HomeMy WebLinkAbout2007/12/11 Item 5
CITY COUNCIL
AGENDA STATEMENT
ITEM TITLE:
SUBMITTED BY:
REVIEWED BY:
12/11/07, Item~
RESOLUTION ACCEPTING BIDS AND AWARDING
THE CONTRACT FOR THE "G STREET SEWER PUMP STATION
REHABILITATION PROJECT IN THE CITY OF CHULA VISTA,
CALIFORNIA (CIP NO. SW-238)" TO TAMANG ELECTRIC, INC.IN
THE AMOUNT OF $477,420 AND AUTHORIZING THE DIRECTOR
OF PUBLIC WORKS TO ISSUE CHANGE ORDERS AS NECESSARY
IN AN AGGREGATE AMOUNT NOT TO EXCEED $71,613
DIRECTOR OF ENG~INEERING AND GENERAL SERVICES ~~
CITY MANAGER
ASSISTANT CITY AGER 'S /
4/STHS VOTE: YES i:8;J NO D
BACKGROUND
The proposed project provides for the rehabilitation of the "G" Street sewer pump station located
on "G" Street west of the Goodrich Company western property gate and east of Marina Parkway
in the City of Chu1a Vista. On Wednesday, November 7, 2007 at 2:00 p.m, the Director of
Engineering and General Services received seven (7) sealed bids for the "G" Street Sewer Pump
Station Rehabilitation Project, in the City ofChu1a Vista, California (CIP No. SW-238)".
ENVIRONMENTAL REVIEW
The Environmental Review Coordinator has reviewed the proposed project for compliance with
the California Environmental Quality Act (CEQA) and has determined that the project qualifies
for a Class 2(c) categorical exemption pursuant to Section 15302, entitled Replacement or
Reconstruction of the State CEQA Guidelines. Thus, no further environmental review is
necessary.
RECOMMENDATION
Council adopt resolution accepting bids and awarding contract for the "G" Street Sewer Pump
Station Rehabilitation Project in the City ofChu1a Vista, California (CIP No. SW-238)" project
to Tamang Electric, Inc., in the amount of $477,420 and authorizing the Director of Public
Works to issue change orders as necessary in an aggregate amount not to exceed $71,613.
BOARDS/COMMISSION RECOMMENDATION
Not applicable.
5-1
12/11/07, Item~
Page 2 of 4
DISCUSSION
This project consists of various improvements to the existing City of Chula Vista "G" Street
Sewer Pump Station. The work generally includes the removal and disposal of existing
improvements, a new concrete slab supported by columns for the pump room, new pumps,
motors, piping, valves and appurtenances, new asphalt concrete pavement, new emergency diesel
generator, a section of new chain link fence with a sliding gate, lining of the existing wet well,
new fiberglass grating, various building improvements including a new roof, doors, skylights and
ventilation, and the construction of all appurtenances and other work as may be required to
complete and render project workable. The items are to be constructed, finished and installed in
a complete and workmanlike manner in accordance with the plans and specifications.
The proj ect is located west of the Goodrich Company western property gate and east of Marina
Parkway in the City of Chula Vista. The existing pump station was originally built in 1969. It
has been modified several times over the years. The pump station facility conveys raw
wastewater via a force main into City of San Diego Metro Interceptor.
The project originated in 2005 as a full upgrade to current standards including emergency
storage, new pumps, generator, and a new building at a cost of five million dollars. At that time
more formal negotiations regarding the Bayfront development were taking place. As this project
was being advertised as a design built proj ect and the vision for the Bayfront unfolded, staff
realized the opportunity of ultimately eliminating this pump station. The Bayfront development
was proposing a sewer line close to the location of the pump station that would eliminate the
need for a pump station. At that point staff reanalyzed the benefit of such a large investment for
a full upgrade to a temporary pump station and revised the project. The project before Council
tonight is a limited upgrade to vital components of the station as described above. Because of
the pump station's proximity to the bay and the age of its equipment these upgrades are
necessary to curve the risk of a sewage spill for the next five to ten years.
