINTS I \...--- ...___Cl \ \ \ CITY OF CHULA VISTA SEWER REHABILlA T10N (SW250) PHASE 2 PREPARED BY: POTF:N G. SAN PEDRO APPROVED BY: ROBERTO YANO 7-17 ~ \ \ ~\ G-- %\~ ~\ CI DRAWN BY: paTEN G. DATE: 04-25-08 8" vep Sw.'i' - 312' *AR THUR AVE ;;::Ol :t:'" ",,<0 ",,:> <00<] OJ:t Ol~ ::tl :> "" SPOT Rf?A1RS (MH, 3069 to MHI 2986) SEcnON LOCA nON LENGTH LA TERAL DCSarfPTIONS 33.0' 39.0' 6.0' 0 ROOTS IN THE JOINTS 42.0' - 106.0' 54.0' 2 ROOTS. AND l.A7ERAL DUEer 111.0' - 117.0' 6.0' 0 ROOTS IN THE JOINTS 120.0' - '30.0' 10.0' 0 ROOTS IN THE JOINTS 134.0' - 150.0' 15.0' 1 ROO7S. LA TCRAL DVFCT 154.0' 160.0' 6.0' 0 ROOTS IN THE JOINTS 197.0' 212.0' 15.0' 2 ROOTS LA7ERAL DEFECT 225.0' - 2J1.Q' 6.0' 0 ROOTS IN THe JOINTS TOTAL LA TERALS 9 \ \ *SDG&E UTILITY WITHIN WORK AREA I I ! Gl Gl I I / ~8l """, "":.. Cl"O ~:t ~ :.. "" SAN PEDRO SHEET 2 OF /4 SHTS. TInE: PREPARED BY: paTEN G. SAN PEDRO APPROVf:D BY: ROBERTO YANO CITY OF CHULA VISTA SEWER REHABILlA TlON (SW250) PHASE 2 7-18 :l:. '2. x .". <. 'I ~I ~ CJI :>> ~\ \ 8" VCP SWI? - 400' *E QUEEN ANNE DR - - SPOT REPAIRS (UH, 5717 to MHl 5716) SEenON tOCA TlON LENGTH LA TERAL DESCRIP110NS 42.0' - 54.0' 12.0' 0 ROOrs IN mE JOINTS 81.0' - 87.0' 6_0' 0 ROOTS IN mE JOINTS 9.].0' - 114.0' 21.0' J ROOTS. AND TERAL DCFECT 124.0' - 130.0' 6.0' 0 ROOTS IN THE JOINTS 136.0' - 751.0' 15.0' 0 ROOTS IN JOIN CRACKS 188.0' - 192.0' 6.0' 1 ROO AND uTERAL DEFECT 222..0' - 231.0' 9.0' 2 ROOrs. AND LATE7TAL DEFFCr 2-41.0' - 68.0' 27.0' a ffOD1S IN TH. JOINTS 72.0' - 3D .0' .10.0' 1 ROO AND A A 0 'CT __ 305.0' - 323.0' 18.0' 1 ROO AND LA ~L DmCT J40.0' - 352.0' 12.0' 0 ROOTS rN mE ROOTS 356.0' - 374.0' 18..0' 2 ROOTS. AND UJEl\"AL OEFECT ___ 385.0' - 395.0' 10.0' 2 ROOTS AND LAT&AL DUEeT -- --:I: ~t ~ ~ *SDG&E WITHIN WORK AREA QUEEN 73 ~ 5716 MHJr - - c--- -- - DRAWN BY: PO TEN G. SAN PEDRO DA 7[: SHEET 3 04-25-08 OF 14 SHTS. TITLE: CITY OF CHULA VISTA SEWER REHABILlA TlON (SW250) PHASE 2 PREPARW BY: POTCN G. SAN PEDRO APPROVED BY: ROBERTO YANO 7-19 ------- 51 .- -- ------- E NAP;!? ::.--- .- .- \.. .......... ~ \ \ \ NETIE ~ --- :'\ NA .-- y'- ~ \ c 51 ANETTo. 495 N 6590 MrI# 8" vep SWR - 300' *OCELOT A V SPOT REPAiRS (A/HI 6590 to MHI 6589) SECTiON tDCA nON WJGTH LA TERAL DESCRIPT1QNS 8.0' - 14.0' 5.0' 0 ROOTS IN JOINTS '21.0' - 127.0' 5.0' 1 ROO AND LA7t:RAL Queer 250.0' 271.0' 21.0' 1 ROO AND LA1FR'AL DEffCT *SDG&E UTILITY WITHIN WORK AREA ;;::::: ! \ I~ \ _-...> 0\0 \ u\o ~ 0> r<1 <.Or 0 ~ --\ "> <. \ DRAWN BY: POTEN G. SAN PEDRO DA TE: SHEET 4 04-25-08 OF 14 SHTS. TITLE: CITY OF CHULA VISTA SEWER REHABILlA TION (SW250) PHASE 2 PREPARED BY: POTEN G. SAN PEDRO APPROVED BY.' ROBERTO YANO 7-20 - .-&-- - - - *SHASTA ST 1 ~ SPOT REPAIRS (MHI 2862 to UHf 2876) SEC110N WCA nON LENGTH LA TERAL OCSCR1P17ONS 27.0' 39.0' 2 ROOTS. AND LA1ERAL Durer 122.0' - 128.0' .0' 1 ROOTS AND t.A7E'RAL DEFeCT 160.0' _ 1720' 12.0' ROO AND LA7E'RAL VErreT 243.0' - 249.0' 6.0' 1 ROOTS. AND LA TCRAL DfFECT 287.0' - 302..0' 15.0' 2 ROOrs. LATERAL DUECT *SDG&:E UTILITY WITHIN D WORK AREA fA 51 HAS' 53 5 ZB6Z 51 MH# SH~'~ ~ .....