SECTION: Permit Proc'/Plan Checkllnspection SUBJECT: Special Inspection Program
DATE EFFECTIVE: DATE REVISED:
PURPOSE:
The purpose of this procedure is to outline the steps and responsibilities of each
discipline when plan checking, processing and inspecting projects requiring special
inspection,
Note: Throughout this procedure, HERS (Home Energy Rating System) raters are to be
considered special inspectors and the procedures outlined below apply to HERS
raters as they apply to special inspectors unless noted otherwise,
PROCEDURES:
California Building Code, Section 1701, and California Energy Efficiency Standards,
require special inspection for the following types of work:
Special inspection may not be required when the work requiring special inspection is
performed on the premises of an approved fabricator and the procedure for "Shop
Fabrication" is complied with, See Items F (a) and (b) under "Inspection,"
During Plan Check:
On projects where the Plans Examiner identifies work requiring special inspection
and/or shop fabrication; the Plans Examiner shall do the following:
Page 1 of 7
Assistant Director of Planning and Building/Building Official
DRAFT DEPARTMENT OF PLANNING & BUILDING
~\~ BUILDING DIVISION
--...---
p -
- --
CllY OF OPERA TlONS AND PROCEDURES
(HUlA VISTA
SECTION: Permit Proc'/Plan Check/Inspection SUBJECT: Special Inspection Program
DATE EFFECTIVE: DATE REVISED:
A. Identify all work requiring special inspection and request that the designer shows
the information in one location on the plans (i.e, Title/Cover Sheet, S-1 Sheet-
Special Inspection Table/Schedule,)
B. Insert a comment in the correction list stating that the attached "Property
Owner/Contractor Agreement Form" to be completed and signed prior to permit
issuance,
C, Attach the applicable special inspection forms to the correction list (for HERS,
"Property Owner/Contractor Agreement Form" and energy compliance forms CF-
4R and CF-6R.)
0, Complete the "Special Inspection" screen in Permits Plus,
At Building Counter:
The Development Services Technicians (DS1's) will hand over or fax to the applicant
the special inspection forms that are attached to the correction lists generated by the
plans examiners.
At time of permit issuance, the DST must collect a completed "Property
Owner/Contractor Agreement Form" and attach it to the Permit Application,
Inspection:
Prior to the first day a special inspector is scheduled to be on the job site, he/she must
do the following:
1, Notify the Inspection Section of the permit number, project address, date and
approximate time he/she is scheduled to be on the job site, and a phone number
that he/she can be reached at (preferably his/her cell phone,) This can be
accomplished by either calling in the information or completing Form 4545 and faxing it
to the Inspection Section,
2, Fax a copy of his/her qualifications, experience and driver license/photo 10 to the
Inspection Section,
Page 2 of 7
Assistant Director of Planning and Building/Building Official
DEPARTMENT OF PLANNING & BUILDING
BUILDING DIVISION
CllY OF OPERA TIONS AND PROCEDURES
(HUlA VISTA
SECTION: Permit Proc.lPlan Check/Inspection SUBJECT: Special Inspection Program
DATE EFFECTIVE: DATE REVISED:
The two requirements shown above are also required when a replacement special
inspector, other than the originally approved special inspector, takes over the project on
a temporary or permanent basis.
Special inspectors can notify the Inspection Section by phone (619) 409-5868 or Fax
(619) 216-7306,
The following are the steps taken by the Inspection Section staff:
A, Staff receives a call or a fax from a special inspector or Inspection Agency
identifying the permit number, project address, date and time the special
inspector's first day on site,
ß, The Office Specialist or Development Services Technician enters the information
on the "Special Inspection" screen in Permits Plus,
C, The Office Specialist or Development Services Technician forwards the
information collected under item (A) above to the Building Inspector (BI) assigned
to the project.
0, The BI incorporates the time into his daily schedule and meets the special
inspector at the job site to verify his/her qualifications, inform him/her of the City's
procedures and expectations and give him/her the "Special Inspection
Instructions To Speciallnspectors/lnspection AgencieslTesting Labs/HERS
Raters."
