HomeMy WebLinkAbout2006/09/19 Item 11
COUNCIL AGENDA STATEMENT
Item
Meeting Date
II
09/19/06
ITEM TITLE:
Resolution Accepting Bids and Awarding a Contract for the Traffic
Signal Installation at the Intersection of Greens gate Drive and North Greensview
Drive (Tf-320) to Southwest Traffic Signal Services Incorporated and
Appropriating Funds from the available balance of the Traffic Signal Fund
SUBMITTED BY: Acting Director ofEngineering~Q.-f!'~
~
REVIEWED BY: Interim City Manager JI (4/5ths Vote: Yes..K. No->
The traffic signal installation at the subject intersection was approved and budgeted as part of the FY
05/06 Capital Improvement Program (ClP). Tonight, the City Council will consider authorizing
additional appropriation of traffic signal funds in the amount of$1 0,000 to the TF -320 project from the
cost savings of various Traffic ClP projects completed and closed inFY 06/07. The scope of the project
includes the installation of a fully actuated traffic signal system and other necessary work needed to
complete the project.
RECOMMENDATION: That Council adopt the resolution and authorize the appropriation of
additional $10,000 to TF-320 project from the available balance of the Traffic Signal funds.
BOARDS/COMMISSIONS: Not applicable.
DISCUSSION:
This traffic signal installation project was originally required by the EastIake Greens SPA approval.
The project is funded by the Traffic Signal Fund and was programmed for Fiscal Year 2006. The
project will install a traffic signal system at the intersection of Greens gate Drive and North Greensview
Drive.
The intersection at Greensgate Drive and North Greensview Drive is a three-way intersection situated in
the eastern part ofChula Vista. This intersection is adjacent to the EastIake Golf Course (located on the
eastside of North Greensview) and Chula Vista Community Park (located along Eastlake Parkway, the
next intersection to the west). This intersection is also within close proximity to Eastlake High School
and Library, EastIake Village Shopping Center, and Olympic View Elementary School. The scope of
work is summarized in Attachment I.
O~l~1l:.__1,~.l..~90~_~.i.~~w':::!:..E.~ei ":~.9 fr'?~~ fog~.~I}.$..~.?!!!!~c~or~:_._._.___.....___.._,__...._._,
i Contractor I Bid Amount 1.
~ .-
i 1. SouthwestTraffic Signal Services (EI Cajon, CA) i $114,100 !
...~.."---'----:---"-"-"------"-'-'-"-'--"'----'-----"-..-...-'------------..--.-.-----.--------...~..; .-.-.------.--.--------------..--.--.-----e
i 2. Hl\1S Construction, Incorporated (San Marcos, CA), $114,417 ,
13. T & M Electric dba Perry Electric (Santee, CA) . . ,--------- $118,350 ------;
...r- -.-.-------.----.-----.-.---.- .---------------.-----------.-.-----.-- -.---- -'.....-.-.-...---.-..-..-------.--.--..-----------...----II
14- Lekos Electric, Incorporated (EI Cajon, CA) , $124,500 I
".-----,.--------------------~l
I 5 - Select Electric (Spring Valley, CA) r $126,800 I
.iu''''''''="''"'''''"''.,~,.,.'''''"''''''_'=~um..''''~~..........._=_''''''""'',.....~'''''''.._"..._''''''''''...''''""..........'"=.....''''.."m''''''''',..,.'''''"''.~...''u"''''_m"'''...'''.'''"''=~,_"''''''''',u'''=....-.-..=,==,~"=.",.~.....".-~..,=.."",...~.......=.,,"'''''..
11-1
Page 2, Item
Meeting Date
II
09/19/06
The low bid, submitted by Southwest Traffic Signal Services is above the engineer's estimate of
$110,850 by $3,250 (2.8 %). Staff conducted an interview with the contractor's references and has
received favorable comments indicating satisfactory performance on traffic signal and street light
projects.
In order to comply with the TF-320 project specification that states, "...The award, if made, will be
made within (60) sixty days after the opening of the bids," staff has mailed a letter to \he Contractor
requesting to extend and secure the bid proposal item costs from 60 days to 90 days. Since the bid
opening on July 12, 2006, it would be (68) sixty-eight days before the award on September 19, 2006.
The Contractor has responded to the request and agreed to extend and secure the bid proposal.
Disclosure Statement: The Contractor's Disclosure Statement is provided as Attachment 2.
Environmental Status: The Environmental Review Coordinator has reviewed the proposed activity
for compliance with the California Environmental Quality Act (CEQA) and has determined that the
activity is not a "Project" as defined under Section 15378 of the State CEQA Guidelines because it
will not result in a physical change to the environment; therefore, pursuant to Section 15060(c)(3) of
the State CEQA Guidelines the activity is not subject to CEQA. Thus, no environmental review is
necessary.
DECISION MAKER CONFLICTS: Staffhas reviewed the property holdings ofthe City Council and
has found no property holdings within 500 feet of the intersection at Greensgate Drive and North
Greensview Drive, which is the subject ofthis action.
