HomeMy WebLinkAboutRCC AGENDA PK 1990/04/09negative declaration
PROJECT NAME: Rancho Del Rey Auto Park
PROJECT LOCATION:
PROJECT APPLICANT
Rancho Del Rey, north side of East "H" Street on Paseo Del
Rey and Tierra Del Rey in the Rancho Del Rey Employment Park
Assessor Parcel Numbers
02.
City of Chula Vista
CASE N0: IS-90-33
A. Project Setting
640-292-04 to 16; 640-293-01 to
DATE: Plarch 21, 1990
The proposed Auto Park would be located on approximately 40.00 acres of
the previously approved Employment Park in the Rancho Del Rey SPA I Plan
area. The Rancho Del Rey project is located north of East "H" Street and
east of Interstate 805 in the eastern territory of the City (see Exhibit
1).
The Rancho Del Rey Employment Park was originally approved for a mixture
of office, commercial and light industrial uses. The Rancho Del Rey
Employment Park site has been previously graded, and street improvements
have already been implemented. No building construction has begun yet for
the approved Employment Park uses, although minor grading would be
required to reconfigure the existing pads to accommodate the proposed Auto
Park.
The proposed Auto Park would be located in the southwestern portion of the
Rancho Del Rey Plan Area (see Exhibit 2). Due to previous grading, there
are no sensitive plant or animal species presently utilizing the Auto Park
site, however, open space areas immediately abut the site to the north.
These open space areas provide mitigation of biological impacts associated
with Rice Canyon, which were previously analyzed in the E1 Rancho Del Rey
SPA I EIR (Michael Brandman and Associates, 1985).
The previous Environmental Impact Report for the Rancho Del Rey Project
included analyses of Biology, Land Use, Traffic/Circulation Noise, Fiscal
Impacts, Cultural/Paleontological Resources, Geology/Soils,
Hydrology/Water Quality, Landform/Aesthetics Air Quality,
Parks/Recreation, Open Space, Public Utilities, Energy and Socioeconomic
Impacts (E1 Rancho Del Rey Specific Plan Amendment Final Environmental
Impact Report 1985).
city of Chula vista planning department
environmental review section
wr,
._._~.
clTV of
CHUTA VISTA
-2-
A Mitigated Negative Declaration has been prepared for the proposed Auto
Park project to provide a mechanism by which potentially significant
environmental effects identified in the Initial Study are reduced and
adequate mitigation is implemented. The Mitigation Monitoring Program
required for the proposed Auto Park project includes specific mitigation
measures to reduce potentially significant environmental impacts to a
level of less than significant. The Mitigation Monitoring Program is
included as Addendum "A" of this Mitigated Negative Declaration.
B. Project Description
The proposed Rancho Del Rey Auto Park would consist of approximately 40
acres of the 84-acre Employment Park (see Exhibit 3). The Auto Park would
be designated for retail automobile sales and service by new car dealers
with a limited amount of used car sales. The types of facilities which
would be allowed in the Auto Park include new and used automobile and/or
truck sales, automobile service and repair, automobile parts and
accessories, retail and wholesale sales, and automobile washing and
fueling for dealer use.
Also included in the project proposal, but not subject to environmental
review, is the proposed name modification of that portion of East "H"
Street from I-805 to State Route 125 as "East H Street/Auto Center
Drive". The internal circulation routes "Paseo Del Rey" and "Tierra Del
Rey" are also proposed for a name modification to "Auto Center Circle".
The proposed discretionary actions include amendments to the Rancho Del
Rey SPA I Planned Community District Regulations and Employment Park
Design Guidelines to create "Auto Center District" regulations. The
creation of an Auto Center District would require the adjustment of land
use regulations on the balance of the Employment Park site and the
implementation of development agreements for Rancho Del Rey SPA II and SPA
III development proposals. Also proposed is the vacation of two internal
circulation loops in the Employment Park, Lazo Court and Avila Way.
The 40-acres of proposed Auto Park uses would replace a corresponding
amount of originally approved commercial and industrial uses in the Rancho
Del Rey Employment Park. This will require that commercial and industrial
land use designations on the remainder of the Employment Park site be
reconfigured and adjusted accordingly. Although not all of the tenants for
the Auto Park are known at this time, ultimately the Park could consist of
approximately 10 to 11 different automobile dealerships.
Surrounding land uses include the Rancho Del Rey Employment Park to the
east and west, the Rancho Del Rey Open Space District and residential uses
to the north, and existing residential uses to the south across "H"
Street. The proposed Auto Park is physically separated from existing
residential uses on the south by H Street and by the southern leg of Rice
Canyon. Existing residential uses to the south are approximately 1,000
feet away from the proposed Auto Park site.
-3-
C. Compatibility with Zoning and Plans
The proposed project involves an amendment to the Rancho Del Rey SPA I
Planned Community District Regulations and Employment Park Design
Guidelines, as well as development agreements for the Rancho Del Rey SPA
II and SPA III projects. The proposal would change the land-use
designations within the Employment Park to allow an "Auto Park" category.
The Auto Park would be subject to special regulations and design
guidelines as an "Auto Center District", as well as the regulations
established for the Employment Park. With compliance to the regulations
set forth for these proposed discretionary actions, the Auto Park would
become compatible with the "EP" (Employment Park) zone for the Rancho Del
Rey SPA I Plan and with the Land Use Element of the General Plan.