Special Inspector Qualifications
Special inspectors shall have current copies of certificates or cards for work requiring
special inspection and a current driver license/photo 10,
Except for grading, smoke control, and other specialty inspections for which a
certification is not required by law, special inspectors must be certified in their areas of
expertise. The following table indicates required certification for each type of special
inspection:
Re uired Certification
ICBO - Reinforced Concrete
Page 3 of 7
Assistant Director of Planning and Building/Building Official
DRAFT DEPARTMENT OF PLANNING & BUILDING
~\~ BUILDING DIVISION
-fi-
r -= __
- OPERA TIONS AND PROCEDURES
CllY OF CHULA VISTA
SECTION: Permit Proc'/Plan Checkllnspection SUBJECT: Special Inspection Program
DATE EFFECTIVE: DATE REVISED:
Moment Frame
Shotcrete ICBO - Reinforced Concrete
Insulating Concrete Fill, Reinforced Gypsum ICBO - Reinforced Concrete
Concrete
Bolts installed in Concrete (per Section 17015, item ICBO - Reinforced Concrete
2,)
Structural Masonrv ICBO - Structural Masonrv
Pre-stress/Post-tension Steel Tendons ICBO - Pre-stressed Concrete
Structural Welding ICBO - Structural Steel & Welding
orAWS
HiOh-strenqth Boltina ICBO - Structural Steel & Weldino
SoraV-aoolied Fireoroofino ICBO - SoraV-aoolied Fireoroofinq
Piling, Drilled Piers and Caissons Reinforced Concrete + Soils
Engineer/Engineering Geologist of
record
Grading, Excavation and Filling Soils Engineer/Geotechnical
Enaineer of record'
Smoke-control System Certified Air Balancing Technician +
Mechanical Enqineer of Record
HERS Ratina CHEERS certified HERS rater
Special cases when required by the Building Official Based on the work requiring special
or a oroduct evaluation reoort insoection
1. The soils engineer or Geotechnical engineer of record may designate a qualified
individual as their agent to perform special inspection on grading, excavation and filling.
Note: Except for grading, smoke control, and other specialty inspections for
which a certification is not required by law, the fact that a person is the
architect or engineer of record should be no factor in determining whether the
person is qualified as a special inspector, If the architect or engineer is
qualified as a special inspector by demonstrating satisfactory competence in
a particular type of construction, it is acceptable for the architect or engineer
to perform special inspection for a project.
E, Special inspection reports and test results are to be reviewed by the BI assigned
to the project within two working days from the date of receipt of the report or test
results. Identified issues/concerns are to be communicated to the special
inspector or Testing Agency by the next working day from the date the
issue/concern is identified,
Page 4 of 7
Assistant Director of Planning and Building/Building Official
DEPARTMENT OF PLANNING & BUILDING
BUILDING DIVISION
CllY OF OPERA TIONS AND PROCEDURES
CHUlA VISfA
SECTION: Permit Proc.lPlan Check/Inspection SUBJECT: Special Inspection Program
DATE EFFECTIVE: DATE REVISED:
F. The BI shall collect the following forms, if applicable, at the stage of construction
as identified below:
a, "Application to Perform Off-Site Fabrication" - Form 4540: This application
shall be completed by the fabricator of building components when such
components are fabricated within the premises of the fabricator's shop,
This application must be submitted to the Inspection Section for approval
at least three business days prior to the scheduled start of fabrication, A
BIIII (or Snr. BI) shall review the application within the next working day of
receipt for completeness and qualification, If the application is not
complete or the fabrication shop is not qualified, the BIIII (or Snr. BI) shall
immediately notify the fabrication shop and the contractor of the
requirements,
b, "Certificate of Compliance for Off-Site Fabrication" - Form 4541: This form
shall be completed by the fabricator of building components when such
components are fabricated within the premises of a fabricator's shop, This
form must be filed with the Inspection Section and approved prior to the
installation of the fabricated components,
c, "INSTALLATION CERTIFICATE" (CF-6R) and "CERTIFICATE OF FIELD
VERIFICATION AND DIAGNOSTIC TESTING" (CF-4R): Form CF-6R to
be completed and signed by the installer and form CF-4R to be completed
and signed by the HERS rater. Both forms must be submitted to the
Inspection Section prior to "Final" inspection,
d, "Special Inspector/Inspection Aqencv!Testinq Laboratorv Final Report"-
Form 4543 (not applicable to HERS raters): This form shall be completed
by the special inspector and/or the special inspection agency and/or the
construction materials testing laboratory after all work requiring special
inspection or testing have been completed, and submitted to the
Inspection Section prior to final inspection,
e, "Property Owner's Final Report" - Form 4542: This report shall be
completed by the property owner or his/her authorized agent of record or
the architecUengineer of record acting as the property owner's agent for
the types of work requiring special inspection, construction materials
testing or off-site fabrication, This form must be filed with the Inspection
Section prior to final inspection,
Page 5 of 7
Assistant Director of Planning and Building/Building Official
DEPARTMENT OF PLANNING & BUILDING
BUILDING DIVISION
CllY OF OPERA nONS AND PROCEDURES
CHULA VISTA
SECTION: Permit Proc.lPlan Check/Inspection SUBJECT: Special Inspection Program
DATE EFFECTIVE: DATE REVISED:
Prior to "Final", and only after the 81 verifies that all required reports and forms have
been submitted and are in compliance, he/she must approve Item 4470, "8ldg, Special
Insp," in the Permits' Plus Inspection Module,
Quality Control:
A. The 81 shall visit the job site at least once a week to verify that the special
inspector is performing his/her duties while work requiring special inspection is in
progress, The 81 shall document his/her observation, If the Special Inspector is
not performing his/her duties while work requiring special inspection is in
progress, staff must follow the steps listed below under "8",
8, All corrective actions must be properly documented (ie: correction notice and
computer entry including verbal warnings), Staff must follow the steps listed
below in the order shown:
Step 1, First occurrence
Written Notice - Performed by 81.
