RESOLUTION NO. 2005-196
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA APPROVING THE FIRST AMENDMENT TO
THE DESIGN BUILD AGREEMENT WITH T.e.
CONSTRUCTION COMPANY, INC., TO INCORPORATE THE
GUARANTEED MAXIMUM PRICE (GMP) OF $1,047,961 FOR
THE DESIGN AND CONSTRUCTION OF POGGI CANYON
TRUNK SEWERlUPGRADE OF REACH 205 (CIP SW226);
AND AUTHORIZING THE MAYOR TO EXECUTE SAID
AMENDMENT
WHEREAS, On November 16, 2004, City Council approved an agreement with T.C.
Construction Company, Inc., for the services required to design and construct a completed and
fully functional tunneled/open-excavation trunk sewer line that will upgrade Reach 205 of the
Poggi Canyon Trunk Sewer and provide wastewater service to the eastern territories of the City;
and
WHEREAS, the City Council previously approved capital improvement program project
No. SW226 and on November 16, 2004 approved a Design Build Agreement with T.C.
Construction Company, Inc. for this project (City Council Resolution 2004-361); and
WHEREAS, the Design Build Agreement contained a not-to-exceed price of
$1,250,000.00 with the GMP to be set upon receipt of90% construction drawings. The project is
nearing the end of the design phase and ready to start the construction phase this month; and
WHEREAS, the Guaranteed Maximum Price (GMP) is to be established at 90%
construction documents, which would include, but not be limited to, the cost for all labor,
equipment, and material to design and construct a fully functional trunk sewer line in accordance
with all applicable codes and requirements; and
WHEREAS, the GMP includes all design and construction services to complete a fully
functional tunneled/open-excavation trunk sewer line that will upgrade Reach 205 of the Poggi
Canyon Trunk Sewer. The total cost of the project and the GMP do not surpass the not-to-
exceed amount of $1 ,250,000 set forth in the original agreement; and
WHEREAS, T.e. Construction Company, Inc., has requested the GMP be set at
$1,047,961. The GMP includes, but is not limited to, design services, general conditions,
insurance, bonds, construction management, the cost for all labor, equipment, and material to
design and build a fully functional tunneled/open-excavation trunk sewer line that will upgrade
Reach 205 of the Poggi Canyon Trunk Sewer in accordance with all applicable codes and
requirements.
Resolution No. 2005-196
Page 2
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Chula
Vista does hereby approve the First Amendment to the Design Build Agreement with T.C.
Construction Company, Inc., to incorporate the Guaranteed Maximum Price (GMP) of
$1,047,961 for the design and construction of Poggi Canyon Trunk Sewer/Upgrade of Reach
205 (CIP SW226) and other minor modifications; and authorizes the Mayor to execute said
amendment.
Presented by
Approved as to form by
/>f;:t5//7~ ~
Jack Griffin
General Services Director
Cl'-. <'YVq:~-'\~
Ann Moore
City Attorney
Resolution No. 2005-196
Page 3
PASSED, APPROVED, and ADOPTED by the City Council of the City of Chula Vista,
California, this 14th day of June, 2005, by the following vote:
AYES:
Councilmembers:
Castaneda, Davis, McCann, Rindone and Padilla
NAYS:
Councilmembers:
None
ABSENT:
Councilmembers:
None
AI- ~c!2rL1l
. Stephen c. Jadilla, Mayor
ATTEST:
~ ~J l~ T3.~Sd 0 A"1
Susan Bigelow, MMC, City Clef!{
-'
STATE OF CALIFORNIA )
COUNTY OF SAN DIEGO )
CITY OF CHULA VISTA )
I, Susan Bigelow, City Clerk of Chula Vista, California, do hereby certify that the foregoing
Resolution No. 2005-196 was duly passed, approved, and adopted by the City Council at a
regular meeting of the Chula Vista City Council held on the 14th day of June, 2005.
Executed this 14th day of June, 2005.
:: --V,l A. ~~ ()~
Susan Bigelow, MMC, City Cler .