HomeMy WebLinkAboutrda min 1987/02/03 (2)
MINUTES OF A SPECIAL MEETING OF THE REDEVELOPMENT AGENCY
OF THE CITY OF CHULA VISTA, CALIFORNIA
February 3, 1987
6:15 p.m.
ROLL CALL
Council Chambers
Public Services Building
MEMBERS PRESENT:
Chairman Cox; Members Nader, Moore, McCandliss, Malcolm
MEMBERS ABSENT:
STAFF PRESENT:
None
Executive Director Goss, Community Development
Director Desrochers, Agency Attorney Harron, Senior
Community Development Specialist Buchan
1. APPROVAL OF MINUTES of 1/15/87 and 1/20/87
MSUC (Cox/Moore) to approve the minutes of 1/15/87 and 1/20/87.
Malcolm was not present for the vote.)
(4-0; Member
CONSENT CALENDAR
Member Nader requested that item number 2 be pulled from the Consent Calendar.
CHAIRMAN COX OFFERED ITEMS 3, 4 AND 5 FROM THE CONSENT CALENDAR, the reading
of the text was waived by unanimous consent, passed and adopted unanimously.
3. RESOLUTION 771 APPROVING A CONTRACT WITH WYLIE ASSOCIATES FOR THE
FABRICATION AND INSTALLATION OF SIGNS FOR THE TOWN CENTRE I
PUBLIC SIGN PROGRAM AND APPROPRIATING FUNDS THEREFOR
4. RESOLUTION 772 APPROVING AN OWNER PARTICIPATION AGREEMENT BETWEEN THE
REDEVELOPMENT AGENCY AND DALE OHLAU FOR THE REMODELING OF
THE EXISTING 2-STORY BUILDING AT 293-295 THIRD AVENUE
5. RESOLUTION 773 APPROVING MICHAEL BRANDMAN ASSOCIATES, INC. AS THE
CONSULTANT TO PREPARE THE OTAY VALLEY ROAD BIOLOGICAL
STUDIES AND AUTHORIZING THE AGREEMENT
2. RESOLUTION 774 APPROVING A 26 DAY EXTENSION AND $20,000 TO RAMM
CONTRACTING COMPANY FOR ON-SITE COSTS DUE TO HVAC DELAY FOR
NATURE INTERPRETIVE CENTER CONSTRUCTION
Based on the bar chart prepared by Ramm Contracting for the construction of
the Nature Interpretive Center, the heating and air conditioning system (HVAC
system) was to be installed in the building between the weeks of November 10
and December 1 of 1986. Ramm Contracti ng notifi ed the City by 1 etter, dated
November 19, that their subcontractor, Lanthier, would be unable to complete
constructi on of the flVAC system for the south si de of the bui 1 di ng on schedul e
Redeve1opment Agency Minutes
-2-
February 3, 1987
due to the need for re-desi gn. Shel don Ty1 er (Cl erk-of-the-Works) verifi ed
that the system in the approved plans needed corrections and material
replacements, etc. Ramm Contracting has requested a time extension and costs
related to the delays.
Member Nader stated he wanted it to be cl ear that in approvi ng thi s change
order, the Agency is at the same time di recti ng staff to pursue any remedi es
existing against offending contractors.
Member Malcolm questioned if the architect was contacted as soon as the
probl em was di scovered. He further asked if the archi tect agreed that the
changes were necessary. Senior Community Development Specialist Buchan
responded that the architects were contacted right away. The architects
indicated that some changes and corrections should be made.
Member Malcolm noted his concern that staff was not on top of the problem,
that it should have been discovered at an earlier point in time. He stated
the architect and builder should have resolved this problem. Member Malcolm
stated he woul d 1 i ke to see a report from the archi tect stati ng (1) the
architects agree they designed the HVAC system wrong; (2) what their
recommended changes were and did the City go beyond their recommended changes;
and (3) what is their position on paying for the costs involved.
Community Development Director Desrochers stated that staff has been on top of
the situation. The Clerk-of-the-Works has been on site every day. As soon as
staff was aware of the problem the architects were asked to remedy the
problem. Mr. Desrochers pointed out in the Agenda Statement it states that
the Agency has the right to submit a claim to the architect for the $20,000
si nce it is staff's opi ni on that the pl ans were not prepared properly or
expediently corrected.