Issued by the 81 on site identifying the dutieslresponsibilities the Special
Inspector failed to comply with, The Notice must include a statement
informing the Special Inspector what are his/her duties/responsibilities as
it relates to the dutylresponsibility he/she failed to comply with, A copy of
the notice shall be given to the Special Inspector, Inspection Agency (if
applicable), contractor and the owner/owner's agent.
Step 2, Second occurrence
Second Written Notice - Performed by 81.
Issued by the 81 on site identifying the duties/responsibilities the Special
Inspector failed to comply with, The Notice must include a statement
informing the Special Inspector what are his/her duties/responsibilities as
it relates to the duty/responsibility he/she failed to comply with,_A copy of
the notice shall be given to the Special Inspector, Inspection Agency (if
applicable), contractor and the owner/owner's agent.
Page 6 of 7
Assistant Director of Planning and Building/Building Official
DRAFT DEPARTMENT OF PLANNING & BUILDING
~(~ BUILDING DIVISION
-.-
.- -
-- -
erN OF OPERA TlONS AND PROCEDURES
CHULA VISTA
SECTION: Permit Proc.lPlan Check/Inspection SUBJECT: Special Inspection Program
DATE EFFECTIVE: DATE REVISED:
Step 3, Third occurrence
Office Interview - Performed by Snr, Inspector.
Snr, Inspector meets with the Special Inspector to discuss his/her
performance, code requirements and City requirements, and inform
him/her of the potential dismissal from inspecting projects in the City if
he/she continues to be irresponsible.
Step 4. Fourth occurrence
Dismissal - Performed by the Building Official or the Deputy Building
Official.
The Building Official or the Deputy Building Official, with the assistance of
the City Attorney's Office, notifies the Special Inspector and/or Inspection
Agency, in writing, that the Special Inspector is no longer authorized to
perform special inspection on projects in the City Of Chula Vista, The
special inspector or inspection agency may appeal the decision of the
Building Official orJhe Deputy Building Official to the Board of Appeals
and Advisors.
Page 7 of 7
Assistant Director of Planning and Building/Building Official
~!f?
DRAFT -1'1-
~ - - - _:
(nYQF
CHUIA VISTA
BUILDING INSPECTION SECTION
SPECIAL INSPECTION INSTRUCTIONS TO SPECIAL
INSPECTORS/INSPECTION AGENCIES/TESTING LABS/HERS RATERS
900 Lane Avenue, Suite 200
Chula Vista, CA 91914
Phone (619) 409-5868
Fax (619) 216-7306
1. PURPOSE:
The purpose of this document is to inform special inspectors, inspection agencies, material
testing labs and HERS raters_hired for their services on building construction projects in the City
of Chula Vista of building code regulations and City requirements related to special inspection
and testing of construction material.
Note: Throughout this procedure, HERS (Home Energy Rating System) raters are to be
considered special inspectors and the instructions outlined below apply to HERS raters as they
apply to special inspectors unless noted otherwise,
2, START WORK NOTIFICATION:
Prior to the first day a special inspector is scheduled to be on the job site, he/she must do the
following:
1 Notify the Inspection Section of the project, date and approximate time he/she is
scheduled to be on the job site, and a phone number that he/she can be reached
at (preferably his/her cell phone,) This can be accomplished by either calling in
the information (619) 409-5868 or completing Form 4545 and faxing it to the
Inspection Section (619) 216-7306. This information is needed to coordinate a
time when the City inspector can meet the special inspector on site,
2, Fax a copy of his/her qualifications and current driver license/photo ID to the
Inspection Section.