Rancho Del Rey SPA I Planned Community District Regulations establish
specific design criteria accompanied by a written text outlining
operational standards for the entire Employment Park. These regulations
would be amended to provide specific operational standards for the
proposed Auto Park to ensure its compatibility with the underlying "EP
(Employment Park) zone and land use designations. The Auto Park signage,
lighting, and day-to-day operations would be required to be compatible
with the existing Covenants, Conditions, and Restrictions (CC&Rs) for the
Employment Park to ensure land use compatibility.
D. Compliance with the Threshold/Standards Poli
1. Fire/EMS
The Thresholds/Standards Policy requires
must be able to respond to calls within
the cases and within 5 minutes or less in
of Chula Vista has indicated that this
met, since the nearest fire station is
associated with a 7 minute response time.
2. Police
that fire and medical units
7 minutes or less in 95% of
75% of the cases. The City
threshold standard will be
4 miles away and would be
The Thresholds/Standards Policy requires that police units must
respond to Priority 1 calls within 7 minutes or less and maintain an
average response time to all Priority 1 calls of 4.5 minutes or
less. Police units must respond to Priority 2 calls within 7 minutes
or less and maintain an average response time to all Priority 2 calls
of 7 minutes or less. The City of Chula Vista Police Department has
indicated that this threshold standards policy would be met.
-4-
3.
5.
Traffic
The Thresholds/Standard Policy requires that all intersections must
operate at a Level of Service (LOS) "C" or better, with the exception
that Level of Service (LOS) "D" may occur during the peak hours of
the day at signalized intersections Intersections west of I-805 are
not to operate a LOS below their 1987 LOS. No intersection may reach
LOS "F" during the average weekday peak hour. Intersections of
arterials with freeway ramps are exempted from this policy. The City
Traffic Engineer has indicated that this Threshold Standard Policy
would be met through implementation of the City's Transportation
Phasing Plan (TPP). Traffic impacts are discussed in detail in
Section E of this document.
Parks/Recreation
The Thresholds/Standard Policy
acres/1,000 population. This
residential projects, therefore,
this standard.
for Parks and Recreation is 3
threshold standard applies only to
the proposed project is exempt from
Drainage
The Thresholds/Standard Policy requires that storm water flows and
volumes shall not exceed City Engineering Standards.CP] Individual
projects will provide necessary improvements consistent with the
Drainage Master Plan(s) and City Engineering Standards. The Auto
Park will be required to comply with the drainage requirements
established by the City Engineering Department.
Sewer
The Thresholds/Standard Policy requires that sews
shall not exceed City Engineering Standards.CP]
will provide necessary improvements consistent
Plan(s) and City Engineering Standards. The
required to comply with the City standards
infrastructure.
7. Water
ge flows and volumes
Individual projects
with Sewer Master
Auto Park will be
concerning sewage
The Thresholds/Standard Policy requires that adequate storage,
treatment, and transmission facilities are constructed concurrently
with planned growth and that water quality standards are not
jeopardized during growth and construction. The Auto Park will
comply with this threshold standard.
-5-
Identification of Environmental Effects
An initial study conducted by the City of Chula Vista determined that the
proposed project could have one or more significant environmental
effects. Subsequent revisions in the project design have implemented
specific mitigation measures to reduce these effects to a level of less
than significant.
The project, as revised, now avoids or mitigates the potentially
significant environmental effects previously identified, and the
preparation of an Environmental Impact Report will not be required. A
Mitigated Negative Declaration has been prepared in accordance with
Section 15070 of the State CEQA Guidelines. Specific mitigation measures
have also been set forth in the Mitigation Monitoring Program which is
attached as Addendum "A."
The following impacts have been determined to be potentially significant
and are required to be mitigated to a level of less than significant:
LAND USE, VISUAL/LIGHTING, NOISE AND TRAFFIC. A discussion of each of
these potentially significant impacts is provided.
1. Land Use
Potentially significant land use impacts are associated with the
proposed change in the previously-approved Employment Park uses from
"Employment Park Manufacturing and Office District" and "Employment
Park Commercial/Service District" to "Auto Center District." This
proposal represents a significant departure from land uses previously
approved at the employment park site.
Discretionary actions include an amendment to the Rancho Del Rey SPA
I Planned Community District Regulations and Employment Park Design
Guidelines. A development agreement will also address the proposed
land use changes. With these proposed actions, the Auto Center would
become an allowed use under the "EP" (Employment Park) zone of the
Rancho Del Rey SPA I Plan.
Land use compatibility will be ensured through implementation of the
Rancho Del Rey SPA I Planned Community District regulations and
Employment Park Design Guidelines. These regulations include
stringent design criteria for setbacks, building heights, parking,
landscaping, density, fencing, signage, performance and operation
standards for the Auto Park. Compatibility issues will also be
addressed through implementation of one or more development
agreements which will require that certain conditions be met in order
to allow the Auto Park to be constructed. Land use compatibility
will be ensured through strict compliance to the CC&Rs developed for
the Employment Park.
