HomeMy WebLinkAbout2008/10/07 Item 5 CITY COUNCIL AGENDA STATEMENT ~f:.. CITY OF '=l:~~~ CHULA VISTA 10/07/08, Iteml SUBMITTED BY: RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA APPROVING THE FIRST AMENDMENT TO THE DESIGN/BUILD AGREEMENT WITH ERICKSON-HALL CONSTRUCTION CO. FOR THE DESIGN AND CONSTRUCTION OF MT. SAN MIGUEL COMMUNITY PARK TO REVISE THE GUARANTEED MAXIMUM PRICE RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA AMENDING THE FISCAL YEAR 2008/2009 CIP PROGRAM AND APPROPRIATING $7,769,399 FROM THE AVAILABLE PARK ACQUISITION AND DEVELOPMENT (PAD) FUND BALANCE TO EXISTING CAPITAL IMPROVEMENT PROJECT, MOUNT SAN MIGUEL COMMUNITY PARK (CIP PR260) TO COMPLETE THE PROJECT DIRECTOR OF ENGINE~ INTERIM CITY MANAGER "7-;- 4/5THS VOTE: YES [gJ NO 0 ITEM TITLE: REVIEWED BY: SUMMARY The City Council previously approved CIP Project No. PR260 and the Master Plan for Mount San Miguel Community Park, which conceptually designed and provided for the construction of a completed and fully functional 19-acre park On September 19, 2006, Council approved a Design Build Agreement with Erickson-Hall Construction Co. for this park The Design Build Agreement contained a not-to-exceed price of$5,841,067 with the GMP to be set upon receipt of 90% construction drawings. The project is nearing the end of the design phase and ready to start the construction phase. Tonight's first resolution will approve the first amendment that will set the Guaranteed Maximum Price (GMP) at $8,688,462. In addition, the second resolution will amend the Fiscal Year 2008/09 CIP Program and approve the appropriation of$7,769,399 to the existing CIP PR260 for said purpose. ENVIRONMENTAL REVIEW The Environmental Review Coordinator has reviewed the proposed project for compliance with the California Environmental Quality Act (CEQA) and has determined that the proposed project was adequately covered in previously adopted San Miguel Ranch Sectional Planning Area (SPA) Plan and Subsequent Tentative Map Final Environmental Impact Report 97-02 (EIR 97-02) and associated Addendum. Thus, no further environmental review or documentation is necessary. 5-1 10/07/08, Item2 Page 2 of 4 RECOMMENDATION Council approve the resolutions. BOARDS/COMMISSION RECOMMENDATION Not applicable. DISCUSSION On September 19, 2006, City Council approved an agreement with Erickson-Hall Construction Co. by Resolution 2006-290 for the services required to design and construct a completed and fully functional 19-acre, Mount San Miguel Community Park. As part of that agreement, a Guaranteed Maximum Price (GMP) is to be established at 90% construction documents, which would include, but not be limited to, the cost for all labor, equipment, and material to design and build a fully functional park in accordance with all applicable building codes. A not-to-exceed amount of$5,841,067 for the park was established based upon rough schematic drawings in the Design Build agreement. As the design progressed and some of the complexities of this project became known, .the actual GMP as determined at the 90% construction drawing stage exceeded the noHo-exceed amount in the original agreement. PROJECT SCOPE AND CONTRACTUAL REOUIREMENTS The Design-Build Agreement with Erickson-Hall Construction Co. provides the City with a fully functional Mount San Miguel Community Park including the facilities and site work required to provide park service to residents ofthat community as well as other residents of the City. The First Amendment (Exhibit A) to the Design Build Agreement between the City of Chula Vista and Erickson-Hall Construction Co. will include setting the GMP at $8,688,462 which includes the revised Design Fees and General Conditions costs consistent with the project cost (Attachment I) and revise the statement for Substantial and Final Completion dates. The GMP shall include all design and construction services to complete a fully functional park. The GMP is higher than the not-to-exceed amount in the original agreement due to the process of refining the various project elements. Staff has made every effort in value engineering the project and concurs with the Design Builder's GMP amount. The increase in the GMP is a result of two-year project