BID ACCEPTANCE
On November 7, 2007, Engineering and General Services staff received and opened bids from
seven (7) contractors as follows:
CONTRACTOR BID AMOUNT
1. Tamang Electric, Inc. - Chino, CA $477,420.00
2. Cass Construction, Inc. - EI Cajon, CA $525,957.00
3. Southwest Civil Contracting, Inc. San Marcos, CA $526,700.00
4. DenBoer Engineering and Construction, Inc. - Thousand Palms, CA $527,000.00
5. Orion Construction Corp. - Vista, CA $547,300.00
6. Ahrens Corp San Diego, CA $599,360.00
7. NEWest Construction Co., Inc San Diego, CA $628,375.00
The apparent lowest bid of $477,420 submitted by Tamang Electric, Inc. is $7,420 or
approximately 1.5% higher than the Engineer's estimate of $470,000. The Engineer's estimate
was based on average prices for similar types of work completed during the last two years as
provided by our consultant, Boyle Engineering Corp. On November 8th, 2007 a protest was file
by Cass Construction, Inc. (the second lowest bidder) on the grounds that Tamang Electric Inc.
5-2
12/11/07, Item~
Page 3 of 4
had only listed one subcontractor. City specification call for any subcontractor that will perform
work in excess of Y2 of I percent be listed. Because this project involves such variety of
disciplines, the second lowest bidder requested that the City investigate this issue. City staff
contacted Tamang Electric, Inc. and requested proof that they were able to perform all work
necessary for this project. Tamang Electric, Inc. issued a letter assuring the City of their
capabilities and included references for each discipline. References provided by the contractor
have been reviewed and their work record found to be satisfactory. This Contractor has worked
consistently with other City's standards and State standards. The Contractor is familiar with our
City's Standards and is bound to comply with our requirements. The Contractor's license is in
good standing and is current. Cass Construction, Inc. was informed of the City's findings and
had no further issue.
Approval of tonight's resolution will also authorize City staff to expend all available funds and
increase the value of the contract as necessary due to unforeseen circumstances. Unforeseen
circumstances may cause an increase in quantities beyond what was anticipated during the
preparation of the project specifications. Due to the age of the surrounding area, unforeseen
circumstances may occur during the removal of the existing improvements and the Contractor
may find field conditions different from proposed improvement plans and specifications. As a
result, a change order for additional labor and/or material may be required to complete the
project. This is a typical situation with all underground projects built within this area.
According to City Council Policy No. 574-01, if a change order exceeds the cumulative contract
change order aggregate amount allowable to be approved by the Director of Public Works
Operations, City Council approval is required. Under said City Council Policy, the amount
would be $47,742. However, approval of tonight's resolution will increase the Director of
Public Works Operations' authority to approve change orders as necessary up to the contingency
amount of $71,613 (an increase of $23,871). If this money is not used during construction, the
additional funds shall be returned to the original funding source - Sewer Facilities Replacement
Fund.
DISCLOSURE STATEMENT
Attached is a copy of the Contractor's Disclosure Statement (Attachment 2).
STAFF COSTS
After the advertisement of this project as a Design-Build full upgrade to the pump station,
additional staff time was necessary to reanalyze this project and to invest the appropriate amount
of funds at this location given the forecasted development of the Bayfront area and the need for
upgrading the old equipment. The rehabilitation of pump stations is not typical of the work the
City performs, consequently, staff sought the expertise of an engineering firm to help resolve the
complex issues associated with the design of the required improvement for this pump station
project. Staff also provided technical support/oversight during the design phase and managed the
project advertisementlbidding process. It is pertinent to note that Boyle Enginering is one of
three firms that have an on-call contract with the City to support the Engineering and General
Services Department for expertise and workload issues.
DECISION MAKER CONFLICT
Staff has reviewed the property holdings of the City Council and has found no property holdings
within 500 feet of the boundaries of the properties which are the subject of this action.