-6-
Auto Park land-use regulations will be implemented and enforced by
the City of Chula Vista and all officials charged with the issuance
of licenses and/or permits for the Auto Park to ensure that
potentially significant land use impacts are reduced to a level of
less than significant:
Specific project mitigation for potentially significant land use
impacts is outlined in Section F of this document, a well as in the
Mitigation Monitoring Program attached as Addendum "A."
2. VISUAL/LIGHTING
Potentially significant visual impacts are associated with the
proposed night and display lighting associated with the Auto Park.
Potentially significant visual impacts relating to lighting were
analyzed in detail in two separate lighting studies prepared by
different lighting consultants.
First, lighting guidelines were presented by Spaulding Lighting,
Inc. (December, 1989) to serve as a guide to the automotive dealers
in the selection and placement of outdoor lighting in an
environmentally sensitive manner. The Spaulding Study provided
recommendations on the type and size of lighting fixtures for
adequate lighting of the proposed use for both display areas and for
security purposes (see Addendum "B").
Second, a more detailed lighting study was conducted by Lighting
Consultants of San Diego (February, 1990). The objective of this
lighting study was to analyze potential light and glare impacts on
the surrounding environment. The visual impact of proposed lighting
of display and storage areas was analyzed more in relation to
surrounding land uses in this study (see Exhibit 4). Particular
attention was paid to potential visual impacts to adjacent,
residential land uses (see Addendum "C").
As outlined in the Lighting Consultants' Study, the primary visual
impacts anticipated from the proposed Auto Park use are brightness
and glare. The study considered the pole heights, materials,
specific fixtures, light mountings, locations and alignments
proposed. These variables were analyzed to determine the most
effective, yet environmentally sensitive, lighting available for the
proposed use.
Potentially significant visual impacts would occur from the proposed
Auto Park since outdoor auto sales typically use lighting to attract
customers. Lighting is also necessary for security reasons at auto
dealerships, thereby creating potentially significant brightness and
glare impacts to surrounding uses (see Exhibit 5).
-7-
Recommendations established in the Lighting Consultants' Study, such
as lowering the average lighting level would lower overall area
brightness and ensure visual uniformity with surrounding land uses.
Visual impacts from lighting would also be reduced through the use of
landscaped screening and shielding to soften views from adjacent land
uses.
Visual impacts are also associated with the signage required for an
Auto Park use. Due to the potential for significant, adverse visual
impacts related to signage, a project redesign was required to reduce
visual impacts by allowing only monument type ground level signs. No
pole or roof-mounted signage will be allowed at the Auto Park, and
signage will be limited in size and quantity. Additionally, the
originally proposed freeway sign at I-805 entryways was deemed to be
infeasible, thus resulting in further project modifications. No
freeway-oriented directional pole signs will be allowed for the
proposed project and all signage will be required to be internal in
nature, in order to blend in with surrounding land uses.
With implementation of specific project mitigation for visual impacts
set forth in Section F of this document, a well as in the Mitigation
Monitoring Program, visual impacts associated with light and glare
impacts and signage would be reduced to a level of less than
significant.
3. Noise
Potentially significant noise impacts are
operation of a proposed Auto Park use, with
vehicle repair and maintenance facilities.
1990) was conducted to assess the potE
conformance to the City of Chul a Vista Noise
to future, planned residential uses in the
planning area (see Addendum "D").
associated with the
its proposed auxiliary
A noise study (ERCE,
~ntial noise impacts,
Ordinance, and impacts
Ranch Del Rey SPA I
Existing conditions at the project site were analyzed and one hour
sound level measurements were taken at the northern boundary of the
project between the hours of 5:00 p.m. and 6:00 p.m. on January 22,
1990. The resultant, peak one hour sound level was 46.5 dBA Leq
(equivalent sound level).
The primary noise sources expected from the Auto Park would result
from vehicle repair and maintenance, in addition to proposed auto
sales activities and additional, cumulative traffic generated. The
primary noise source associated with vehicle repair would be the use
of pneumatic tools and the pounding of metal during repairs. These
activities could generate noise levels as high as 78 dBA from a
distance of 50 feet away.
-B-
Noise levels generated by the use of pneumatic tools occur for brief
periods of time. It can be expected that the average noise levels
generated by the repair facilities would be a maximum of 65.7 dBA 50
feet away from a 5 or 10 bay, open door facility.
Acoustical analyses were performed to project the anticipated noise
levels generated from the closest automobile dealership to the
closest planned residence in Rancho Del Rey SPA I.
Results of the noise study indicated that the maximum A-weighted Leq
(equivalent sound level) at the closest residence would not exceed 47
dBA, due to its physical separation from the site by the topography
of Rice Canyon and the distance of approximately 530 feet. Noise
impacts generated from the project would comply with the 55 dBA Leq
maximum hourly sound level standard for single-family residences in
the City of Chula Vista. Noise attenuation, or reduction is thus
provided due to the distance from surrounding residential land uses.
The use of landscaping and berming techniques will serve to reduce
noise impacts even further.
The proposed project would not be allowed to have a public address
system as indicated in the noise study, so this would not be an
impact. Due to project redesign, employees will be individually
equipped with beepers for internal communication; thereby reducing
noise impacts. All vehicle repairs and maintenance activities will
be required to be performed in fully-enclosed building areas.