The two requirements shown above are also required when a replacement special
inspector, other than the originally approved special inspector, takes over the
project on a temporary or permanent basis,
Except for grading, smoke control, and other specialty inspections for which a certification is not
required by law, special inspectors must be certified in their areas of expertise, The following
table indicates required certification for each type of special inspection:
WORK REQUIRING SPECIAL INSPECTION REQUIRED CERTIFICATION
Concrete, Reinforcing Steel, Special Concrete Moment ICBO - Reinforced Concrete
Frame
Shotcrete ICBO - Reinforced Concrete
Insulating Concrete Fill, Reinforced Gypsum Concrete ICBO - Reinforced Concrete
Bolts installed in Concrete (per Section 1701,5, item 2.) ICBO - Reinforced Concrete
Structural Masonry ICBO - Structural Masonry
Prestress/Post-Tension Steel Tendons ICBO - Prestressed Concrete
DRAFT SPECIAL INSPECTION INSTRUCTIONS - Continued
Structural Welding ICBO - Structural Steel & Welding or AWS
High-strength Bolting ICBO - Structural Steel & Welding
Spray-applied Fireproofing ICBO - Spray-applied Fireproofing
Piling, Drilled Piers and Caissons Reinforced Concrete + Soils
Enoineer/Enoineerino Geolooist of record
Grading, Excavation and filing Soils Engineer/Engineering Geologist or
Gradino'
Smoke-control System Certified Air Balancing Technician +
Mechanical Enoineer of Record
HERS Rating CHEERS certified HERS rater
Special cases when required by the Building Official or a Based on the work requiring special
product evaluation report insoection
* The soi!s engineer or engineering geologist of record as an alternative must designate grading Special Inspector
NOTE: Desiqn Professional of Record vs Special Inspector, Except for grading, smoke control,
and other specialty inspections for which a certification is not required by law, the fact that a
person is the architect or engineer of record should not be a factor in determining whether the
person is qualified as a Special Inspector, If the architect or engineer is qualified as a Special
Inspector by demonstrating satisfactory competence in a particular type of construction, it is
acceptable for that architect or engineer to perform special inspection on a project.
3, SCOPE OF AUTHORITY:
The special inspector's authority is limited to the extent of providing special inspections for the
types of work in the category in which he/she is certified for.
The special inspector is not authorized to:
A. Inspect or approve any work for which a building permit has not been issued,
B, Infer/inform others that the special inspection is in lieu of City inspection and approval.
C, Accept changes, revisions and substitutions to the approved permitted plans that have not
been approved in writing by the Building Division,
4, DUTIES AND RESPONSIBILITIES:
A. The special inspector shall observe the work assigned for conformance to the approved
permitted design drawings and specification,
B, The special inspector shall verify compliance with the requirements of the California Building
Code and other code related publications pertaining to special inspection, HERS raters shall
verify compliance with the requirements of the California Energy Efficiency Standards,
C, The special inspector shall bring all "discrepancies" to the immediate attention of the
contractor for correction, then if uncorrected, to the Building Inspection Section, the engineer
or architect of record, and the owner, The written report may be submitted by fax or delivered
in person,
D. The special inspector shall submit written inspection reports to the Building Inspection
Section, to the engineer or architect of record and to other designated person(s),
E, Prior to "Final" inspection, the special inspector shall submit to the Building Inspection Section
a final signed report (Form 4543 - Special Inspector/Inspection AgencyfTesting Laboratory
Final Report) stating that the work requiring special inspection is, to the best of his
knowledge, in conformance to the approved plans and specifications and the applicable
workmanship provisions of the California Building Code,
F. Prior to "Final" inspection, HERS raters shall submit a completed and signed "CERTIFICATE
OF FIELD VERIFICATION AND DIAGNOSTIC TESTING" (CF-4R) to the Building Inspection
Section,
Page 2 of 5
DRAFT SPECIAL INSPECTION INSTRUCTIONS - Continued
5, SPECIAL INSPECTION AND MATERIAL TEST REPORT
For writing and submitting special inspection reports and for construction materials testing
reports, the following information must be included (not applicable to HERS raters):