5-3
12/11/07,IteID~
Page 4 of 4
FISCAL IMPACT
At this time, staff recommends awarding the contract in the amount of $477,420 to accomplish
the construction of the capital improvement project SW-238.
FUNDS REQUIRED FOR PROJECT
Contract Amount $477,420
Contingencies (15% of contact amount) $71,613
Total Hard Cost (T.H.C) $549,033
Consultants and Staff Time Cost
Consultant Staff Time Total % ofT.H.C.
Design/Construction Management $80,000 $40,000 $120,000 21.86%
Construction Inspection $0 $10,000 $10,000 1.82%
Environmental $0 $118 $118 0.02%
Engineering $0 $21,072 $21,072 3.84%
Structural $0 $10,000 $10,000 1.82%
Fire $0 $205 $205 0.04%
Bldg and Parks Construction $0 $55,000 $55,000 10.02%
Right of Way $0 $1,000 $1,000 0.18%
City Attomey/Finance/GIS $0 $1,000 $1,000 0.18%
Testing and Study $10,000 $0 $10,000 1.82%
Permits and Other Proiect Cost
Title Reports $0
Property Owner's Compensation $0
Miscellaneous $0
Total Soft Cost $228,394
TOTAL $777,427
FUNDS BUDGETED FOR PROJECT
A. Sewer Facilities Replacement Fund $ 777,427
TOTAL FUNDS BUDGETED FOR PROJECT $ 777,427
The project is currently funded with funds frOID the Sewer Facilities Replacement Fund and there
are sufficient funds to complete the project. There is no impact to the General Fund. Upon
completion of the project, the improvements will require only routine City maintenance.
ATTACHMENTS
Attachment 1 - Project Area Plat
Attachment 2 - Contractor Disclosure Statement
Prepared by: Roberto Yano. Sr. Civil Engineer, Engineering and General Services
M:\General Services\GS Administration\Council Agenda\SW238 G St Sewer Pump Station\SW238 Agenda 112707~FINAL.doc
5-4
.........
.........
?\>.\l?"\>.'~
,,\l\l"\l~V\>.
~/~
SW2J8 PROJECT SITE
SEWER PUMP STA TION OUTSIDE
OF THE GOODYEAR PROPERTY
DRAWN BY:
POTEN G.
DATE::
11-28-07
nTLE:
ATTACHMENT /
SAN PEDRO
SHEET 1
OF 1 SHTS.
CITY OF CHULA VISTA
G S1REET SEWER PUMP STAlKlN RaIABlUTAlION
(aP NO. 5W-238)
PROJECT FILE #SW2J8-08
PREPARED BY:
POTEN G. SAN PEDRO
APPROVED BY:
ROBERTO YANO
5-5
"'rTACHMENT ~
CITY OF CHULA VISTA DISCLOSURE STATEMENT
Pursuant to Council Policy 101-01, prior to any action upon matters that will require discretionary action
by the Council, Planning Conunission and all other official bodies of the City, a statement of disclosure of
certain ownership or financial interests, payments, or campaigo contributions for a City of Chula Vista
election must be filed. The followiog information must be disclosed:
1. List the names of all persons having a financial interest in the property that is the subject of the
application or the contract, e.g., owner, applicant, contractor, subcontractor, material supplier.
NONE
2. If any person" identified pursuant to (1) above is a corporation or partnership, list the names of all
individuals with a $2000 investroent in the business (corporation/partnership) entity.
NONE
3. If any person" identified pursuant to (1) above is a non-profit organization or trust, list the names
of any person serving as director of the non-profit organization or as trustee or beneficiary or
trustor of the trust
NONE
4. Please identify every person, including any agents, employees, consultants, or independent
contractors you have assigoed to represent you before the City in this matter.
NONE
5. Has any person" associated with this contract had any linancial dealings with an official"" of the
City ofChula Vista as it relates to this contract within the past 12 months? Yes_ NO-LL
NONE
17
M:\General Services\Design\SW23S\Contract CVVJI-G St Sewer PS-Pan l-FinaLdoc
5-6
If Yes, briefly describe the nature of the financial ioterest the official-- may have io this contract.