delay, unanticipated site conditions, increases in the price of fuel and materials, new environmental guidelines, as well as a master plan which at the time (2004) was overly optimistic when it came to actual construction/management costs wher~by the scope of work exceeded the budget. Based on the City's financial condition and proposed budget reductions, the City Manager asked that construction of the park be delayed until the City was in a better financial condition to handle the operating costs of the park. In that two-year delay, the price of fuel and materials increased as a result of the current downturn in the economy and new environmental guidelines regarding (Stormwater Prevention Pollution Program) SWPPP regulations and permanent Best Management Practices (BMPs) which had to be incorporated to meet the new guidelines. In addition, unanticipated soil and rock conditions provided for geotechnical challenges and the relocation of existing utilities contributed to the cost of design and construction. 5-2 10/07/08, ltem2 Page 3 of 4 As Council may recall, the original GMP was set in 2006. Over the past two years, the Design Build Team (DBT) created a value-engineered scope that was near or at the original budget of $5.8M, which resulted in a significantly reduced scope. This severely impacted the programming of the Park and was unacceptable. At that point in time, staff directed the DBT to include all the scope of work in the master plan and value-engineer items that did not impact the original scope, which has brought us to where we are today with a GMP of$8.7M. By doing this, the City will realize a much nicer, programmable park while maintaining the original scope of work. It should be noted that although the GMP has increased, in comparison to a recently completed Design Build Community Park, Salt Creek, the estimated cost per acre for Mt. San Miguel Park is an increase of approximately 10%. Calculated as follows: Actual Park Costs (Salt Creek) $381,000/acre vs. Estimated Cosntruction Park Costs (Mt. San Miguel Community Park) $420,000/acre. This increase is reasonable based on the items described above. The Substantial and Final completion dates will be amended to include the revised Substantial Completion date of "no later than twelve (12) months after the Notice to Proceed" and the revised Final Completion date of no later than thirty (30) calendar days from Substantial Completion. The total cost of the project and GMP exceed the amount set forth in the Design Build Agreement as the amount not- to-exceed cost of the project. At the time of the Design Build Agreement, staff recommended an amount not-to-exceed that was less than the total budgeted cost of the project. This is commonly done, as the costs of the project that are estimated at the master plan level rarely remain consistent through the design process. By establishing a less than budgeted amount not- to-exceed, staff is better able to focus the design builder on designing a project that remains within our budgetary constraints. Staff felt it prudent at that time to establish a conservative cost of the project and be able to respond to unexpected changes in material costs. The final design of the project remains consistent with the adopted master plan. CHANGE ORDERS Under the designlbuild process, change orders are handled differently than under the designlbidlbuild process. Change orders are only returned for Council approval if they exceed the approved GMP, or are for additional work requested by City, which results in a significant change to the original scope. Otherwise, change orders are reviewed/approved by staff and the design builder. This practice is commonplace when using the designlbuild construction technique. DECISION MAKER CONFLICT Staff has reviewed the property holdings of the City Council and has found no property holdings within 500 feet of the boundaries of the property which is the subject of this action. 