The hours of operation proposed for the Auto Park are 7:00 a.m. to
10:00 p.m. The closest planned residence will be located
approximately 530 feet north of the Auto Park and will be physically
separated by one of the northern legs of Rice Canyon. Surrounding
land uses will be buffered further through the provision of
landscaped screening and the use of a noise attenuation wall or
berm. Even without the construction of an 8 ft. high noise
attenuation wall, however, noise impacts are deemed to be less than
significant.
With compliance to specific noise mitigation established in Section F
of this document, as well as in the Mitigation Monitoring Program,
potentially significant noise impacts would be reduced to a level of
less than significant.
4. Traffic/Circulation
The City Engineering Department required that potential traffic/
circulation impacts from the Auto Park be analyzed in detail in
relation to the surrounding circulation network. A traffic study was
conducted by Bankston/Pine Associates, Inc. (December, 1989) to
assess the project's potential for significant traffic impacts beyond
those previously analyzed for the Employment Park. This study was
-9-
reviewed by the City Traffic Engineer and traffic mitigation was
developed by the City Engineering Department to reduce potentially
significant traffic impacts to a level of less than significant (see
Addendum "E").
Potential Traffic Impacts
The project includes redesignation of 40.0 acres of Industrial land
in the Employment Park to Auto Park and 2.9 acres to Commercial. Of
the total 84.5 acres in the business center, 42.3 acres were
originally approved to be developed in Phase I and the remaining 42.2
acres were to be developed in Phase 7. This project moves an
additional 18.3 acres from Phase 7 to Phase 1.
Traffic generation rates of 200 Average Daily Trips (ADT) per acre
are expected from the industrial development and 400 ADT per acre
from the proposed commercial development. A traffic generation rate
of 270 Average Daily Trips (ADT) per acre was calculated for the
proposed Auto Park, based upon research conducted by the City of
Chula Vista and its traffic consultant. Similar auto park uses in
other jurisdictions were analyzed to provide a comprehensive basis
for analyses. The projected 270 ADT takes into consideration
customer test drive trips to and from the Auto Park facility.
Thus, the results of the traffic study indicated that the existing
approved Business Park will generate 18,240 ADT (6.7 acres at 400
trips/acre plus 77.8 acres at 200 trips/acre). The proposed changes
in land use associated with the Auto Park will generate 21,620 ADT
(9.6 acres at 400 trips/acre, 40.0 acres at 270 trips/acre, 34.9
acres at 200 trips/acre). This is an overall increase of 3,380 ADT.
Although this represents an increase in traffic volumes over what was
previously approved, the City Engineering Department has indicated
that anticipated street improvements in the overall circulation
system would adequately absorb this increase.
The study also indicates that the short term increase in Phase 1
traffic due to the Auto Park will be 7,000 ADT (16,860 ADT under the
proposed development as compared to the 9,860 ADT originally
approved) for the Employment Park. Since 72% of the project traffic
will be distributed no East "H" Street through the Hidden Vista
intersection, there will be an increase in traffic volumes of 11,693
ADT over present volumes. Thus, project traffic plus existing
traffic will result in a total volume of 43,443 ADT. When
considering traffic generated by other developments, traffic
mitigation, including implementation of the East Chula Vista
Transportation Phasing Plan (TPP) will reduce traffic impacts to a
level of less than significant.
-lo-
Primary access to the project site is from East "H" Street, a portion
of which is proposed for a name modification to East "H" Street/"Auto
Center Drive". The Auto Park would be accessed from East "H" Street
by Paseo Del Rey and Tierra Del Rey, which are both previously
improved streets in the Employment Park. These internal circulation
networks are proposed to be renamed to "Auto Center Circle".
Particular attention was paid in the traffic analyses to potential,
adverse impacts to traffic threshold levels on East "H" Street, prior
to the construction of a four-lane facility in the State Route 125
corridor between Telegraph Canyon Road and the South Bay Freeway (SR
54). The Auto Park will not, at the point when the Eastern Territory
is built out inclusive of a completed circulation system, result in
an overloaded condition on East "H" Street.
The critical location in order to determine whether or not East "H"
Street can handle the short term increase prior to the construction
of SR 125 is the intersection of East "H" Street and Hidden Vista
Drive. According to the City Engineering Department, the current ADT
along this critical segment of East "H" Street is 31,750 ADT. This
value represents a "C" Level of Service (LOS).
After project completion, the anticipated ADT along this critical
segment will be 43,443, (existing volumes plus project traffic) with
a Level of Service (LOS) "C", thereby complying with the City's
Threshold Standards for traffic. When considering the cumulative
impacts of surrounding development prior to construction of SR 125,
it is expected that the total traffic volume on East "H" Street at
the critical intersection may exceed the existing 55,000 ADT capacity
of the roadway, as defined by the City's Threshold Standards.
Critical Intersection Analyses
The Bankston/Pine Associates, Inc. traffic study indicates that on a
project specific basis, it can be expected that the project would
create significant traffic impacts to the critical intersection
segment of Hidden Vista Drive. Engineering Department traffic counts
indicate that the current A.M. peak hour traffic flow at this
location is westbound and, in the P.M., is eastbound.