-: 51 SH AS' A - y 51_ \M-il~ - - _n -- ? ~ _G~~", -- DRAWN BY. PO TEN G. SAN PEDRO DA TE: SHEff 5 04-25-08 OF 14 SHTS. TITLE: CITY OF CHULA VISTA SEWER REHABILlA TlON (SW250) PHASE 2 PREPARED BY: PO TEN G. SAN PEDRO APPROVED BY: ROBERTO YANO 7-21 ... :C'" -::i.':;i- = ,- ..--::; ~ ~ (#1Pi(J ~ =-li =-,-~~ \ ~ ,~ ,::.--:;; ::.--0:: IS" VCP SlW? - 280' *TELEGRAPH CANYON RD ,- %:= -' NO SPOT REPAIRS (Mffl 4069 to JJHI 4120) SECTION LOCA 710N UHGTH LA mfAL DESCRlPlIONS 15~ \oCP SlIR UNlNC 28D' 0Nf.1' NO SPOT REPNR 'SDG&:E UnUTY WITHIN WORK AREA IS" VCP SlW? - 600' *TELEGRAPH CANYON RD NO SPOT REPAJRS (A/HI 41+f. III MHI f7!i4) SECllCW LOCAl1CN LENGTH LAlE'RAL OE:SCRJPTJONS '5- '..cP S*R UNINC 600' ONU' NO SPOT REPAIR -'- - - - - ,- "- .. /.iH #4144 fZJ 8NlHQlIC.cr \ .s.wtr<<MA DR DRAWN BY' PO TE:N G. SAN PEDRO oA fe: SHEFr 5 04-25-08 OF 14 SHrs. TITLE: CITY OF CHULA VISTA SEWER REHABILlA TION (SW250) PHASE 2 PREPARED BY' POTE:N G. SAN PEDRO APPROVED BY: ROBERTO YANO 7-22 ...... \ co a (J1 ,... AJ f'< f'< :<: ~ -< 8" VCP SWR - 200' *OCALA CT A SPOT REPAIRS (MHI 575/ t. MHI 5752) 1. SEcnON toCA nON LENGTH LA TCRAL DESCRJPTlONS N T52.0' - 158.0' 6.0' 0 BROKEN prp~ E:XAl.1RAnON l 757.0' 174-.0' 5.0' , LA TERAL DEFECT F:XF1L 11i'A nON ~ 188.0' - 195,0' 6.0' 0 BRQI<ON PIPE EXFlLTRATlON *SDG&E UTILITY WITHIN WORK AREA A Cl 1403 QCAL \'\\-\ ~b 751 r- >--< "M~ ~> >r- r- l/) ---- G / ---- I / ~ r ~ I ~ Q\JINC~G5T - c1 -~ r i t::! \ ~ 1411 T OCALA C Cl 77TLE: DRAWN BY: POTEN G. SAN PEDRO DA TE: SHEET 7 04-25-08 OF /4 SHTS. CITY OF CHULA VISTA SEWER REHABILlATlON (SW250) PHASE 2 PREPARED BY.' paTEN G. SAN PEDRO APPROVED 8Y: ROBERTO YANO 7-23 ~~ ~ \~S\ - ____ ____G- \ a" vcp Sw.'i' - 250' *MINOT A V - SPOT REPAIRS (AlHI 3JBB to MHI 3300) SECl10N LOC..411ON LENG7H LA 1ERAL DESCR/PTlONS 20.0' - 29.D' I ROOTS. AND LATER. DEffCT 191.D' _ una' 6.0' r ROOTS. AND LAT9ML D CT 214.0' - 220.0' 6.(" , F1N~ ROOTS fN JOINTS *SDG&:E UTILITY WITHIN WORK AREA 1 ~ H H338~ MMINOT A 662 DRAWN BY: POTEN G. SAN PEDRO DA TE: SHEH 8 04-25-08 OF 14 SHTS. nTLE: CITY OF CHULA VISTA SEWER REHABILlA nON (SW250) PHASE 2 7-24 PREPARW BY' POTEN G. SAN PEDRO APPROVED BY: ROBERTO YANO (l l. 1J~ - L. L. ,...-' -Q vi 17 --' 1J17 -r- ~ S~ d'i 17 *MAR/NA PARKWA Y SPOT REPAiRS (JJH 4101 10 IIH j4072) SECTION l.OC411ON lENGtH U1al..u, DESCRJPrlONS rSD.D' - '6 0' . a 'ACX1NC ~ ~ 'i 17 -Q ~ SPOT REPNRS (lJH 14140 'I'D JIH #4105) SECTrON LOC411ON lDlG1H UDAL DF:SCRfPT/ONS O' _ ,..' 6. . T10N T 6110' - 15.0' "'.0' 0 OSS1RUC17CW T 165.0' - 1710' 6.0' (} INFIl.TRA OUECT SPOT REPAJRS (IIH .,..tea ro IoIH l,n40) SEcrrON I.0C411Ci'1 1.ENG1H I.A7E'i'AL D6CR1PTIOHS . - 0' 90' (} 1tl A .CRA 8110' - !UO' 5.0' " 0NQ1UlJTNA. CRACK1NG 'SDG&E WITHIN WORK AREA u,,, \I~\\l\ 16' '" '/If/.