6. Have you made a contribution of mOre than $250 within the past twelve (12) months to a current
member of the Chula Vista City Council? No X Yes _ If yes, which Council member?
7. Have you provided more than $340 (or an item of equivalent value) to an official.- of the City
of Chula Vista in the past twelve (12) months? (This includes being a source of income, money to
retire a legal debt, gift, loan, etc.) Yes_ No L
If Yes, which official-- and what was the nature of item provided?
Date:
11/07/07
;1
~!*'^-
.atun a C 1 lcant
~
Abel Tamang
Print or type name of Contractor! Applicant
· Person is defined as: any individual, firm, co-partnership, joint venture, association, social
club, fraternal organization, corporation, estate, trust, receiver, syndicate, any other county,
city, municipality, district, or other political subdivision, -or any other group or combination
acting as a unit.
.. Official includes, but is not limited to: Mayor, Council member, Planning Commissioner,
Member of a board, commission, or committee of the City, employee, or staff members.
18
M:\General Services\Design\SW23B\Contract CV\OI~G Sf Sewer PS~Part I-Final.doc
5-7
RESOLUTION NO. 2007-
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA ACCEPTING BIDS AND AWARDING THE
CONTRACT FOR THE "G STREET SEWER PUMP STATION
REHABILITATION PROJECT (CIP NO. SW-238)" TO
TAMANG ELECTRIC, INe. IN THE AMOUNT OF $477,420,
WAIVING COUNCIL POLICY 574-01, AND AUTHORIZING
THE DIRECTOR OF PUBLIC WORKS TO ISSUE CHANGE
ORDERS AS NECESSARY IN AN AMOUNT NOT TO
EXCEED $71,613
WHEREAS, City staff and the consultant fIrm of Boyle Engineering Corporation
prepared the plans, contract documents and technical specifications for "G Street Sewer Pump
Station Rehabilitation Project in the City ofChula Vista, California (CIP No. SW-238)"; and
WHEREAS, on Wednesday, November 7,2007 at 2:00 p.m., the Director of Engineering
and General Services received seven (7) sealed bids for the "G Street Sewer Pump Station
Rehabilitation Project in the City ofChula Vista, California (CIP No. SW-238)"; and
WHEREAS, the lowest bid was submitted by Tamang Electric, Inc.; and
WHEREAS, staff has reviewed references for Tamang Electric, Inc. and found them to
be satisfactory for the rehabilitation of the sewer pump station; and
WHEREAS, there are suffIcient funds in "G Street Sewer Pump Station Rehabilitation
Project in the City ofChula Vista, California (CIP No. SW-238)" to complete the job; and
WHEREAS, pursuant to Council Policy 574-01, the City Council shall consider all
change orders involving changes in the scope of the project, increases of contract amounts
greater than 1 0 percent for contracts up to $100,000, or aspects concerning the public health,
safety, or welfare; and
WHEREAS, as with all underground projects built within this area, unforeseen
circumstances and field conditions different from the proposed improvement plans and
specifIcations may occur during the removal of the existing improvements; and
WHEREAS, staff recommends that the City Council waive Council Policy 574-01 to
give the Director of Public Works the authority to approve change orders up to the contingency
amount of$71,613.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City ofChula Vista
as follows:
5-8
1. That it accepts bids and awards the contract for the "0 Street Sewer Pump Station
Rehabilitation Project in the City of Chula Vista, California (CIP No. SW-238)" to
Tamang Electric, Inc. in the amount of $477,420.
2. That it waives Council Policy 574-01 and authorizes the Director of Public Works to
issue change orders as necessary in an amount not to exceed $71,613.
Presented by
Approved as to form by
Jack Griffin
Director of Engineering and General Services
y"b-~J,vC. -~ ~
Ann Moore (,;
City Attorney
H:\ENGfNEER\RESOS\Resos2007\12_11 ~07\sw238 Reso 1 REV.FrNAL-st revised by ec.doc
5-9