A. The building permit number.
B, Street Address
C, Scope of work Performed, The reports must clearly and legibly state the scope of work
performed, The reports must also define the area of work inspected/tested by physical
location and/or grid lines, stories, etc" and the type of special inspection/testing performed
at each location,
0 Statement of Compliance The report must clearly state work performed "was in
compliance with the City approved permitted plans, details and specifications" or "was not
in compliance with the City approved permitted plans, details and specifications",
E, Date & Time, The reports must state the date of inspection and the time of arrival and
departure from the job site, Also the date the material was sampled and the date it was
tested,
F, Reports must be consecutively numbered,
G. Name & Signature with the certification number,
H, Report Submittal Date, The Building Inspection Section and the engineer/architect of
record must receive weekly inspection reports within five (5) calendar days after the date
when special inspection was performed.
The Building Inspection Section must receive material test reports within five (5) calendar
days after the date when testing was performed, A copy of material test reports shall also
be submitted to the architect/engineer of record,
I. Deviations When the special inspector becomes aware of a deviation from the Building
Code, the City approved permitted plans and specifications, or the standard construction
practice, he/she shall bring this to the attention of the project superintendent and/or to the
attention of the person responsible for doing the work immediately for corrective action,
If no corrective action is taken the special inspector must report such deviations or non-
compliance to the Building Inspection Section no later than the next business day by
calling and submitting a written report, The written report may be submitted by fax or
delivered in person,
6, FIELD REPORT(S) SHOULD INCLUDE BUT NOT LIMITED TO (EXAMPLE OF DETAILED
REPORTS): (Not applicable to HERS raters)
A. Concrete - Rebar grade, mix design, location of placed concrete, yardage, quantity of
samples, time spent in truck drum, slump, temperature of concrete, location of samples
taken, pumped or tailgated, consolidated, detail(s)/sheet numbers from approved set of
plans, batch plant ticket number, concrete supplier, lap and clearances and general
weather conditions,
B, Epoxy - Hole depth, diameter, evaluation report number, expiration and batch number,
location, approximate air temperature, detail(s)/sheet numbers from approved set of
plans,
Page 3 of 5
DRAFT SPECIAL INSPECTION INSTRUCTIONS - Continued
C, Welding - Welders to be certified by name and qualified welding positions, verified
welding procedure specification (WPS), amps, volts, electrode(s), type of welds, location,
preheat, interpass, fit-up, detail(s)/sheet numbers, mill certification(s); changes to
procedure qualification record (PQR) may require re-qualification,
D, Structural masonry -location of C,M,U, wall, lift location, size of C.M,U" working stress
design, reinforcing steel for size, grade, lap, clearance, location, cleanouts, consolidated
and reconsolidate, location of samples - prisms, grout, mortar, grout supplied by, ticket #,
truck #, detail(s)/sheet numbers from approved set of plans,
E, Pre-stressed/post-tension concrete - see applicable requirements for reinforced
concrete, concrete reached a compressive strength of ~ PSI prior to tensioning
operations, gauge and ram number were used with a recent calibration date of ~,
tendons stressed to a gauge pressure of ~ PSI corresponding to ~ % of the
tendons ultimate strength and anchored at ~% of ultimate strength, individual tendon
elongations, detail(s)/sheet numbers from approved set of plans ..,etc,
F, Sprayed fireproofing - verify thickness, density and adhesion/cohesion strength of the
sprayed fire-resistive material (SFRM) in accordance with approved plans, specifications
and applicable ASTM standards, where a fireproofing schedule is not included in the
approved plans and specifications, prepare a schedule and submit it to the Building
Division, Document the names of SFRM applicators, Applicators shall be approved by
the manufacturers of the materials specified, unless specifically approved by the design
professional of record, Verify that the SFRM is as specified, verify that if primer is
required, it is of the type recommended by the SFRM manufacture Detail(s)/sheet
numbers from approved set of plans..,etc,
G. High strength bolting - verify type of joint specified (I.e, slip critical, non-slip critical)
bolts, nuts and washers are in compliance to project specifications, installation procedures
meet minimum bolt tensions required by code, faying surfaces are free from dirt, When
applicable, verify bolt tensioning torque with a tensioning device such as the skidmore
wilhelm at least once a day, once a shift and each time a new batch is opened, Bolts
other than the snap-off variety or the direct tension indicator shall have tension/torque
verified, detail(s)/sheet numbers from approve set of plans..,
7, SUB-CONTRACTING AND TESTING:
A. Special inspectors are strictly prohibited from employing, delegating and/or sub-
contracting their services to another special inspector after having been approved by the
Building Inspection Section to work on a project. Substitute Special Inspectors, temporary
or permanent, must be approved by the Building Inspection Section prior to performing
special" inspection,
B. Concrete cylinder test specimen sampling slump test and other field related work
associated with the concrete at the point of truck delivery may be preformed by an ACI-
GRADE 1 field technician, provided: the approved special inspector for concrete is on the
job site when the concrete truck arrives "and" the field technician's work is performed
under supervision of the approved concrete special inspector.
