HomeMy WebLinkAbout1994/09/20 Item 11
COUNCIL AGENDA STATEMENT
ITEM TITLE:
Item J I
Meeting Date 09/20/94
Resolution ) 7~VrAuthorizing a Change Order with Granite Construction For
Installation of Storm Drain Facilities in Otay Valley Road in Conjunction with
Development of the Girard Financial Parcel on Otay Valley Road and appropriating
funds therefore.
SUBMITIED BY: Director of Public Works ~
REVIEWED BY: City Manager ~tl~0 (4/5ths Vote: Yes..x. NO-J
Girard Financial owns a 3.3 acre site on Otay Valley Road. The road is currently being widened by
Granite Construction Company under Assessment District 90-2. In order to develop the Girard property,
certain storm drain improvements within the road right-of-way are required. It is in the best interest of
all parties to have Granite Construction install the drainage improvements as part of their work on Otay
Valley Road. Girard will reimburse the City the full cost of this work (letter agreement attached).
RECOMMENDATION: That the City Council approve the resolution authorizing a change order with
Granite Construction for installation of storm drain facilities in Otay Valley Road and appropriating funds
from the developer's deposit.
BOARD/COMMISSION RECOMMENDATION: Not applicable.
DISCUSSION:
Girard Financial Corporation owns a site at the northwest comer of Otay Valley Road and Maxwell Road
comprising 3.3 acres. Approximately 1.4 acres was recently sold to Sweets Specialty, a chocolate
manufacturer currently completing an industrial building on the site. Although there has been interest in
the remaining two parcels comprising .9 acres each, no development is imminent.
Girard is required to provide storm drain improvements adjacent to the site within the right-of-way of Otay
Valley Road which is estimated to cost $64,475. The work cannot be completed at this time because of
conflicts with an existing gas main which will be relocated as part of the Otay Valley Road Improvements.
Granite is willing to undertake this work in conjunction with the Otay Valley Road work in order to avoid
having another contractor working concurrently in the roadway and to allow better control of the work
within the right-of-way. Girard will deposit 110% of the estimated cost for the work with the City so that
there will be no additional expense for the assessment district (see attached letter). It is anticipated that
the contractor will be working in the vicinity of the Girard site in approximately three months.
Staff recommends that the City Council authorize the Director of Public Works to approve the requested
change order conditioned upon receipt of funds from Girard Financial.
FISCAL IMPACT: The storm drain work is estimated to cost $64,475. Additional cost for inspection
and testing is estimated at $2,500. Girard Financial will deposit 110% of the funds required for this work
with the City before the contractor is authorized to proceed.
Attachments: _~
Exhibit 1 - Letter from Girard It SC~\...-
~-'q-""-~ ~O II" / /;/-2.
filo_AO-Oro
~^
"i~il L.I .1\)11" \ I:LI~l' Drl',._
\l: ii" .~I H I
),'11 1 J,<).:" , (,\ ')212..'
1,[')II"',7'>!I(j
:.;.:, i
GIRARD
FINANCIAL.
Corporation
August 3, 1994
AUG - 8
'"'" 51
",-'1 I ~
Mr. Dennis Davies, Civil Engineer
City of Chula Vista
Engineering Department
276 Fourth Avenue
Chula Vista, CA 91910
RE: GRANITE CONSTRUCTION COMPANY
INSTALLATION OF STORM DRAIN [CHANGE ORDER 4/18/94]
OTAY VALLEY ROAD, CHULA VISTA, CA
Dear Mr. Davies:
You are hereby authorized to finalize and execute a change order
with Granite Construction Company for the jn~tallation of a storm
drain in Otay Valley Road per revised plan ~heets 92~I62 to 164,
92-169, 170, 175, and 176, all dated March 2.3, 1994. It is
understood that the change order will be in the amount of
$64,475.00 with the elimination of all contingencies outlined in
the 4/18/94 change order quotation except for some pot holing and
soils testing during construction. We are agreeable to the above
contingencies, provided they collectively may not exceed $2,500.00.
To secure the above change order, Giran: Financial Corporation is
enclosing a good faith deposit of $5,000.00 payable to the City of
Chula Vista. Once the change order has been finalized under the
above terms and conditions, Girard agrees to substitute a cash
deposit for 110% of the change order and contingencies, with the
understanding that the $5,000.00 deposit and improvement Bonds
#1194570 and #119457] shall be immediately returned to Girard.
After payment for the completion of the work contained within the
above described change order, any excess remaining from the cash
deposit shall be immediately y'eturned to Girard.
I acknowledge and agree that the City shall not be responsible for
any negligence or delays in connection with Granite Construction
Company's performance of the change order work.
Thank you for your assistance in finalizing this matter.
Sincerely,
ao~nsi!- ~
President/CEO
1/. ,;.
RESOLUTION NO. /7&',/
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA AUTHORIZING A CHANGE ORDER WITH
GRANITE CONSTRUCTION FOR INSTALLATION OF STORM
DRAIN FACILITIES IN OTAY VALLEY ROAD IN
CONJUNCTION WITH DEVELOPMENT OF THE GIRARD
FINANCIAL PARCEL ON OTAY VALLEY ROAD, AND
APPROPRIATING FUNDS THEREFOR
WHEREAS, Girard Financial owns a 3.3 acre site on Otay
Valley Road, which road is currently being widened by Granite
Construction Company under Assessment District 90-2; and
WHEREAS, in order to develop the Girard property, certain
storm drain improvements within the road right-of-way are required;
and
WHEREAS , it is in the best interest of all parties to
have Granite Construction install the drainage improvements as part
of their work on Otay Valley Road; and
WHEREAS, Girard will reimburse the city the full cost of
this work as set forth in their letter agreement; ad
WHEREAS, staff recommends that the City Council authorize
the Director of Public Works to approve the requested change order
in the estimated amount of $64,475.
NOW, THEREFORE, BE IT RESOLVED the city Council of the
City of Chula vista does hereby authorize a Change Order with
Granite Construction for installation of storm drain facilities in
otay Valley Road in conjunction with development of the Girard
Financial parcel on otay Valley Road.
BE IT FURTHER RESOLVED that the Director of Public Works
is hereby authorized to execute said Change Order on behalf of the
city of Chula vista.
BE IT FURTHER RESOLVED the the amount of $64,475 is
hereby appropriated from the Developers Depo 't into P Account
ST123.
c:\rs\granite.co
Bruce M.
Attorney
city
Presented by
John P. Lippitt, Director of
Public Works
1/.3