5-3 10/07/08, Item--5- Page 4 of 4 FISCAL IMP ACT PROJECT COSTS GMP $8,688,462 Master Plan (complete) $96,245 Land Purchase (complete, approved by Reso 2008-164) $350,000 City Staff Costs, Consultant and Oversight (including geotech/special inspections) $400,000 Utilities $350,000 City Contingency $200,000 FF&E $10,000 TOTAL PROJECT COSTS $10,094,707 PROJECT FUNDS Existing Appropriation $1,190,386 San Miguel Ranch CFD 2001-1 $1,134,922 Additional Appropriation (PAD Funds) $7,769,399 TOT AL PROJECT FUNDS $10,094,707 Erickson-Hall Construction Co. has requested the GMP be set at $8,688,462. The GMP includes, but is not limited to, design services, general conditions, insurance, bonds, construction management, the cost for all labor, equipment, and material to design and build a fully functional park in accordance with all applicable building codes. ;The total project cost is $10,094,707. Approval of tonight's first resolution will approve the first amendment to the agreement with Erickson-Hall Construction Co. to incorporate the Guaranteed Maximum Price (GMP) for the design and construction of Mount San Miguel Community Park (CIF PR260) located in the San Miguel Ranch Neighborhood in Eastern Chula Vista and authorize the Mayor to execute said amendment. In addition, tonight's second resolution will authorize amending the Fiscal Year 2008/09 Capital Improvement Program and appropriate $7,769,399 from the available PAD fund balance to Mount San Miguel Community Park (CIF PR260). Project funding in the amount of $1,134,922 will be paid directly from the Community Facilities District (CFD) 2001-1 identified as Improvement 15 which was established for this purpose. An allowance of $100,000 is within the GMP to be used towards limited maintenance for one year once a maintenance program has been agreed upon by staff and the Design Builder. Thereafter, Public Works will acquire an annual on-going cost for the park of approximately $11,904 per acre in FY 2010-11. ATTACHMENTS Attachment 1 - Revised Exhibit 2, Design Build Fee Structure Exhibit A - First Amendment to the Design Build Agreement Prepared by: Merce LeClair, Sr. Management Analyst, Engineering Dept. and Gordon Day, Sr. Building Project Manager, Engineering Dept. J:IGeneral ServiceslGS AdministrationlCouncil AgendaIMount San Miguel ParklSan Miguel GMP Al13 Final 093008 doc 5-4 Mt. San Miguel Community Park GMP with VE and Maintenance Allowance Mt. San Miguel Community Park - GMP incl VE and Maint 1. GMP Construction Budget - including 5% contingency 2. General Conditions -12 Months (11 months prior to GMP with VEl 3. Subtotal - Hard Construction Costs 4. Design/Builders Fee - sliding scale Fee on first $1,000,000 of construction cost Fee on next $500,000 over $1 ,000,000 - 6% Fee on next $500,000 over $1,500,000 - 51/2% Fee over $2,000,000 - 5% 5. Total - Preliminary Cost of Construction Estimate Design and Pre-Construction Fees: 6. Preconstruction Services for Design/Builder - sliding scale Preconstruction fee on first $1 ,000,000 of construction cost Preconstruction fee on construction cost over $1 mil. - 3/4% 7. AlE Site Design Fees Schematic Design 50% CD Design 100% CD Design Final CD Construction Administration As-Built Preparation Design Meetings 8. AlE Building Design Fees 9. Topo Verification of Existing Site Budget 9.1 Additional Topo survey authorized by City 9.2 Geotech report/geotech testing/materials testing by CTE 9.3 Additional CTE WQTR Report Requirements auth by City 9.4 Complete VE Design Allowance 10. Reimbursables Budget Total Preliminary Design & Build Cost 11. Cost of bond premium - sliding scale First $500,000 - $12.00 per 1,000 Premium over $500,000 - $8.00 per 1,000 12. Insurance 13. Building/Utility/Site Fees (by owner) 14. City staffing / Inspections (by owner) 15. Additional 1 yr Landscape Maintenance Allowance (Scope TDB) Total Preliminary Project Cost Design Fees, Pre-Construction Fees and GC Summary: General Conditions (line item 2 above) Design and Pre-Construction Fees (line items 6-9.4 above) Total Design Fees, Pre-Canst. Fees and General Conditions Erickson-Hall Construction Co. Sept 30, 200 5-5 fl.TTACHMENT I GMP with VE $ 7,249,813 $ 276,000 $ 7,525,813 $ 100,000 $ 30,000 $ 27,500 $ 276,291 $ 7,959,604 $ 20,000 $ 52,197 $ 14,650 $ 93,925 $ 70,580 $ 31,155 $ 39,998 $ 7,135 $ 9,040 $ 68,180 $ 5,000 $ 9,215 $ 65,000 $ 2,360 $ 25,000 $ 20,000 $ 8,493,038 $ 6,000 $ 63,944 $ 25,479 $ $ $ 100,000 $ 8,688,462 $ 276,000 $ 513,435 $ 789,435 THE ATTACHED AGREEMENT HAS BEEN REVIEWED