Due to the proposed location east of I-805, the peak hour traffic
flows from the Auto Park on East "H" Street immediately east of
Hidden Vista Drive will be in the opposite direction of the current
peak hour flows. This, in itself, somewhat mitigates the effect of
the increased traffic generation. It has been estimated that the
maximum amount of traffic that could be accommodated at this location
was 55,000 ADT under the Threshold Standards.
-11-
The proposed mitigation of the widening of East "H" Street at the
critical intersection increases the capacity of East "H" Street to
67,000 ADT, which is sufficient to accommodate existing volumes,
project traffic, plus other traffic prior to SR 125. Due to the
potential for significant traffic impacts, mitigation will require
compliance with the East Chula Vista Transportation Phasing Plan
(TPP) and Threshold/Standards Policy to reduce potentially
significant traffic impacts to a level of non-significance.
Additional project specific-traffic mitigation is set forth in
Section "F" of this document, as well as in the Mitigation Monitoring
Program. Traffic volumes on East "H" Street will be monitored until
an ADT of 51,000 is reached. At which time, further analysis will be
performed to determine the scheduling and need for widening. As
indicated above, when SR 125 is completed, this widening may not be
necessary. Therefore, it may be possible that the Commission and
Council may choose to allow a limited time period of traffic on East
"H" Street which exceeds the Threshold Standards. This will be
required project mitigation for potentially significant traffic
impacts.
F. Mitigation necessary to avoid significant effects
Specific project mitigation measures and project redesign have been
required to reduce potentially significant environmental impacts
identified in the initial study for this project to a level of less than
significant.
Mitigation measures have been incorporated into the project design and
have been made conditions of project approval, as well as requirements of
the attached Mitigation Monitoring Program. Mitigation measures set forth
in this document shall be ensured through the implementation of
development agreements for Rancho Del Rey SPA II and III and enforced as a
condition of project approval for the proposed discretionary actions.
Land Use Mitigation
The following land use mitigation will be required for the proposed
project, in order to reduce potentially significant land use impacts to a
level of less than significant. These mitigation measures will be
enforced as a condition of project approval:
1. Implementation and monitoring of the Rancho Del Rey SPA I Planned
Community District regulations, Employment Park Design Guidelines,
and development agreement conditions will be enforced to guide the
use of land, building structures, size of yards abutting buildings
and structures, height and bulk of buildings, standards of
performance and day-to-day operations for the Auto Park.
-12-
2. The City Council, City Attorney, City Manager, Director of Public
Safety, Building Official, Planning Director, City Clerk and all city
officials charged with the issuance of licenses and/or permits for
the Auto Park will enforce the provisions of the Rancho Del Rey SPA I
Planned Community District Regulations, Employment Park Design
Guidelines, and development agreement.
3. Any building or structure erected or any use of property contrary to
the provisions of a duly approved Design Review, Site Plan, Variance,
Conditional Use Permit, Administrative Permit, and/or Planned
Community District Ordinance shall be declared unlawful and a public
nuisance and subject to abatement in accordance with local Ordinance.
Visual/Lighting Mitigation
The following project specific visual/lighting mitigation will be required
for the proposed project, in order reduce potentially significant
aesthetic impacts to a level of less than significant. These mitigation
measures will be enforced as a condition of project approval:
1. Poles and luminaires shall not be aligned in rows in two directions
(grid type layout) and only alignment parallel with the roadway shall
be permitted.
2. Pole heights shall be fixed at 24 feet and spaces not closer than 40
feet on front rows to reduce overall area brightness and eliminate
the sea of poles and light appearance.
3. Landscaping lighting shall be permitted only in designated locations
and limited in wattage and quantity.
4. Graphics and feature display lighting shall be limited in location,
wattage, and quantity and shall be shielded away from residential
uses to the north.
5. Internally illuminated and backlit signs shall be limited in size,
placement and brightness and shall be limited to one color.
6. Advertising, string lights, marquee lights or similar decorative
lighting shall be prohibited to reduce glare.
7. The use of brick or wood as opposed to metal or light color stucco on
exteriors of buildings shall be encouraged to reduce reflected light
and overall area brightness.
8. The lighting setback zone shall be fixed along "H" Street to preserve
the Parkway designation. Individual dealership signs shall be
prohibited from directly facing "H" Street.
-13-
9. Dealerships facing Rice Canyon to the north of the site shall have
their primary display areas limited in order to control lighting and
glare impacts to residential properties to the north in Rancho Del
Rey SPA I.
10. The use of high quality lighting fixtures shall be required as
recommended in the Lighting Consultants Study in order to reduce
overall area brightness.
11. All display lighting shall be limited to metal halide (maximum 1000
watts) or high pressure sodium lighting.
12. All recommendations set forth in the lighting Consultants of San
Diego Lighting Study (February 8, 1990) shall be complied with.
13. Detailed lighting plans shall be submitted to the City by each auto
dealer, indicating design layout and exact fixture/pole locations and
wattages proposed. Additionally, a computer generated footcandle
printout shall be required for each dealership lighting proposal.
Noise Mitigation
The following project specific noise mitigation will be required for the
proposed project, in order to reduce potentially significant noise impacts
to a level of less than significant. These mitigation measures will be
enforced as a condition of project approval:
1. The proposed use of a public address system at the Auto Park will be
prohibited and will be enforced through project redesign. Internal
communication will be conducted, instead, through the use of
individual beepers which would not generate any significant noise
impacts to surrounding land uses.
