HomeMy WebLinkAbout2007/03/27 Item 2
CITY COUNCIL
AGENDA STATEMENT
~~ CITY OF
,~ CHULA VISTA
3/27/07, Item~
ITEM TITLE:
RESOLUTION WANING THE FORMAL CONSULTANT
SELECTION PROCESS AND APPROVING THE FIRST
AMENDMENT TO THE AGREEMENT WITH ALLEGIS
DEVELOPMENT SERVICES, INC. TO PROVIDE CONTINUED
OWNER'S REPRESENTATION SERVICES DURING THE
DESIGN AND CONSTRUCTION OF THE CNIC CENTER AND
RELATED IMPROVEMENTS
DIRECTOR OF GErL SERVICES(j~'
CITY MANAGER /1
.
SUBMITTED BY:
REVIEWED BY:
4/5THS VOTE: YES D NO ~
BACKGROUND
On February 18, 2003, City Council approved by Resolution 2003-068, waiving the formal
consultant selection process and an agreement with Allegis Development Services, Inc. to
provide Owners' Representation services during the design and construction of the Civic Center
and related improvements. The time frame has been extended to August 6, 2008 for completion
of the Civic Center Project as previously approved by Council on August 3, 2004.
RECOMMENDATION
That Council waive the formal consultant selection process and approve the first amendment
with Allegis Development Services, Inc. to provide continued Owner's Representation services
during the design and construction of the Civic Center and related improvements.
BOARDS/COMMISSION RECOMMENDATION
Not Applicable
DISCUSSION
On February 18, 2003, City Council approved by Resolution 2003-068, waiving the formal
consultant selection process and an agreement with Allegis Development Services, Inc. (ADS) to
provide Owner's Representation services during the design and construction of the Civic Center
Project and related improvements.
ADS' agreement with the City was to provide professional services through April 20, 2007 or
City's acceptance of the project, whichever occurred earlier, which was sufficient based on the
completion dates at that time. However, the Substantial and Final completion dates of the
2-1
3/27/07, Item 2
Page 2 of2
project had been extended and were approved by Council on August 3, 2004. Extended dates for
the completion of the final phase of the project are as follows: Substantial Completion, May 7,
2008 and Final Completion, August 6, 2008.
In reference to Chula Vista Municipal Code 2.56.110 (C), the Director of General Services has
determined the use of a Consultant is most effective. ADS is competent and capable of
performing required services as demonstrated in these past years regarding oversight and
management of the New Police Facility project and in their current involvement with the Civic
Center Renovation project. The time required and disruption to the project, which would occur
by selecting a new Owners Representation, would not be beneficial to the project or the City at
this time because of the expertise ADS possesses regarding the project. It is recommended that
the City Council waive the formal consultant selection process and continue Owners
Representation services with ADS consistent with the change in completion dates for the Civic
Center Project.
DECISION MAKER CONFLICT
Staff has reviewed the property holdings of the City Council and has found a conflict exists, in
that Councilmember Jerry Rindone has holdings within 500 feet of the boundaries of the
property which is the subject of this action.
FISCAL IMPACT
There are no fiscal impacts to the budget. Compensation to Allegis Development Services, Inc.
will be paid from existing funds in the approved Civic Center project budget.
ATTACHMENTS
First Amendment to Agreement
Prepared by: Merce LeClair, Sr. Mgt. Analyst, General Services
J:\General Services\GS Administration\Council Agenda\Civic Center\Allegis Amendment 030807.doc
2-2
THE ATTACHED AGREEMENT HAS BEEN REVIEWED
AND APPROVED AS TO FORM BY THE CITY
ATTORNEY'S OFFICE AND WILL BE
FORMALLY SIGNED UPON APPROVAL BY
THE CITY COUNCIL
A(~~ jJ~ ./-Ju-p
,...--/ Ann Mob e
City Attorney
Dated: .3 /f}.,~ )07
,
First Amendment to
the Agreement between the City of Chula Vista
and Allegis Development Services, Inc.
2-3
First Amendment
To the Agreement between
City ofChula Vista
and
Allegis Development Services, Inc.