In response to Member Nader's question if the architect agreed that changes
necessitating the expendi ture of $20,000 is necessary, Mr. Desrochers stated
the architect has agreed there was a need for the change; however, they do not
feel this is a legitimate claim to them. They do not feel the contractor is
due the $20,000 for the delay.
Mr. Coulter Wi nn of Wi nn-Cutri Architects addressed the Agency. Mr. Cutri
stated he and his partner are concerned that they are being held 100%
responsibl e for the del ay of the contract when construction forces were at
work on a percentage basis.
Ms. Buchan poi nted out the contractor ori gi na lly requested 60 days for del ay
and $40,000 per month, a total of $80,000. In the best interest of the
project, staff negotiated the requested amount down to 26 days and $20,000.
Member Nader questi oned if it is staff's posi ti on that the $20,000 fi gure is
defensible in terms of being causily related to the delays caused by this
particular problem. Ms. Buchan responded yes, this was a critical path iteM
which was to be completed by the end of November. In the early part of
December it became clear other trades would be delayed because of this
Redevelopment Agency Minutes
-3-
February 3, 1987
problem. This is the point in time when staff met with the architect and
contractor and tri ed to make correcti ons on si te. There were some time
delays. Requests for information were not taken care of in a timely manner
which staff felt the architect was responsible for.
Member McCandl i ss asked the Ci ty Manager if he concurred with the
recommendation. Mr. Goss noted the recommendation is a reasonable compromise
in a diffi cult si tuati on. The abil ity of the City to conti nue to pursue a
claim against the architect is a key factor.
Chairman Cox pointed out the action is necessary in order to allow the project
to move forward, however, it is the City's intention to look into this further
and come back with a report to the Agency regarding whether to seek
restitution from the architect or other parties that are deemed responsible.
MEMBER MOORE OFFERED THE RESOLUTION, the reading of the text was waived by
unanimous consent.
Chairman Cox noted he has visited the job site on a number of occasions and
from hi s observati on the Cl erk-of-the-Works, Mr. Shel don Tyl er, has done an
excellent job. He also pointed out the architects came up with an excellent
design.
t1ember Nader stated although it is in the staff report that staff will be
seeking compensation from the architects, it is not part of the resolution.
MSUC (Nader/Moore) to amend the resolution to include a direction for staff to
seek appropriate compensation from the architect.
The resolution as amended was passed and adopted unanimously.
MSUC (Moore/Malcolm) that staff prepare the following report for the Agency
regarding the Nature Interpretive Center construction: (1) Individual
contractors fees; (2) number of changes and costs along wi th responsi bil i ty
for changes; (3) paper trial involved in changes and charges.
Mr. Shel don Tyl er, Cl erk-of-the-Works, addressed the Agency. He stated hi s
job is to go through the plans and specifications and be sure they agree. All
through this project the plans and specifications do not agree and that is why
there have been approximately 34 change orders. He noted everyone of the
change orders have been renegoti ated by him with the contractor or
subcontractor and each one has been cut down by 30 to 60%.
Member Moore asked the Clerk-of-the-Works to describe the process involved in
the change of size of the amphitheater. Mr. Tyler stated the elevations were
wrong on the plans. This was discovered by him in working with the
contractor. The architect was then contacted to look into the probl em and
issue a change order. A bi d of $4,700 was submitted whi ch was negoti ated to
$2,700. Mr. Tyl er further noted it is not unusual to have thi s number of
change orders, that the number of change orders on simil ar projects is often
higher.
Redevelopment Agency Minutes
-4-
February 3, 1987
6. ORAL COMMUNICATIONS:
None.
7. DIRECTOR'S REPORT:
None.
8. CHAIRMAN'S REPORT:
None.
9. MEMBERS' COMMENTS
None.
The Redevelopment Agency adjourned at 6:58 to Closed Session to discuss Sierra
Club vs. Marsh; Sierra Club vs. Coastal Commission et al and items of
potential litigation. The Agency adjourned from Closed Session at 8:00 p.m.
ADJOURNMENT to a regular meeting of February 10, 1987 following the City
Council meeting beginning at 7:00 p.m.
WPC 27l0H