C, All construction materials and test specimen shall be tested by a testing laboratory listed
on the City of San Diego or the City of Los Angeles most current list of approved testing
laboratories. Testing laboratories are permitted to employ, delegate to and or sub-
Page 4 of 5
DRAFT SPECIAL INSPECTION INSTRUCTIONS - Continued
contract their material testing services to another approved construction materials testing
laboratory,
D, Non-destructive testing of materials are considered to be testing and shall be performed
by qualified/certified technicians employed by and under the approved construction
materials testing laboratories supervision, Laboratories shall be on a current approved list
from the City of San Diego or the City of Los Angeles,
E, Special inspectors are strictly prohibited from performing non-destructive testing or testing
of construction material or assemblies unless they are employed by an approved
construction materials testing laboratory and are properly certified/qualified to perform
such testing,
F, The soils engineer or engineering geologist of record is deemed qualified as a special
inspector for excavation and filling, As an alternative, the soils engineer or engineering
geologist of record may designate another soils engineer or engineering geologist, or a
certified grading inspector, to be the special inspector,
8, CONTINUOUS vs. PERIODIC SPECIAL INSPECTION:
Continuous Special Inspection:
Continuous special inspection means that the special inspector is on site at all times observing
the work requiring special inspection,
Periodic Special Inspection:
Some inspections may be made on a periodic basis and satisfy the requirements of continuous
inspection, provided the periodic scheduled inspection is performed as outlined in the project
plans and specifications and approved by the Building Official.
NOTES:
A. If there is no periodic inspection schedule outlined on the project permitted plans, Special
inspections are required to be performed on a continuous basis,
B, Periodic special inspection will only be permitted to be performed for the types of work
which are allowed by the Building Code to be performed on a periodic basis in lieu of
continuous basis,
C, Periodic special inspections must include initial inspections, inspections of work in
progress in accordance with the schedule outlined in the project plans and final
inspections,
9, SUSPEND OR TERMINATE:
The Building Official or the Deputy Building Official may disqualify a special inspector, inspection
agency, testing lab or HERS rater from working on projects in the City Of Chula Vista when
he/she determines that the special inspector, inspection agency, testing lab or HERS rater is
incompetent or in violation of building code regulations and/or City requirements, A special
inspector, inspection agency, testing lab or HERS rater may appeal the decision of the Building
Official or the Deputy Building Official to the Board of Appeals and Advisors,
Page 5 of 5
FORM 4544
~ 1ft.. City Of Chula Vista SPECIAL INSPECTIONI
-.,- Building Division Inspection Section CONSTRUCTION
~-.,.. Planning and Building Department
CIlY OF 900 Lane Avenue, Suite 200 MATERIALS TESTING
(HUlA VISTA Chula Vista CA 91914
Information: (619) 409-5868 Fax: (619) 216-7306 INSTRUCTIONS
Property Owner's/Contractor's/Builder's Responsibilities
PLEASE READ THESE INSTRUCTIONS CAREFULLY. YOU ARE RESPONSIBLE FOR COMPLYING
WITH THESE REQUIREMENTS. ANY VIOLATIONS OF THESE INSTRUCTIONS MAYBE A CAUSE FOR
REMOVAL OF THE WORK PERFORMED.
Note: Throuohout this orocedure. HERS (Home Enerov Ratina Svstem) raters are to be considered saecial insaectors
and the resoonsibilities outlined below aDo Iv to HE'ìS raters as the'l aool'l to scecial inscectors unless noted
otherNise.
I. PROPERTY OWNER'S RESPONSIBILITIES:
The property owner or his/her authorized agent of record or the architec:/engineer of record acting as the property owner's
agent shall:
1. Complete, sign and execute the 'PROPERTY OWNER/CONTRACTOR A,GREEMENT' fcrm for the special
inspection, off-site fabrication or ccnstruction mater:als testing and submit it to :he Planning and Building
Department at time of permit issuance.