- 10' "eP 5 1J\t.GD S~\'\ ~~" A(l ~r -:r->::;; --'0 ->'% ~,...-' r'17 -Z- 17 DRAWN BY: PO TEN Go SAN PEDRO DA TE:: SHEET 9 04-25-08 OF 14 SHTS TITLE: CITY OF CHULA VISTA SEWER REHABILlA TlON (SW250) PHASE 2 PREPARED BY: POTEN G. SAN PEDRO APPROVED 8Y: ROBERTO YANO 7-25 DRAWN BY' paTEN G. SAN PEDRO DA TE: SHEET 10 04-25-0B OF 14 SHT5. ,,~<:I I "'i! \ "'... '" ~+7 6"Y..94'..> I-. &>.5",;> <'1'<:>",'" "'.... ",.. <>~.. "'It 'r .:100 *'>5 t"S Il"S <:RtPtvlJ: <: /)R~ SPOt REPNIl (ltH ,n2f TO 1OI/76Z) S[t:fIfW l~lIQIII I.EHCTH U.DAL COWW!HI'S 'f.D' _ ,0.11' 1.0' .NFll.nt.4m:w REPAIR tr-.J5.tr 1.0" Q lI'fIt.1JlAntWRtPNIf +f.Q'-~a' 1.0 IHn..TRJH!ClHRt1'AIIt 1"-0" _ ~'.Q' Hltm.t/lCW fID'.A1If 'SDG.tE IIfTIIIN IIORK AREA . 8" VCP SIIR - 250' :.< ~1b~~\\~ *BONITA VERDE DR Yi f:/o\"'P rt.. \)~ SPOt RePASt (JIH Pfi2$ TO WHPW) ~ --.I(.~.:u: SEC'OQi LOCInOH tEHCTH tA1El'I'Al. CfMIEH1S 174.0' _ 150.0' lur .wRtmA1lCWflEPAJIl . 'SDGM: IIfTHIN IIORK AREA I TITLE: PREPARED BY' paTEN G. SAN PEDRO APPROVED BY: ROBERTO YANO CITY OF CHULA VISTA SEWER REHABILlA TlON (SW250) PHASE 2 7-26 304 SURREY DR ~ ""- If g c., ".. <B' ORA WN BY: POTEN .G. SAN PEDRO DA TE: SH~ET 11 04-25-08 OF 14 SHTS. TIllE: ...J a.. >- w 0:: 0:: ::J (.1 0 SURREY DR 0 0 *SURRY DR AND CORAL CT SECllON LOCA nON MANHOLE :s MANHOLE MANHDLE .., MANHOLE 7 A/ANHot.E D:JB MANHOlE -f9 MANHOLE J AlANHQl.E o<<J r- z w :;:' Ww_ ...Ju"- D<rCIl I...J# za.. <l:wI ::E OC"::E $U\<,\<'E.'< "D\<. @ 0:: '" >- W "" 0:: ::J (.1 RDrlOwr AND REPUC~ MANHOlE LENGTH LA "fERAL CQMIJENTS 0.0' " MANHOLE REPU,CEJ./ENT a.O' a MANHOLE REPLACDlENT a.o' 0 MANHlXE REPf..ACSlENT a.O' (} MAM<<X.E REPt.A.CDlENT D.O' " MANHOLE REPLACElIENT 0.0' 0 MANHOLE REPUCEJlENT 0.0' a IIANHfXE REPUCEJlen D.O' 0 MANHOLE REPf..ACEJlENT ! ~ 'SDG&E WITHIN WORK AREA ..- (\J ('") CITY OF CHULA VISTA SEWER REHABILlATlON (SW250) PHAS~ 2 PR~PARED BY: . PO TEN G. SAN PEDRO APPROVED BY.' ROBERTO YANO 7-27 *SURRY DR AND CORAL CT SCCllON LDCAlION MANHOLE 15"5 UANHOlE ~ MANHOLE 41 MANHOlE 67 UANHOl.E 03B MANHOlE "'9 MANHOlE 3.J UANHOf.E -4D REMOVE' AND REPtACE UANHfXE LENGTH LA 1FRAl COllA/DolTS 0.0' 0 UANHcx.E RCPLACEMENT 0.0' 0 I.tANH~ REPLACEJJOiT 0.0' AlANHOLE REPLACEMCNT 0.0' 0 MANHOLE REPLACEMENT 0.0' 0 MANHOLE REPLACEMOIT 0.0' 0 MANHOLE REP/J.CE1rfENT 0.0' 0 MAJYHOLE REPLACEJlEJIT 0.0' 0 MANHOLE REPUCE:MENT ! ~ !z 'SDG&E WITHIN WORK AREA w :E ww_ -'U'<t D<[CO I-,,,,, Za.. <[wI ::E0:::E S\.lRRt:'i DR @ 0:: '" >- W 0:: 0:: ::J CI) CORRAL CT 3'56 ORA WN BY: POTEN G. SAN PEDRO DA TE:: SHEET /2 04-25-08 OF 14 SHTS. '<t '" M o SURREY DR lITLE: CITY OF CHULA VISTA SEWER REHABILlATlON (SW250) PHASE 2 7-28 ~ "G ~ ~ ~ 'P> o @ o ~'Z"" 6't~ }i.JJ:r. <t'i~ $..