2. In order to reduce potentially significant noise impacts associated
with the use of pneumatic tools during repairs, the service bays at
dealerships 3, 4, 6, 8, and 10 (see Exhibit 3) shall be designed to
be oriented away from planned residences to the north.
3. All automobile repairs and service shall be conducted indoors in
fully-enclosed repair facilities. No automobile repairs shall be
allowed outside of the designated auto repair service bay areas.
Traffic Mitigation
The following project specific traffic mitigation will be required for the
proposed project, in order to reduce potentially significant traffic
impacts to a level of less than significant. These mitigation measures
will be enforced as a condition of project approval:
-14-
1. Traffic mitigation, as required by the City Engineering Department,
will consist of implementation of the standards and requirements of
the East Chula Vista Transportation Phasing Plan (TPP) and compliance
with applicable Interim Eastern Area Development Impact Fees (Willdan
Associates, June 1989).
2. Plonitor traffic until traffic reaches 51,000 ADT as determined by
theoretical calculations which equates approximately to a third
highest hour of level of service "C" at a ratio of .75. This would
provide staff with enough time to evaluate the status and scheduling
of SR-125 and other alternative projects. Also, when the ADT reaches
51,000, staff will evaluate the intersection of East "H" Street and
Hidden Vista Drive utilizing hourly traffic counts and verify the
level of service at which the intersection is actually performing.
Based on the results of the intersection study and the scheduling of
SR-125, staff will determine whether an interim widening of East "H"
Street is required or other appropriate options are considered. This
will give staff sufficient time to evaluate and monitor the
intersection more closely, and, if necessary, prepare plans to the
point of construction before the level of service on East "H" Street
reaches "D" for the third highest hour.
3. Place the widening of East "H" Street between the freeway and Terra
Nova Drive (Ridgeback Road) on both the north and south sides into
the DIF so that, if it is necessary when the volumes reach a capacity
on East "H" Street in accordance to the threshold standards, the
project can be completed as a DIF project. The widening mitigation
for East "H" Street should be a DIF project because it would benefit
all developments since the improvement would give East "H" Street a
theoretical capacity of 67,000 ADT at the east leg of East "H" Street
and Hidden Vista.
4. The applicant will be required to comply with the requirements of the
City Engineering Department concerning the funding and implementation
of necessary street improvements.
G. Findings of Insignificant Impact
Based on the following findings, it is determined that the proposed
project will not have a significant, adverse environmental effect,
therefore, no environmental impact report is deemed necessary.
1. The project has the potential to substantially degrade the quality of
the environment, substantially reduce the habitat of a fish or
wildlife species, cause a fish or wildlife population to drop below
self-sustaining levels, threaten to eliminate a plant or animal
community, reduce the number or restrict the range of a rare or
endangered plant or animal, or eliminate important examples of the
major periods of California history or prehistory.
-15-
The proposed auto park would not adversely impact any sensitive plant
or animal species, since the site has previously been disturbed for
grading and biological mitigation has already been implemented in
conjunction with the E1 Rancho Del Rey SPA I EIR (Michael Brandman &
Associates, 1985). There are no known cultural resources which would
be impacted by the proposed project, therefore, it would not be
expected to eliminate important examples of California history or
prehistory.
2. The project has the potential to achieve short-term environmental
goals to the disadvantage of long-term environmental goals.
The proposed project is consistent with the elements of the General
Plan and will be consistent with the Rancho Del Rey SPA I Plan, with
implementation of the proposed discretionary actions. The project is
in conformance to the City's applicable threshold standards regarding
public services and facilities.
Therefore, the proposed project will not achieve short-term
environmental goals to the disadvantage of long-term environmental
goals, since these long-term goals will be achieved through project
specific mitigation and compliance with the conditions of project
approval and requirements of the Mitigation Monitoring Program.
3. The project has possible effects which are individually limited but
cumulatively considerable. As used in the subsection, "cumulative)
considerable" means that the incremental effects of an individual
project are considerable when viewed in connection with the effects
of past projects, the effects of other current projects, and the
effects of probable future projects.
The proposed auto park would be associated with cumulative impacts
which were not specifically addressed in the E1 Rancho Del Rey SPA I
EIR (1985) for the Employment Park. Cumulative impacts associated
with land use, traffic, noise, and visual/lighting impacts have been
identified and analyzed in this document, and specific mitigation has
been proposed to reduce them to a level of less than significant (see
Attachment "A").
4. The environmental effects of a project will cause substantial adverse
effects on human beings, either directly or indirectly.
There were no potential human health impacts identified in the
initial study conducted for this project. There are no substantial,
adverse health effects on human beings anticipated from the proposed
project. The environmental impacts identified in the initial study
have been addressed in this document and project specific mitigation
will be required to be implemented to reduce environmental impacts to
a level of less than significant.
-16-
H. Consultation
1. Individuals and Organizations
City of Chula Vista: Maryann Miller, Environmental Review Coordinator
Steve Griffin, Current Planning
Captain Keith Hawkins, Police Dept.