For Project Management/City's Representative Services
This tirst amendment is made and entered into this 27th day of March 2007 by and between lhe
City ofClm!a Vista (herein "City"), a municipal corporation, and Allegis Development Services,
[nc, (herein "Consultant"). City and Consultant are sometimes hereinafter referred to as Parties
("Parties")
RECITALS
WHEREAS, the City Council approved by Resolution 2003-068, an agreement ("Original
Agreement") with Allegis Development Services. Inc. to provide Owners' Representation
services during the design and construction ofthe Civic Center and related improvements; and
WHEREAS. Consultant has been actively engaged in the oversight and project management of
the Civic Center project since the date of the Original Agreement; and
WHEREAS, said Original Agreement with the City was to provide professional services through
April 20. 2007 or City's acceptance of the building, whichever occurs earlier: and
WHEREAS. the Substantial and Final completion dates of the project had been extended and
approved by Council on August 3, 2004; and
WHEREAS, StatT is recommending that the City waive the Consultant Selection process based
upon the satisfactory performance to date and the need to have these services in place without
disruption and continue Owners Representation services with Consultant consistent with the
change in completion dates for the tinal phase of the Civic Center.
NOW, THEREFORE, in consideration of the recitals and the mutual obligation of the Parties set
torth herein, the City and Consultant agree as follows:
I. Section 8 D of Original Agreement is hereby amended to read as follows:
D. Date for completion of all services: August 6, 2008 or City's acceptance of the
building, whichever occllrs earlier,
ry All other terms and conditions of the Original Agreement shall remain in full larce
and effect.
2-4
First Amendment
To the Agreement between
City orChula Vista
and
Allegis Development Services, Inc,
For Project Management/City's Representative Services
CITY OF CHULA VISTA
Cheryl Cox, Mayor
ATTEST:
Susan Bigelow, City Clerk
Appl"Oved as to [onTI by
Allegis Development Services, Inc.
~Jk~~
Ann Moore, City Attorney
2-5
RESOLUTION NO. 2007-
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA WAIVING THE FORMAL CONSULTANT
SELECTION PROCESS AND APPROVING THE FIRST
AMENDMENT TO THE AGREEMENT WITH ALLEGIS
DEVELOPMENT SERVICES, INC. TO PROVIDE
CONTINUED OWNER'S REPRESENTATION SERVICES
DURING THE DESIGN AND CONSTRUCTION OF THE
CIVIC CENTER AND RELATED IMPROVEMENTS
WHEREAS, on February 18, 2003, City Council approved by Resolution 2003-068,
waiving the formal consultant selection process and an agreement with Allegis Development
Services, Inc. to provide Owners' Representation services during the design and construction of
the Civic Center and related improvements; and
WHEREAS, the time frame has been extended to August 6, 2008 for completion of the
Civic Center Project as previously approved by Council on August 3, 2004; and
WHEREAS, the time required and disruption to the project, which would occur by
selecting a new Owners Representation, would not be beneficial to the project or the City at this
time; and
WHEREAS, although there are overlapping phase expenditures, the project as a whole is
within budget; and
WHEREAS, pursuant to Chula Vista Municipal Code 2.56.l10(c), the Director of
General Services has determined the use of a consultant is most effective; and
WHEREAS, ADS has successfully performed such services for the City in the past; and
WHEREAS ADS has demonstrated they are competent and qualified to continue
providing these services; and
WHEREAS, selecting a different consultant to act as the City's owner representative
would not be in the City's best interest because of the expertise ADS possesses regarding the
project, potential delays while selecting a different consultant, and the change would be
disruptive to the overall management of the project; and
WHEREAS, it is recommended that the City Council waive the formal consultant
selection process and continue Owners Representation services with ADS consistent with the
change in completion dates for the Civic Center Project; and
WHEREAS, extended dates for the completion of the final phase of the project are as
follows: Substantial Completion, May 7, 2008 and Final Completion, August 6, 2008; and
2-6
WHEREAS, there are no fiscal impacts to the budget since compensation to Allegis
Development Services, Inc. will be paid from existing funds in the approved Civic Center project
budget.
NOW, THEREFORE, BE IT RESOLVED the City Council of the City of Chula Vista
does hereby waiving the formal consultant selection process and approving the first amendment
to the agreement with Allegis Development Services, Inc. to provide continued owner's
representation services during the design and construction of the civic center and related
improvements consistent with the completion dates for the project.
Presented by
Approved as to form by
~;;trJf#A 4d
Ann oore C
City Attorney
Jack Griffin
Director of General Services