> 'b ct PREPARED BY: POTEN G. SAN PEDRO APPRO 'lED BY: ROBERTO YANO \ DRAWN BY: PO TEN G. SAN PEDRO DA TE: SHEET 1 J OJ-15-08 OF 14 SHTS. n M; CITY OF CHULA VISTA SEWER REHABILlA TlON (SW250) PHASE 2 PREPARED BY: PO TEN G. SAN PEDRO APPROVED 8 Y: ROBERTO YANO 7-29 ~l ~ ~ ~ I :1~>j'2. <' ~ ~ ADDITIONAL MANHOLE IF ADDITIONAL MONEY BECOMES AVAILABLE DRAWN BY.' POTEN G. SAN PEDRO DA TE: SHEET 14 OJ-15-08 OF 74 SHTS. TInE: CITY OF CHULA VISTA SEWER REHABILlA TlON (SW250) PHASE 2 PREPARED BY: POTEN G. SAN PEDRO APPRO VED BY: ROBERTO YANO 7-30 ATTACHMENT t.{ CITY OF CHULA VISTA DISCLOSURE STATEMENT Pursuant to Council Policy 101-01, prior to any action upon matters that will require discretionary action by the Council, Planning Commission and all other official bodies of the City, a statement of disclosure of certain ownership or financial interests, payments, or campaign contnbutions for a City of Chula Vista election must be filed. The following information must be disclosed: 1. List the names of all persons having a financial interest in the property that is the subj ect of the application or the contract, e.g., owner, applicant, contractor, subcontractor, material supplier. 17om'ln; G 'f1udec.h J l.(. [Ie !:>udec'o 2. If any person' identified pursuant to (1) above is a corporation or partnership, list the names of all individuals with a $2000 investment in the business (corporation/partnership) entity. 10/4- 3. If any person' identified pursuant to (1) above is a non-profit organization or trust, list the names of any person serving as director of the non-profit organization or as trustee or beneficiary or trustor of the trust. WA, 4. Please identify every person, including any agents, employees, consultants, or independent contractors you have assigned to represent you before the City in this matter. 0/1< 5. Has any person' associated with this contract had any financial dealings with an official"~ of tbe City ofChula Vista as itre]ates to this contract within the past 12 months? Yes_ No~ 31 M:\General Services\Design\SW -250\PHASE 2\SW250B _SpecsPha.se2.rev5e.doc 7-31 If Yes, briefly descnoe the nature of thdinancial interest the official-- may have in this contract. 6. Have you made a contribution of more than $250 within the past twelve (12) months to a current member of the Chula Vista City COWlciJ? No ./ Yes _ If yes, which Council member? 7. Have you provided more than $340 (or an item of equivalent value) to an official-- of the City ofChuIa Vista in the past twelve (12) months? (This includes being a source of income, money to retire a legal debt, gift, loan, etc.) Yes _ No L If Yes, which official-- and what was the nature of item provided? Date: /0115/2008 . , 0/". Signature of Contra U. PIP€- U 0G {/0C.. I ontractor/ Applicant * Person is defined as: any individual, firm, co-partnership, joint venture, association, social club, fraternal organization, corporation, estate, trust, receiver, syndicate, any other county, city, municipality, district, or other political subdivision, -or any other group or combination acting as a unit. ** Official includes, but is not limited to: Mayor, Council member, Planning Commissioner, Member of a board, commission, or committee of the City, employee, or staff members. 