HomeMy WebLinkAbout2007/05/01 Item 7 CITY COUNCIL AGENDA STATEMENT ~~f::. CllY OF ~- (HULA VISTA 05/01107 Item~ SUBMITTED BY: REVIEWED BY: RESOLUTION APPROVING A CHANGE ORDER REQUESTED BY MCMILLIN LAND DEVELOPMENT ASSOCIATED WITH STORM DRAIN FACILITIES CONSTRUCTED IN BIRCH ROAD WITHIN THE SR125 RIGHT-OF-WAY. x- CITY ENGINEER S) / INTERIM CITY MANAGER Ji ITEM TITLE: 4/5THS VOTE: YES D NO ~ BACKGROUND On January 23, 2007, McMillin Land Development submitted a payment request for reimbursement in the form of Transportation Development Impact Fee (TDIF) credits for the construction of storm drain facilities in Birch Road within the SR125 right-of-way. The change order total of $302,206.19 is above the $50,000 limit and therefore requires Council approval. Tonight, Council will consider approving the TDIF change order for the construction of the storm drain facilities associated with Birch Road and the reimbursement to McMillin in the form ofTDIF credits. ENVIRONMENTAL REVIEW The Environmental Review Coordinator has reviewed the proposed actIVIty for compliance with the California Environmental Quality Act (CEQA) and has determined that the activity is not a "Project" as defined under Section 15378 of the State CEQA Guidelines therefore, pursuant to Section 15060(c)(3) of the State CEQA Guidelines the activity is not subject to CEQA. Thus, no environmental review is necessary. RECOMMENDATION That Council adopt the Resolution approving a change order requested by McMillin Land Development associated with storm drain facilities constructed in Birch Road within the SRl25 right-of-way. BOARDS/COMMISSION RECOMMENDATION Not applicable. 7-1 05/01/07, Item -:; Page 2 of3 DISCUSSION The TDIF program is responsible for the equitable construction of major roads east ofI- 805 by developers. The program works by allowing developers to competitively bid and construct these roads. The audited cost is applied as a credit that can be used in lieu of paying the TDIF fee at building permit issuance. Therefore, the City's general fund does not finance the construction of TDIF facilities. Staff brings all TDIF change orders above a cumulative $50,000 to City Council for their consideration prior to authorizing the TDIF credit for the developer. On January 23, 2007, McMillin Land Development submitted a TDIF credit request for the construction of storm drain facilities constructed by TC Constmction Company within Birch Road. The current TDIF program dated January 5, 2005, identifies this portion of Birch Road as a portion of Facility #42 and #43 (See Figure 1). The TDIF estimate for facilities 42 and 43, Birch Road from La Media to Eastlake Parkway, was $11,438,026 (See Table 1 below and Exhibit 1). The original contract between McMillin and TC Constmction Company encompassed the construction of Birch Road from Magdalena Avenue to the western right-of-way line of SR125. Subsequently, McMillin received an encroachment permit from Caltrans, which allowed them to expand the scope of work through the right-of-way of SR125 as shown in Figure 1. This additional work was added to the contract using the originally competitively bid unit prices. Although the actual costs for the drainage facilities exceed the cost estimates, the overall project is well below the overall TDIF cost estimate as shown in Table 1 below. The reason for the cost difference was that the TDIF cost estimate assumed smaller pipe sizes than were actually constructed. Staff