FISCAL IMPACT:
FUNDS REQUIRED FOR CONSTRUCTION
Contract Amount (Southwest Traffic Signal Services, EI Cajon) , 114,100 i
A. I $
B. 10% Contingencies $ 11,410
C. Total Expenses as of June 30, 2006 (Staff and Advertising Costs) $ 17,750
,
D. Construction and Admin Staff Costs $ 16,740 ~
-
TOT~~D~~~D F~~~_'!'~ECTION $ 160,000.00 ij
......-..""""""'"
-'""1
I
i $ 150,000 il
~ 10,000 ~
_J $ 160,000.00 I
'--"'
i FUNDS AVAILABLE FOR CONSTRUCTION
~ A. Traffic Signal Fund
I B. Additional Appropriation - Traffic Signal Fund
l TOT ~_~1'lDS AVAILABLE FOR CONSTRUCTION
Staff time estimated for the design ofTF -320 project has increased as staffaddressed issues related to
the bid submittals. From six Traffic CIP projects completed and closed in FY06/07, staffhas returned
approximately $110,005 back into the traffic signal fund. Therefore, we request that the City Council
authorize staffto appropriate an additional $10,000 from the available balance of the traffic signal fund
11-2
Page 3, Item
Meeting Date
II
09/19/06
to TF-320 project required for the completion of the project so that the existing 10% construction
contingency amount of $11 ,41 0 remain available during the construction phase.
There is no impact to the General Fund for construction. Construction will be entirely funded from
Traffic Signal funds. Upon completion of construction, normal annual signal energy and maintenance
costs are estimated to be $4,500 for the intersection.
Attachments:
Attachment I: Scope of Work Summary for projects TF-320
Attachment 2: Contractor's Disclosure Statement
Attachment 3: Capital Improvements Program Detail
J: IEngineerlA GENDA ICAS2006\09-19-06\TF320Al13.mlcm.doc
11-3
Attachment 1
Scope of Work Summary
Proiects TF-320,
Furnish and Install:
.
Mast Arms
New Traffic Signal Standards on New Foundations
Signal Light Emitting Diode (LED) Indications
Pedestrian Push Button
Internally Dluminated Street Name Signs (IISNS)
Meter Pedestal, Uninterruptible Power Supply (UPS) Unit
Interconnect Cable
Signal Controller and Cabinet
Emergency Vehicle Pre-Emption (EVPE) System
Wiring
Conduits
Pull Boxes
Video Detection System
Signs
.
.
.
.
.
.
.
.
.
.
.
.
.
Other Work:
. Traffic Control
. Removal and Disposal, Protection and Restoration of Existing Improvements
. Sandblasting of Existing Striping and Resurfacing Pavement
. 18" Gravity Retaining Wall for the Controller Cabinet/Meter Pedestal Slope Protection
. Construction of all Appurtenances and other Miscellaneous W ork Necessary to make the
Traffic Signal Systems Complete and Operational.
11-4
ATTACHMENT :)..
CITY OF CHULA VISTA DISCLOSURE STATEMENT
Pursuant to Council Policy 101-01, prior to any action upon matters that will require discretionary action
by the Council, Planning Commission and all other official bodies of the City, a statement of disclosure of
certain ownership or financial interests, payments, or campaign contributions for a City of Chula Vista
election must be filed. The following information must be disclosed:
1. List the names of all persons having a financial interest in the property that is the subject of the
application or the contract, e.g., owner, applicant, contractor, subcontractor, material supplier.
(}.Jov-e....
2. If any person* identified pursuant to (I) above is a corporation or partnership, list the names of all
individuals with a $2000 investment in the business (corporation/partnership) entity.
3. If any person * identified pursuant to (1) above is a non-profit organization or trust, list the names
of any person serving as director of the non-profit organization or as trustee or beneficiary Or
trustor of the trust.
4. Please identifY every person, including any agents, employees, consultants, or independent
contractors you have assigned to represent you before the City in this matter.
9v~
5.
Has any person* associated with this contract had any financial dealings with an official**:;!fl'e
City ofChula Vista as it relates to this contract within the past 12 months? Yes_ No_
IICitywide2000lhomelEngineer\TRAFFICIACAD
320Specs.doc
15
DwgslSTANDARD DWGS
(ACAD)ICIP PROJECTSITF320ITF_
11-5
If Yes, briefly desenoe the nature of the financial interest the official"" may have in this contract.
6. Have you made a contribution of more than $250 within the past twelve (12) months to a current
member of the Chula Vista City Council? No v'yes _ If yes, which Council member?
7. Have you provided more than $340 (or an item of equivalent value) to an official** of the City
of Chula Vista in the past twelve (12) months? (This includes being a source of income, money to
retire a legal debt, gift, loan, etc.) Yes _ No ....-
IfY 05, which official"* and what was the nature of item provided?