Shauna Stokes, Parks and Recreation
Carol Gove, Fire Department
Ken Larsen, Director of Building and Housing
Roger Daoust, Senior Civil Engineer
Hal Rosenberg, Traffic Engineer
Fred Kassman, Community Development
Lance Abbott, Community Development
Otay Water District: Manuel Arroyo
Sweetwater Union High School District: Thomas Silva
2. Documents
Chula Vista Municipal Code, Title 19.
Chula Vista General Plan Update EIR, 1989.
E1 Rancho Del Rey SPA I Final Supplemental EIR (MBA, 1985).
E1 Rancho Del Rey SPA I Specific Plan Amendment EIR, EIR-83-2
(Westec, 1985).
Addendum to EIR-83-2 (Westec, 1985).
Rancho Del Rey SPA I Planned Community District Regulations, February
1990.
Traffic Study conducted by Bankston/Pine Associates, Inc., December
5, 1989.
Lighting Study conducted by Spaulding Lighting, Inc., Dec. 21, 1989
Noise Study conducted by ERC Environmental and Energy Services,
January 1990.
East Chula Vista Transportation Phasing Plan prepared by Willdan
Associates (June 6, 1989).
3. Response to Public Review
( ) The proposed project did not receive any comments from the
public or adjacent public agencies during the public review
period. A copy of the Initial Study is attached.
(x) The proposed project did receive comments from the public, but
did not address the Negative Declaration finding of the
accuracy/completeness of the Initial Study. No response is
necessary, and the letters are attached.
( ) Comments addressing the findings of the draft Negative
Declaration and/or accuracy or completeness of the Initial Study
were received during the public review period. The letters and
responses follow.
-17-
4. Initial Study
This environmental determination is based on the attached Initial
Study as well as any comments on the Initial Study and the ~ditigated
Negative Declaration. Further information regarding the
environmental review of the project is available from the Chula Vista
Planning Department, 276 Fourth Avenue, Chula Vista, CA 92010.
NVIRO ENTAL REVIEW COORDINATOR
EN 6 (Rev. 3/88)
WPC 7383P
ATTACHMENT A
Mitigation Monitoring Program
Rancho Del Rey Auto Park
IS-90-33
This Mitigation Monitoring Program is prepared for the Rancho Del Rey Auto
Park project, in order to comply with AB 3180. This legislation requires
public agencies to ensure that adequate mitigation measures are implemented
and monitored on mitigated negative declarations, such as IS-90-33.
AB 3180 requires monitoring of potentially significant and/or significant
environmental impacts. The mitigation monitoring program for the Rancho Del
Rey Auto Park ensures adequate implementation of mitigation for the following
potentially significant impacts:
- Land Use
- Visual/Lighting
- Noise
- Traffic Impacts
Due to the nature of the environmental issues identified, the Mitigation
Compliance Coordinator (MCC) shall be the Environmental Review Coordinator
(ERC) for the City of Chula Vista. It shall be the responsibility of the
applicant to ensure that the conditions of the Mitigation Monitoring Program
are met to the satisfaction of the ERC.
Land Use/Mitigati on
The proposed project is associated with potentially significant land use
impacts on site.
Mitigation of Potentially Significant Land Use Impacts will be ensured through
the following:
1. Implementation and monitoring of the Rancho Del Rey SPA I Planned
Community District regulations, Employment Park Design Guidelines, and
development agreement conditions will be enforced to guide the use of
land, building structures, size of yards abutting buildings and
structures, height and bulk of buildings, and standards of performance and
day-day operations for the Auto Park.
2. The City Council, City Attorney, City P1anager, Director of Public Safety,
Building Official, Planning Director, City Clerk and all city officials
charged with the issuance of licenses and/or permits for the Auto Park
will enforce the provisions of the revised Rancho Del Rey SPA I Planned
Community District Regulations, Employment Park Design Guidelines, and
development agreement.
3. Any building or structure erected or any use of property contrary to the
provisions of a duly approved Design Review, Site Plan, Variance,
Conditional Use Permit, Administrative Permit, and/or Planned Community
District Ordinance shall be declared unlawful and a public nuisance and
subject to abatement in accordance with local Ordinance.
Visual/Lighting Mitigation
The proposed project is associated with potentially significant visual/
lighting impacts. Mitigation of potentially significant visual/lighting
impacts will be ensured through the following:
1. Poles and luminaires shall not be aligned in rows in two directions (grid
type layout) and only alignment parallel with the roadway shall be
permitted.
2. Pole heights shall be fixed at 24 feet and spaces not closer than 40 feet
on front rows to reduce overall area brightness and eliminate the sea of
poles and light appearance.
3. Landscaping lighting shall be permitted only in designated locations and
limited in wattage and quantity.
4. Graphics and feature display lighting shall be limited in location,
wattage, and quantity and shall be shielded away from residential uses to
the north.
5. Internally illuminated and backlit signs shall be limited in size,
placement and brightness and shall be limited to one color.
6. Advertising, string lights, marquee lights or similar decorative lighting
shall be prohibited to reduce glare.
7. The use of brick or wood as opposed to metal or light color stucco on
exteriors of buildings shall be encouraged to reduce reflected light and
overall area brightness.
8. The lighting setback zone shall be fixed along "H" Street to preserve the
Parkway designation. Individual dealership signs shall be prohibited from
directly facing "H" Street.