recommends approval of the change order because the overall costs were below budget and are therefore within the projections of the currently approved TDIF fee program. Table 1 Birch Road Construction Cost Comparison TDIF Facility 42 TDIF Facility 43 (La Media Road to (Centerline of ;To18ls for 42 and 43' the Centerline of SR125 to Easllake (La Medfa Road to SR125 Parkwa i Eastlake Parkwa Actual Totals for TDlF eligible facilities Storm Drain Facilities Overall $637,000.00 $8,937,276.00 $227,500.00 $2,500,750.00 Construction of storm drain facilities is now complete and McMillin is requesting reimbursement in the form ofTDIF credits, for the storm drain component of the work in the amount of$302,206.l9 (See Exhibit 2). There is one Resolution for this item on tonight's agenda, which, if adopted, will accomplish the following: I The requested change order of $302,206.19 is embedded in this cost. 2 Obtained through reimbursement requests and estimates from McMillin Land Development 7-2 05/01/07, Item~ Page 3 of3 . Approve the TDIF change order for the construction of storm drain facilities in Birch Road within the right-of-way for SR125. . Award $302,206.19 in TDIF cash credits to McMillin Land Development. DECISION MAKER CONFLICT Staff has reviewed the property holdings of the City Council and has found no property holdings within 500 feet of the boundaries of the property which is the subject of this action. FISCAL IMPACT There will be no direct fiscal impact to the City. Costs associated with this processing will be borne by the developer. ATTACHMENTS Attachment 1: Limits of work Attachment 2: TDIF cost estimate Attachment 3: Storm Drain change order breakdown Prepared by: Chester Bautista, Associate Civil Engineer, Engineering Department J:IEngineerIAGENDAICAS2007105-0 l-07\Birch Road Change Order v2.doc 7-3 -.i I .po. ~ TDIF Facility 43 ,Birch RD Ph,'2 lChal\ge order) " \ ~ ATTACHMENT 2 Birch Road Change Order (TDIF) Facility Description Price No. $tqtmjl(?t~ril~iR '-".,,,. .. .,;." :;:,'-.",.::::,:,:,:,::,.:::,:,,:,',:,-":. 1 66" 1500D RCP T&G 1,254.00 1,254.00 $ 190.00 $ 238,260.00 $ 238,260.00 2 54" 1500D RCP W/T1 154.00 154.00 $ 37.00 $ 5,698.00 $ 5,698.00 3 30" 1500D RCP T&G 48.00 4.25 $ 37.00 $ 1,776.00 $ 157.25 4 24" 1500D RCP T&G3 207.00 110.15 $ 45.00 $ 9,315.00 $ 4,956.75 5 18" 2000D RCP T&G 203.00 104.87 $ 37.00 $ 7,511.00 $ 3,880.19 6 MOD A-8 CLEANOUT 1.00 1.00 $ 5,350.00 $ 5 350.00 $ 5 350.00 7 A-7 CLEAN OUT 2.00 2.00 $ 4,630.00 $ 9 260.00 $ 9,260.00 8 12" B-1 CURB INLET 1.00 1.00 $ 4,217.00 $ 4217.00 $ 4,217.00 9 11' B-1 CURB INLET 2.00 2.00 $4,125.00 $ 8 250.00 $ 8 250.00 10 10' B-1 CURB INLET 1.00 1.00 $ 4,362.00 $ 4,362.00 $ 4 362.00 11 9' B-1 CURB INLET 3.00 3.00 $ 3,897.00 $ 11691.00 $ 11691.00 12 8' B-1 CURB INLET 1.00 1.00 $ 3,600.00 $ 3 600.00 $ 3,600.00 .... 13 TYPE "F" CATCH BASIN4 2.00 0.00 $ 2,472.00 $ 4 944.00 $ I 14 30" WING HEADWALL 4 1.00 0.00 $ 2,800.00 $ 2 800.00 $ 01 15 66" CONCRETE PLUG 1.00 1.00 $1,120.00 $ 1,120.00 $ 1,120.00 16 24" CONCRETE PLUG 1.00 1.00 $ 435.00 $ 435.00 $ 435.00 17 18" CONCRETE PLUG 3.00 3.00 $ 323.00 $ 969.00 $ 969.00 TOTAL $ 319558.00 \$ ~OZ206}*!l; ....... ..,"-- .... ....... . Footnotes 1 Facility NO.2 - Only 18" RCP is required to drain the right of way. Price was adjusted to reflect 18" RCP 2 Facility NO.3 - Contracted Quantity included an ineligible portion of storm drain and also would only be credited for 18" RCP. Both Quanlily and Price were adjusted. 