32 M;\Genera1 Services\Design\SW-250\PHASE 2\SW250B _SpecsPhase2.rev5e.doc 7-32 .. RESOLUTION NO. 2008- - RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA WAIVING DEFECTS IN THE BID, ACCEPTING BIDS AND AWARDING CONTRACT FOR THE "SEWER REHABILITATION PROGRAM-PHASE 2, FISCAL YEAR 2005/2006 TO FISCAL YEAR 2007/2008 VARIOUS LOCATIONS IN THE CITY OF CHULA VISTA, CALIFORNIA (SW250B)" PROJECT TO BURTECH PIPELINE, INC. IN THE AMOUNT OF $574,176.50 WHEREAS, on April 15,2008, pursuant to Resolution No. 2008-096, the City Council awarded a contract for "Sewer Rehabilitation Program - Phase I, Fiscal Year 2005/2006 and Fiscal Year 2006/2007 and Fiscal Year 2007/2008 various locations in the City of Chula Vista (SW240A)" to KTA Construction, Inc.; and WHEREAS, the Sewer Rehabilitation Program-Phase I is nearly complete; and WHEREAS, City staff prepared specifications for the "Sewer Rehabilitation Program - Phase 2, Fiscal Year 2005/2006 to Fiscal Year 2007/2008 various locations in the City of Chula Vista (SW250B)" project and advertised the project on September 26, 2008; and WHEREAS, on October 15,2008, the Director of Engineering received three sealed bids for the proj ect; and WHEREAS, staff carefully analyzed the three bids submitted and determined that, while all three bids contained minor errors, the apparent low bidder's mathematical error favors the City and is insignificant; and WHEREAS, Section 1009 of the City Carter allows the City Council to waive any defects in any bid to the extent it finds at a public hearing held for that purpose that it is necessary to do so for the benefit of the public; and WHEREAS, Burtech Pipeline, Inc. made a minor error of $220.00 in their submitted bid of $574,176.50 and has submitted written acknowledgment of its error agreeing to perform for the contract price it submitted; and WHEREAS, Burtech Pipeline, Inc.'s bid IS 10% below the Engineer's estimate of $638,075; and WHEREAS, pursuant to Council Policy No. 574-01, the Director of Public Works is authorized to approve change orders amounting to $10,000 plus 7% of the original contract amount over $100,000 for contracts between $100,000 and $1,000,000 and City Council approval is required for approval of a change order exceeding this amount; and 7-33 Resolution 2008- Page 2 WHEREAS, for this project, that amount is $43,192.36; and WHEREAS, staff recommends waiving Council Policy 574-01 and authorizing the Director of Public Works Operations to approve change orders as necessary up to the contingency amount of$64,000. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Chula Vista as follows: 1. That it fmds that it is necessary for the benefit of the public to waive the defect in the bid submitted by Burtech Pipeline, Inc. because the error is in the City's favor and will save the City money. 2. That it waives the defect in the bid submitted by Burtech Pipeline, Inc. 3. That it accepts bids and awards the contract for the "Sewer Rehabilitation Program-Phase 2, Fiscal Year 2005/2006 to Fiscal Year 2007/2008 various locations in the City of Chula Vista, California (SW250B)" project to Burtech Pipeline, Inc in the amount of $574,176.50. 4. That it waives Council Policy 574-01 and authorizes the Director of Public Works Operations to approve change orders as necessary up to the contingency amount of $64,000. Presented by Approved as to form by R. A. Hopkins Director of Engineering c--l~_,,^ IL~ c,rrv Bart Miesfeld Interim City Attorney 7-34 .. RESOLUTION NO. 2008- RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA AUTHORIZING THE TRANSFER OF A V AILABLE SEWER FACILITY REPLACEMENT FUNDS INTO "SEWER REHABILITATION PROGRAM - PHASE 2, FISCAL YEAR 2005/2006 TO FISCAL YEAR 2007/2008 VARIOUS LOCATIONS IN THE CITY OF CHULA VISTA (SW250B)" WHEREAS, on October 15,2008, the Director of Engineering received three sealed bids for the "Sewer Rehabilitation Program - Phase 2, Fiscal Year 2005/2006 to Fiscal Year 2007/2008 various locations in the City of Chula Vista (SW250B)" project; and WHEREAS, the project will rehabilitate existing broken sewer mains and laterals, repair cracked sewer lines and replace asphalt concrete pavement in various locations throughout the City ofChula Vista; and WHEREAS, sufficient Sewer Facility Replacement funds were previously appropriated under Fiscal Year 2007/2008 and Fiscal Year 2008/2009 Capital Improvement Program (CIP) budgets for sewer rehabilitation projects; and WHEREAS, staff proposes that these funds be combined and transferred into the "Sewer Rehabilitation Program - Phase 2 Fiscal Year 2005/2006 to Fiscal Year 2007/08 various locations in the City of Chula Vista (SW250B)" project as follows: Sewer Facility Replacement funds FY 2007/2008 (SW250) $653,125 Sewer Facility Replacement funds FY 2008/2009 (SW255) $128,400 TOTAL TO BE TRANSFERRED TO SW250B $781,525 NOW, THEREFORE BE IT RESOLVED by the City Council of the City Chula Vista that it authorizes the transfer of $653,125 in available funds from Sewer Facility Replacement funds FY 2007/2208 (SW250) and the transfer of $128,400 in available funds from Sewer Facility Replacement funds FY 2008/2009 (SW255) into "Sewer Rehabilitation Program - Phase 2 Fiscal Year 2005/2006 to Fiscal Year 2007/08 various locations in the City of Chula Vista (SW250B)". Presented by Approved as to form by '---I-j~ '" II- L~ ~ Bart Miesfeld Interim City Attorney R. A. Hopkins Director of Engineering 7-35