9. Dealerships facing Rice Canyon to the north of the site shall have their
primary display areas limited in order to control lighting and glare
impacts to residential properties to the north in Rancho Del Rey SPA I.
10. The use of high quality lighting fixtures shall be required as recommended
in the Lighting Consultants Study in order to reduce overall area
brightness.
11. All display lighting shall be limited to metal halide (maximum 1000 watts)
or high pressure sodium lighting.
12. All recommendations set forth in the Lighting Consultants of San Diego
Lighting Study (February 8, 1990) shall be complied with.
13. Detailed lighting plans shall be submitted to the City by each auto
dealer, indicating design layout and exact fixture/pole locations and
wattages proposed. Additionally, a computer generated footcandle printout
shall be required for each dealership lighting proposal.
-2-
Noise Mitigation
The proposed project is associated with potentially significant noise impacts.
Mitigation of potentially significant noise impacts will be ensured the
following:
1. The proposed use of a public address system at the Auto Park will be
prohibited and will be enforced through project redesign. Internal
communication will be conducted, instead, through individual beepers which
would not generate any significant noise impacts to surrounding land uses.
2. In order to reduce potentially significant noise impacts associated with
the use of pneumatic tools during repairs, the service bays at dealerships
3, 4, 6, 8, and 10 (see Exhibit 3) shall be oriented away from planned
residences to the north.
3. All automobile repairs and service shall be conducted indoors in
fully-enclosed repair facilities. No automobile repairs shall be allowed
to be conducted outside the designated auto repair service bay areas.
Traffic Mitigation
The proposed project is associated with potentially significant traffic
impacts.
Mitigation of potentially significant noise impacts will be ensured through
the following:
Traffic mitigation, as required by the City Traffic Engineer, will consist
of implementation of the standards and requirements of the East Chula
Vista Transportation Phasing Plan (TPP) and compliance with applicable
Interim Eastern Area Development Impact Fees (Willdan Associates, June
1989).
2. Monitor traffic until traffic reaches 51,000 ADT as determined by
theoretical calculations which equates approximately to a third highest
hour of level of service "C" at a ratio of .75. This would provide staff
with enough time to evaluate the status and scheduling of SR-125. Also,
when the ADT reaches 51,000, staff will evaluate the intersection of East
H Street and Hidden Vista Drive utilizing hourly traffic counts and verify
the level of service at which the intersection is actually performing.
Based on the results of the intersection study and the scheduling of
SR-125, staff will determine whether an interim widening of East H Street
is required or other appropriate options are considered. This will give
staff sufficient time to evaluate and monitor the intersection more
closely, and, if necessary, prepare plans to the point of construction
before the level of service on East H Street reaches "D" for the third
highest hour.
-3-
3. Place the widening of East H Street between the freeway and Ridgeback Road
on both the north and south sides into the DIF so that, if it is necessary
when the volumes reach a capacity on East H Street in accordance to the
threshold standards, the project can be completed as a DIF project. The
widening mitigation for East H Street should be a DIF project because it
would benefit all developments since the improvement would give East H
Street a theoretical capacity of 67,000 ADT at the east leg of East H
Street and Hidden Vista.
4. The applicant will be required to comply with the requirements of the City
Engineering Department concerning the funding and implementation of
necessary street improvements.
WPC 7393P
-4-
AGENDA
City Planning Commission
Chula Vista, California
Wednesday, April 11, 1990 - 7:00 p.m.
PLEDGE OF ALLEGIANCE
INTRODUCTORY REMARKS
APPROVAL OF MINUTES - Meetings of February 28 and March 14, 1990
ORAL COMMUNICATIONS
City Council Chambers
Opportunity for members of the public to speak to the Planning Commission
on any subject matter within the Commission's jurisdiction but not an
item on today's agenda. Each speaker's presentation may not exceed five
minutes.
1. PUBLIC HEARING: PCZ-90-K-M: City-initiated proposal to rezone certain
territory, generally bounded by Main Street, Rios Avenue,
the agricultural lands adjacent to the Otay River Valley,
and a line 310 feet west of Date Street from its City-
adopted County zone classifications to City classifications
utilized throughout Chula Vista
The proposed rezonings are confined to the Broderick's
Otay Acres subcommunity of Montgomery, and are governed
by the Montgomery Specific Plan adopted by the Chula Vista
City Council on January 12, 1988 and on September 13, 1988.
Short form of Title of Proposal: Broderick's Otay Acres
2. Consideration of Final Environmental Impact Report, EIR-89-11, Olympic
Training Center
3. PUBLIC HEARING: PCM-90-05: Consideration of Olympic Training Center (OTC)
Sectional Planning Area Plan (SPA) and Public Facilities
Finance Plan (PEEP) - San Diego National Sports Training
Foundation
4. PUBLIC HEARING: Variance ZAV-90-09; request to increase floor area ratio
and reduction of side yard requirements at 688 Garrett
Street - Richard Zogob
5. Written Communication
OTHER BUSINESS
DIRECTOR'S REPORT
COMMISSION COMMENTS
Southwest Redevelopment Project
ADJOURNMENT AT p.m. to the Study Session Meeting of April 18, 1990
at 5:00 p. m. in Conference Rooms 2 & 3