RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA ACCEPTING BIDS AND AWARDING THE
CONTRACT FOR THE "SLOPE REPAIR AT OLYMPIC
PARKWAY BETWEEN HERITAGE ROAD AND SANTA
VENETIA STREET (CFD97-IB)" PROJECT TO MJC
CONSTRUCTION IN THE AMOUNT OF $38,500 AND
AUTHORIZING THE DIRECTOR OF PUBLIC WORKS TO
EXPEND ALL AVAILABLE FUNDS AND ISSUE CHANGE
ORDERS AS NECESSARY IN AN AGGREGATE AMOUNT
NOT TO EXCEED $9,625 TO COMPLETE THE PROJECT
WHEREAS, the proposed project provides for the reconstruction of a slope on the north
side of Olympic Parkway between Heritage Road and Santa Venetia Street in the City of Chula
Vista; and
WHEREAS, on December 18, 2007, Engineering and General Service staff received and
opened informal bids from three contractors as follows:
CONTRACTOR BID AMOUNT
1. MJC Construction - Bonita, CA $38,500.00
2. CASS Construction, Inc., - El Cajon, CA $39,600.00
3. R.H. Pollock Grading, Inc., - San Diego, CA $48,750.00
WHEREAS, staff recommends awarding the contract in the amount of $ 38,500.00 to
MJC Construction; and
WHEREAS, references provided by the Contractor have been reviewed and their work
record found to be satisfactory and the Contractor's license is current; and
WHEREAS, the Environmental Review Coordinator has reviewed the proposed action
for compliance with the California Environmental Quality Act (CEQA) and has determined that
this action qualifies for a Class 7 categorical exemption pursuant to Section ] 5307 [Actions by
Regulatory Agencies for Protection of Natural Resources] of the State CEQA Guidelines. Thus,
no further environmental review is necessary; and
WHEREAS, the City Council authorizes the City's Purchasing Agent to execute contract;
and
WHEREAS, there is no impact on the General Fund as the funds for this project have
been provided as part ofthe CFD funds.
Resolution No. 2008-019
Page 2
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Chula
Vista does hereby award a contract in the amount of $38,500.00 for the reconstruction of the
slope on the north side of Olympic Parkway between Heritage Road and Santa Venetia Street in
the City ofChula Vista, California" (CFD97-1B) project to MJC Construction and authorizes the
Director of Public Works Operations to expend all available funds and issue change orders as
necessary in an aggregate amount not to exceed $9,625 to complete the project.
Presented by
Approved as to form by
ngineering and General Services
~Y<:K\~~~~
Ann Moore
City Attorney
PASSED, APPROVED, and ADOPTED by the City Council of the City of Chula Vista,
California, this nnd day of January 2008 by the following vote:
AYES:
Councilmembers:
Castaneda, McCann, Ramirez, Rindone, and Cox
NAYS:
Councilmembers:
None
ABSENT:
Councilmembers:
None
ChJ~:tt-
ATTEST:
terim City Clerk
STATE OF CALIFORNIA )
COUNTY OF SAN DIEGO )
CITY OF CHULA VISTA )
I, Donna R. Norris, Interim City Clerk of Chula Vista, California, do hereby certify that the
foregoing Resolution No. 2008-019 was duly passed, approved, and adopted by the City Council
at a regular meeting of the Chula Vista City Council held on the 22nd day of January 2008.
Executed this 22nd day of January 2008.
I~~ I 'A~
Donna R. Nodis, cMc, Interim City Clerk
~