2. Employ one or more special inspectors who shall previce ¡r,s~ect¡cr,s during ccnstruction and fatricaticn of the
types of work requiring special inspection listed under Califcrnia Building Code !in the C2se of HERS raters.
Caliiornia Enerav Efficiencv Standards) as adcpted by the City of Chula Vista, See, 1701.5 and listed in the
approved plans/specifications and as required by prcduc: manufacturer's apprcval repcrts. These inspections are
in addition to and not a substitution for the required City inspections.
NOTE: The special inspection shall be performed by a spec:al inspector certified in their areas of expertise.
The ccnstruction materials testing shall be performed by a testing laboratorj listed on the City of San Diego or the
City oi Los Angeles most current list of approved materials testing laboratories.
The same special inspector(s) and the construction materials testing laboratorj shall be emplcyed during the
construction of the permitted building/structure to the extent that is possible.
3, Complete, sign, execute the 'PROPERTY OWNER'S FINAL REPORT FOR SPECIAL INSPECTION, AND
CONSTRUCTION MATERIALS TESTING' form and submit It to the Building Inspection Section prior to
requesting a final inspection,
This final report states that all work requiring special inspection, testing, or off-site fabrication was to the best of
his/her knowledge, performed in accordance with the approved plans, speoifications and the applicable
workmanship provisions of the California Building Code (in the case of HERS raters. California Enerav Efficlencv
Standards) as adopted by the City of Chula Vista
4. Remove and replace, repair, test and inspect all non-conforming work as proposed by the architecUengineer of
record and as approved by the City of Chula Vista without any cost to this jurisdiction,
Fêge 1 of 3
FORM 4544
SPECIAL INSPECTIONICONSTRUCTION MATERIALS TESTING INSTRUCTIONS (Continued)
II. CONTRACTOR'S/BUlLDER'S RESPONSIBILITIES:
The contractor/builder shall:
1, Complete, sign, execute the 'PROPERTY OWNER/CONTRACTOR AGREEMENT' form for the soecial
inspection, construction materials testing, off-site fabrication or HERS rating and submit it to the Building Division
at the time of permit issuance.
2, Notify the special inspec:or/construction materials testing labe-rator} and schecule to perform the insf:ection cf the
work requiring special inspection and/or testing.
NOTE: The special inspections are in addition to and not a substitution for the inspecticns required by the C;ty of
Chula Vista, Work performed shall not be conceaied untii it is approved by the special Inspector and the City of
Chula Vista Building I nspection Section,
The special inspec:jon shail be performed by a spec:al inspector certified in their areas of exper:ise.
The construction materials testing shall ce performed by a testing laccratcr/ listed en the City of San Diego or the
City of Los Ange!es most current list cf apcrovec rtêŒriais :esting laccratcr:es.
0 Make available to the spec:al ins¡:ec:cr(s) anc the tes¡ing agency access to the acprcvec plans and spec:f:c2tions
at the job site.
4 Inform an sub-contrac:ors, builders, erec:ors and installers perfcrming work reqL;iring special inspec:íon/tes~¡ng of
these requirements as specified in the approved plans and specifications anc as mancated by the California
Building Code (in the case of HERS raters. Califcriia =;,e:c\¡ Effic:enc'l St.2ncan:si as 2ccpted by the City cf
Chula Vista Dricr to eC'rLlfL,encement ef 'Nerk.
5. Perform the work re~uiring special inspecticn in tr.e ccr,t:r.ucus presence of :r:e s.:ec:a! :nspectcr (or en a periodic
basis as scheduled and noted cn the a!=proved plar.s ar.c s.:ecif¡cat~cns). \jVcr~ ce:=cr~ed bv a scec:al inscectcr
not certified and/or witr.cut the recuired scec:al inscec:ícnitestinc. whether cur:eseTuilv cr inadvertentlv. sn211 be
construed as nen-confcrmina 'Nork and tr-:erefore in '¡iela'Licn cf 'Lrle California EUI!ci~c Ccce (in the case of HERS
raters. California EnerclJ Effic:enc'J Stanc2rc1sì as 2ccctec 2,\¡ tr,e C¡t'l of Chul2 Vista.