AND APPROVED AS TO FORM BY THE CITY ATTORNEY'S OFFICE AND WILL BE FORMALL Y SIGNED UPON APPROVAL BY THE CITY COUNCIL -!h~~~O!5~ ~ Bart Mlesfeld II Interim City Attorney Dated: lo/,/o'g First Amendment to the Design/Build Agreement between the City of Chula Vista and Erickson-Hall Constru,ction Co. . for Design and Construction of Mt. San Miguel Community Park 5-6 First Amendment to the DesignlBuild Agreement between the City of Chula Vista and Erickson-Hall Construction Co. For Design and Construction of Mt. San Miguel Community Park This First Amendment is made and entered into this 7th day of October, 2008 by and between the City of Chula Vista ("City"), a mUIllcipal corporation, and Erickson-Hall Construction Co. ("Design Builder or DiB"). City and Design Builder are sometimes referred to as Parties ("Parties") RECITALS WHEREAS, the City and D/B entered into an agreement ("Original Agreement") dated September 19, 2006 and approved by City Council Resolution 2006-290, whereby D/B agreed to provide design and construction services to the City for the construction of a fully functional park, Mt. San Miguel Community Park ("Project"), including the facilities and site-work; and WHEREAS, pursuant to the Original Agreement, the guaranteed maximum pnce ("OMP") was not to exceed $5,841,067; and I'.'HEREAS, due to the complexities of the Project, the actual OMP, as determined at the 90% construction drawing stage, will exceed $5,841,067; and VlHEREAS, D/B and City staff have value-engineered the Project to provide the best product at the most effective price; and WHEREAS the Parties desire to amend the Original Agreement to increase the OMP to $8,688,462 for a fully functional Mt. San Miguel Community Park. NOW, THEREFORE, in consideration of the Recitals and the mutual obligations of the Parties as set forth in this First Amendment, the City and Design Builder agree as follows: AGREEMENT 1. Section 1: General Scope of Work to be Performed bv DiE. subsection 1.3.1, in the sixth line of the paragraph, delete "$640,386" and replace \Vith "$789,435". 2. Section 1: General Scope of Work to be Performed by DiE. subsection 1.3.2, delete "March 28, 2008" and replace with "rn'elve (12) months after the City-issued Notice to Proceed" . 1 5-7 3. Section 1: Oeneral Scope of Work to be Performed bv DIB, subsection 1.3.3, delete "June 28, 2008" and replace -with "thirty (30) calendar days after "Substantial Completion" (as defined in S16.1)". 4. Section 11: Insurance. subsection 11.3.1.5, Builder's Risk PropertY Insurance, in the ninth line of the paragraph, delete "$4,800,000 million" and replace with "7.9 million". 5. Section 11: Insurance. subsection 11.3.1.5, Builder's Risk Property Insurance, in the third paragraph in this subsection, delete "$5,000" and replace with "$10,000". 6. Section 11: Insurance, subsection 11.4.1.5, delete "$4,800,000" and replace with "$7.9 Million". 7. Section 13: D/B OMP for Services and Reimbursements. subsection 13.1.1, in the first line of the paragraph, delete "$5,841,067" and replace with "$8,688,462". 8. Section 13: DIB OMP for Services and Reimbursements, subsection 13.1.1, in the second line of the paragraph, delete "$640,386" and replace with "789,435". 9. Section 13: DIB OMP for Services and Reimbursements, subsection 13.2, in the fifth line of the paragraph, delete "$253,000" and replace -with "$276,000". 10. Section 13: DIB aMP for Services and Reimbursements, subsection 13.2, in the fifth line of the paragraph, delete "$387,386" and replace with "$513,435". 11. Section 13: D/B OMP for Services and Reimbursements, subsection 13.2, in the sixth line of the paragraph, delete "$640,386", in both places in that sixth line, and replace with "$789,435", in both places in that sixth line. 12. Exhibit 2: Design Build Fee Structure, delete Exhibit 2, Design Build Fee Structure, to the Original Agreement and replace with the attached Revised Exhibit 2, Design Build Fee Structure. All other terms of the Original Agreement shall remain in full force and effect. [END OF PAGE. THE NEXT PAGE IS THE SIGNATURE PAGEl 2 5-8 Signature Page to First Amendment to the DesignlBuild Agreement between the City of Chula Vista and Erickson-HaD Construction Co. For Design and