3 Facility Nos. 4 and 5 - Contracted Quantity included ineligible portions. Quantity was adjusted. 4 Facility No. 13 and 14 - Both facilities were ineligible and deleted from the total. 03/19/2007 Birch Road Change Order for TDIF Credil.xls 05-12-06 10:09 FROM-Mru; I I;. I"t. 6192927497 ATTACHMENT 2 T-257 P.003IU12 F-021 _ lAll-17-200HRl 11: Q7 AM T.C. Construction Co., Inc. P.002 --- PROPOSED CHANGE ORDER No. 2285-03 ......... 10510 PIllsp:c:L Ave. Sontee, CA 92071..4591 l'banc 619-44S-4560 Far. 619-443-3341 TITLE: BlRCHROAD - STORM DRAIN PROJECT: Qu!y:R.1nch Spa 1I Village Ii TO: Attn: Ma=lla Fescina MCMILUNLAND DEVELOPEMEN'! 2727 Hoover Ave N p DA.'J:E: 01117/2003 JOB: CON'DlACT NO: 3 . . 00001 1 0 :acPT&:G OOOOZ 54"150OPRCPWfT 154.000 LF 00003 30" l5OO:O ltCI' T&G 11 ,~q 1 'CI ~.2.5 \.f 00004 24" lSOOP ltCI' T&G aO:.B99 L:I' \\0. \Ei \..~ Sg,3tS.OO 00005 IS" 2000D RCP T&G !es.B81 Lr \O~."l.f ,$7,511.00 '--..'/ 00006 MOD A-a CLEANOUT 1.000 EA $5,350.00 00007 A.7 CI.:IiJJ'IOU! 2.000 aA $4,530.00 $9.260.00 ooooS 12' B-1 C'Oro! lNLllT 1.000 EA $4,217.00 $4,217.00 00009 11'B-1CllRBINUIT :1.000 EA $4,125.00 $8,250.00 00010 10'1l-1 CURB oozr 1.000 EA $4,362.00 $4,362.00 ooon 9' B-1 CIJRB nItEr 3.000 EA $3.897,00 Sll,691,00 OOOU S' B-I'CIJRB lNLE1' 1.000 EA. $3,600.00 $3,600.00 98913 Ymfe!f~~lN 1.~6ij ~ 31,4'fl.ae . ~4~1...a8 \N \L-WI \11 99911 3erWtifG~~I~.H. l.OO8 Q1~ Jl.A(,~.De J1.ovv...,.... l~t...\6.\t 00015 66" CONCRBTEPUlG 1.000 EA $1,120.00 $1,120.00 00016 24" CONCRBTEPLUG 1.000 EA $435.00 $43:S.00 . 00017 IS" CONCllETEWG , 3.000 EA S32.J.OO $969.00 AFFROV,*, By; Zl,.;j !J 1&Jid) I G!aDt Werdiclc Date: I Ii 103 B'/J(d;Md~j;jJ~J~' ~ ~Fescina Date: # 7. 0.3 " . ~. ~..._--_._...._..,....... . ...~_.._._.__ _ ... ..........n._ .... ......-.,......-.- "'-.----..- .- - --_.- ~ .....-. ... .. - 7-6 ATTACHMENT 3 r S T ES TIMA 'FE. '. . - . - . . -. FACILITY 42 ~L:J9~i/~~~)~::~~~~ 'j!,;::;:~~.:.:.,.,~~\"~ -~ ~ ~-~~~S!~:i.~~:~~Il::}~fi_~o:"d;f7:'l1"-:~J7:f.s.:~::-~~~~~~~t]: ~L~ ~ Birch Rd La Media Rd to SR-125 New 6 Lane Major Road Length (Lf): 4,900 1 Earthwork 2 Drainage Items 3 Surface Improvements 4 Dry Utilities 5 Landscape & Irrigation 6 Misc. Construction Logistics 7 Special Items Habitat mitigation 4,900 $ 4,900 $ 4,900 $ 4,900 $ 4,900 $ 4,900 $ 250.00 $ 130.00 $ 425.00 $ 60.00 $ 250.00 $ 10.00 $ $ Linear It Linear It Linear It Linear It Linear It Linear It Acres 13 $70,000 TOTAL HARD COSTS SOFT COSTS Contingency (15% at total hard costs including right-of-way) Civil Engineering (7.5% 01 hard costs, exciudes right-aI-way) Soils Engineering (15% 01 earthwork costs) Landscape Architecture (10% at landscaping costs) Surveying (2% 01 hard costs, excludes right-at-way) Utility Engineering/Coordination (3% 01 dry utilities costs) Inspection/Administration (6% 01 total hard costs including right-aI-way) Deveioper Administration (1.75% 01 total hard costs including right-aI-way) City Project Administration (2% at total hard costs including right-at-way) TOTAL SOFT COSTS PROJECT COST 7-7 1,225,000 637,000 2,082,500 294,000 1,225,000 49,000 91D,000 $ 910,000 $ 6,422,500 $ 963,375 $ 481,688 $ 183,750 $ 122,500 $ 128,450 $ 8,820 $ 385,350 $ 112,394 $ 128,450 $ 2,514,776 $ 8,937,276 . ATTACHMENT 3 r FACILITY 43 ITEM DESCBIPT10N . UlVlTS QTY- UNIT COST TOTAL ITEM TOTAL Birch Rd SR-125 to Eastlake Pkwy New 6 Lane Prime Arterial Length (Lf): 1,750 1 Earthwork 2 Drainage Items 3 Surface Improvements 4 