Date: "1 -I" - OS-
(h~
Signature of Contractor/Applicant
1I"1>12-~o-L- 13 .Q.~
Print or type name of Contractor/Applicant
*
Person is defined as: any individual, firm, co-partnership, joint venture, association, social
club, fraternal organization, corporation, estate, trust, receiver, syndicate, aily other county,
city, municipality, district, or other political subdivision, -or any other group or combination
acting as a unit.
**
Official includes, but is not limited to: Mayor, Council member, Planning Commissioner,
Member of a board, commission, or committee of the City, employee, or staff members.
16
IICitywide2000lhomelEngineerlTRAFFIClACAD DwgslST ANDARD DWGS (ACAD)ICIP PROJECTSITF320ITF-
320Specs.doc
11-6
ATTACHMENT 3
CITY OF CHUlA VISTA
CAPITAL IMPROVEMENTS PROGRAM DETAIL
CIPNO: TFJ20 NEW CIP NO 24563200 INITIALLY SCHEDULED: 07/0112004
TITLE: Traffic Signal Installation at Greensgate Drive and Greensview DEPARTMENT: Engineering I Traffic
Drive
COMMUNITY PLAN AREA: Eastern PROJECT MANAGER: Lombardo DeTrinidad
PROJECT TOTAL
COST ESTIMATES: APPROPRIATIONS FY 2005~O6 FY 2006-01 FY 2007-00 FY 200D-09 FY 2009-10
TOTAL THRU 2004-05
1. Planning I Env. Review $0 SO SO SO SO SO SO
2. Land Acquisition $0 . SO $0 SO SO SO SO
3. Design S20,000 $0 S20 000 $0 $0 SO SO
4. ConslrucUon S130,000 SO S130,000 SO SO SO $0
TOTALS $150,000 SO SI50,OOO $0 $0 $0 $0
FINANCING SOURCES:
SIGNAL I $ 1 50,000 SO I S150,OOO SO I $0 I SO I SO
TOTALS: J S150,000 I $0 I -.L $150,000 SO -.l SO I SO SO
~
~
I
-..J
DESCRIPTION: Installation oCa fully actuated traffic signal system.
JUSTIFICATION: Intersection is within close proximity to the EastLake Golf Course, Olympic View Elementary School,
EastLake High School. a park and a shopping center. This intersection is ranked No. J J on the Traffic Signal
Priority List.
SCHEDULING: Estimated design completion in FY 05/06 wHh construcilon to begin shortly thereafter.
STATUS: In design.
BUDGET EFFECT: Annual operational and maintenance costs are estimated to be S4,500.
I,..
~
N
290
RESOLUTION NO. 2006-
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA ACCEPTING BIDS AND A WARDING A
CONTRACT FOR THE TRAFFIC SIGNAL INSTALLATION
AT THE INTERSECTION OF GREENSGA TE DRIVE AND
NORTH GREENS VIEW DRIVE (TF-320) TO SOUTHWEST
TRAFFIC SIGNAL SERVICES INCORPORATED AND
APPROPRIATING FUNDS FROM THE AVAILABLE
BALANCE OF THE TRAFFIC SIGNAL FUND
WHEREAS, the traffic signal installation at the intersection of Greensgate Drive and
North Greensview Drive was approved and budgeted as part of the FY 05/06 Capital
Improvement Program [CIP] and was approved for funding from the Traffic Signal Fund in
Fiscal Year 2006; and
WHEREAS, the City of Chula Vista [City] issued a Request for Proposals for the traffic
signal installation and five bids were received; and
WHEREAS, the low bid, submitted by Southwest Traffic Signal Services [Southwest], is
above the engineer's estimate of$110,850 by $3,250 (2.8 %); and
WHEREAS, due to staff addressing issues related to the bid submittals, there is an
increase of staff costs; and
WHEREAS, there are sufficient funds available in the Traffic Signal Fund; and
WHEREAS, staff requests that $10,000 of these savings be appropriated to fund the
increase in construction costs and staff costs; and .
WHEREAS, the Environmental Review Coordinator has reviewed the proposed project
for compliance with the California Environmental Quality Act and has determined that the
activity is not a "Project" as defined under Section 15378 of the State CEQA Guidelines because
it will not result in a physical change to the environment; therefore, pursuant to Section
15060(c)(3) of the State CEQA Guidelines the activity is not subject to CEQA. Thus, no
environmental review is necessary.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City ofChula Vista
that it accepts bids and awards the contract in the amount of $114,100 for the Traffic Signal
Installation (TF-320) project to Southwest Traffic Signal Services, Incorporated.
11-8
Resolution No. 2006-
Page 2
BE IT FURTHER RESOLVED by the City Council of the City of Chula Vista that it
appropriates $10,000 to Project TF-320 from the available balance of the Traffic Signal Fund.
Presented by
Approved as to form by
Leah Browder
Acting Director of Engineering
,,-!j3~j t?JA~
Ann Moore
City Attorney
J:\Attorney\ELlSA \RESQS\Reso TF320 Traffic Signal 09-19~06.doc
11-9