Construction ofMt. San Miguel Community Park Cheryl Cox Mayor Erickson-Hall Construction Co. ~ Na.n1e: (.. VI.._I....a1 Title: . CHoI~OtI\Cer ,i. ..:... "'-- I Co. By: City of Chula Vista By: Date: ATTEST: Donna Norris, CMC Interim City Clerk Approved as to form: Bart Miesfeld Interim City Attorney J:\General Services\GS Admil1istration\CouncH Agenda\Mount San Miguel Park\SMR Amendment and Sig Page Final 09300&.doc 3 5-9 RESOLUTION 2008- RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA APPROVING THE FIRST AMENDMENT TO THE DESIGN/BUILD AGREEMENT WITH ERICKSON-HALL CONSTRUCTION CO. FOR THE DESIGN AND CONSTRUCTION OF MT. SAN MIGUEL COM:YIUNlTY PARK TO REVISE THE GUARANTEED MAXIMUM PRfCE WH EREAS. on February In. 2004. pursuant to Resolution No 2004-044. the City COllnci I approved the Final DI'an Master Plan for a 19-acre public community park site in the San VIigucl Ranch subdivision; and WHEREAS. on September 19, 2006, pursuant to Resolution No. 2006-290, the City Council approved a Design/Build Agreement with Erickson-Hall Construction Co. for the design and construction of Mt. San Miguel Community Park; and WHEREAS, the Design/Build Agreement included a not-to-exceed price of $5.841,067 with the Guaranteed Maximum Price ("GMP") to be set upon receipt by the City of 90% CO\lstrllctioll drav'v'ings; and WHEREAS, Erickson-Hall Construction Co is nearing the end of the design phase and is re;lcI v to stan the construction phase for the Park; and WHEREAS, Erickson-Hall Construction Co. has requested that the GMP be set at S8.!,88,4(,2 and that the dates for Substantial Completion and Final Completion be revised. NOW. THEREFORE. BE [T RESOLVED by the City Council of the City of Chula Vista that it approves the First Amendment to the Design/Build Agreement with Erickson-Hall Construction Co. for the design and construction of Mt. San Miguel Community Park to revise the (;uaranleed Maximum Price. Presemed by: Approved as to form by . JiL,,-1L ~ Bali Miesfeld Interim City Attorney / n~ {/ Richard A. Hopkins Director of Engineering IIT~:i r I ~ I-.I~ 1< I': L: \( lS RI.:~I\~~()()X ] (1-()7 -llk'}vlt \Jll IVI i~L1c1 Il'~1\ : I'c\i~cd hy' 'x .dnc 5-10 RESOLunON 2008- REsownON OF THE C[TY COUNCfL OF THE CITY OF CHULA VISTA AMENDrNG THE FISCAL YEAR 2008/2009 CIP PROGRl\M AND APPROPRIATING $7.769,399 FROM THE AVAILABLE PARK ACQUISITION AND DEVELOPMENT (PAD) FUND BALANCE TO EXISTlNG CAP[TAL IMPROVEMENT PROJECT, MOUNT SAN MIGUEL COMMUNITY PARK (CIP PR260) TO COMPLETE THE PROJECT WHEREAS. on Febl-uary 10, 2004. pursuant to Resolution No. 2004-044. the City Council approved the Final Draft Master Plan for a 19-acre public community park site in the San,\[ I"uel Ranch subdivision; and WHEREAS. on September 19. 2006. pursuant to Resolution No. 2006-289. the City Counci I e,;tabl ished a new Capital Improvement Project entitled "MoLll1t San Miguel Community Park (PR260)"': and WHEREAS. on September 19. 2006. pursuant to Resolution No. 2006-290. the City Council approved a Design/Build Agreement with Erickson-Hall Construction Co. for the design and construction of Mt. San Miguel Community Park; and WH EREAS. the Design/Build Agreement contain'ed a not-to-exceed price of $5.841.067 with the GMP to be set upon receipt of90% construction drawings. WHEREAS, Erickson-Hall Construction Co. has requested the GMP be set at $8,rJ88,462; and WHEREAS. the total project cost for Mt. San Miguel Community Park is $lO,094.707; and WHEREAS. staft- requests that $7.769.399 from the available Park Acquisition and Development ("'PAD"') runci balance be appropriated to the Mount San Miguel Community Park (CIP PR260) project. 5-11 NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Chula Vista that it amends the Fiscal Year 2008/2009 C1P Program and appropriates $7,769,399 from avail,lble Park Acquisition and Development ("PAD") Fund balance to existing Capital Improvement Project Mount San Miguel Community Park (CIP PR260) to complete the project Presented by: Approved as to fonn by Richard A. Hopkins Director of Engineering Y-i'-o~_ t~ -01.-?~l ~ Bart Miesfeld / ? Interim City Attomey 1--[: 1:\ i i I N F F I": I~ I~:,,( J."R<:~lls2(j(jX' 11l_()7 -():-\',v!t SJll rvl iO;lIel 1-<:Sl' :: r"evised hy ec.d\lc 5-12