Dry Utilities 5 Landscape & Irrigation 6 Misc. Construction Logistics 7 Special Items Habita}.mltigation Linear It Linear It Linear It Linear It Linear It Linear It 1,750 $ 1,750 $ 1,750 $ 1,750 $ 1,750 $ 1,750 $ 250.00 $ 130.00 $ 425.00 $ 60.00 $ 250.00 $ 10.00 $ $ Acres 7.6 $70,000 TOTAL HARD COSTS SOFT COSTS Contingency (15% of total hard costs including right-ol-way) Civil Engineering (7.5% 01 hard costs, excludes right-ol-way) Soils Engineering (15% 01 earthwork costs) Landscape Architecture (10% 01 landscaping costs) Surveying (2% 01 hard costs, excludes right-ol-way) Utility Engineering/Coordination (3% 01 dry utilities costs) Inspection/Administration (6% 01 total hard costs including right-ol-way) Developer Administration (1.75% 01 total hard costs Including right-ol-way) City Project Administration (2% 01 total hard costs including right-ol-way) TOTAL SOFT COSTS PROJECT COST 7-8 437,500 227,500 743,750 105,000 437,500 17,500 532,000 $ 532,000 $ 2,500,750 $ 375,113 $ 187,556 $ 65,625 $ 43,750 $ 50,015 $ 3,150 $ 150,045 $ 43,763 $ 50,Q15 $ 969,032 $ 3,469,782 . RESOLUTION NO. 2007- RESOLUTION OF THE CITY COUNCIL OF CHULA VISTA APPROVING A CHANGE ORDER REQUESTED BY MCMILLIN LAND DEVELOPMENT ASSOCIATED WITH STORM DRAIN FACILITIES CONSTRUCTED IN BIRCH ROAD WITHIN THE SR125 RIGHT OF WAY. WHEREAS, the City entered into an Acquisition / Financing Agreement for CFD 121 with McMillin Land Development, which authorized McMillin to construct required storm drain improvements within Birch Road, to be reimbursed from the project funds; and WHEREAS, in the course of constructing the project it was determined that additional items of work which were not previously included in the original contract needed to be constructed as part of the required storm drain improvements of Birch Road, thereby necessitating the approval of a Change Order to the contract; and WHEREAS, McMillin has completed the required Birch Road storm drain improvements; and WHEREAS, McMillin has requested that the Birch Road storm drain improvements not be financed by the CFD 121 but rather be a credit against future Transportation Development Impact Fees for the project; and WHEREAS, City staff performed an audit of the project to verify the cost of the project and further verified that the required storm drain improvements have been completed in accordance with the project plans. NOW, THEREFORE BE IT RESOLVED, that the City Council of the City of Chula Vista approves the Change Order, attachment 1 to this resolution, requested by McMillin Land Development, for the construction of Birch Road storm drain improvements within the SRl25 right- of-way. Presented by Approved as to form by Scott Tulloch City Engineer 7~7 Resolution No. 2007- Page 2 PASSED, APPROVED, and ADOPTED by the City Council of the City of Chula Vista, California, this 1st day of May, 2007, by the following vote: AYES: Councilmembers: NAYS: Councilmembers: ABSENT: Councilmembers: Cheryl Cox, Mayor ATTEST: Susan Bigelow, City Clerk STATE OF CALIFORNIA ) COUNTY OF SAN DIEGO ) CITY OF CHULA VISTA ) I, Susan Bigelow, City Clerk of Chula Vista, California do hereby certify that the foregoing Resolution No. 2007- was duly passed, approved, and adopted by the City Council at a regular meeting of the Chula Vista City Council held on the 3rd day of April 2007. Executed this day of April, 2007. Susan Bigelow, City Clerk J :lAttomeylMichaeIShlResosIRESO-BirchROadChangeOrder-Final.doc 7--/0