6. Remove and replace, repair, test and inspect all ncn-sonfcrming wcrk as prc¡:cseci by ~~e architec;:Jenginee: of
record and as approved by the City of Chula Visia. withcut 2r,y cost to this jur:sticticn
7, Furnish the 'Application to Perform Off-Site Fabrication' to the fabrieator(s) of cciJcing components to be
completed and submitted to the Building Divisicn Ir,s.:ecticn Sec:ion,
NOTE: The fabricator of the building components shall be currently ceriified by ICBO, AISC, ACI, PCI, PTi cr
other recognized and approved certifying agencies. For ncn-certified fabricatcrs, or when required per the
approved permitted ~Icms and or spec:ficaticns, one or mere approved certified special inspectors shall be
assigned by the builoing owner when approved by the City of Chula Vista
8. Furnish the 'Certificate of Compliance for Off-Site Facr:caticn' form to the fabricatcr(sj cf building compcne:.ts to
be completed and submitted to the Building Inspection Section.
9. Keep a copy of all special inspection/test reports submitted by the special inspector and/the construction rT'.aterials
testing laboratory at the jcb site A copy of such reports shall be submitted to the Building Divisicn Inspec;;on
Section,
10. Correct all deficient and/or non-conforming work as noted by the special inspector/cons;ruction materials testing
laboratory in accordance with the approved permitted plans and specifications.
Paçe :2 CT ~.
FORM 4544
SPECIAL INSPECTION/CONSTRUCTION MATERIALS TESTING INSTRUCTIONS (Continued)
III. Questions
If you have any questions with respect to these instructions, special inspections, construction materials testing, off-site
fabrication of building components and other related requirements, please cail the Building Division Inspection Section
at (619) 409-5868.
For additionai information on these requirements refer to the City of Chura Vista website www,cichula-vista.ca.us/
The following forms are available on our website and may aiso be requested from the Building Division
1, FORM 4538 - SPECIAL INSPECTION AND OFF-SiTE FABRICATION FORMS (Instructions for the completion
and filing)
2. FORM 4539 - PROPERTY OWNER/CONTRACTOR AGREEMENT
3, FORM 4540 - APPLICATION TO PERFORM OFF-SITE FABRICATION
4, FORM 4541 - CERTIFICATE OF COMPliANCE FOR OFF-SITE FABRICATION
5, FORM 4542 - PROPERTY OWNER'S FINAL REPORT FOR SPECIAL INSPECTiON AND CONSTRUCTION
MATERIALS TESTING
6. FORM 4543 - SPECIAL INSPECTOR/INSPECTiON AGENCYITESTING LABORATORY FINAL REPORT
7. FORM 4544 - SPECIAL INSPECTION/CONSTRUCTION MATERIALS TESTING iNSTRUCTIONS(Property
owner's, contractor's, builder's responsibilities)
Page 3 of 3
FORM 4538
~!f? City of Chula Vista SPECIAL INSPECTION AND OFF-
Building Division Inspection Section SITE FABRICATION FORMS-
-,- Planning and Building Department
~- - 900 Lane Avenue, Suite 200 INSTRUCTIONS FOR THE
0lY OF Chula Vista CA 91914 COMPLETION AND FILING
(HUlA VISTA Information: (619) 409-5868 Fax: (619) 216-7306 Please read these instructions carefully. You are responsible for complying with the
requirements stated therein. Any violations of these instructions may be a cause for removal
of the work performed
PROPERTY OWNER AND CONTRACTOR AGREEMENT for Special Inspection/Construction
Materials Testing/Off-Site Fabrication/HERS Rating
This form shall be completed and submitted by the property owner or his/her authorized agent of record cr the
architect/engineer of record acting as the property owner's agent and the contractor/builder at the time of
permit issuance,
APPLICATION TO PERFORM OFF-SITE FABRICATION
This application shall be completed by the fabricator of building components when such components are
fabricated within the premises of the fabricator's shop, This application must be submitted to the
Inspection Section for approval at least three business days prior to scheduled start of fabrication,
Also see Certificate of Compliance for Off-Site Fabrication,
CERTIFICATE OF COMPLIANCE FOR OFF-SITE FABRICATION
This form shall be completed by the fabricator of building components when such components are fabricéted
within the premises of a fabricators shop, This form must be filed with and approved by the Building
Division Inspection Section prior to erection of fabricated components, Also see Application to Perform
Off-Site Fabrication,
INSTAllATION CERTIFICATE (CF-6R) and CERTIFICATE OF FIELD VERIFICATION AND
DIAGNOSTIC TESTING (CF-4R)
Form CF-6R to be completed and signed by the installer and form CF-4R to be completed and signed by the
HERS rater. Both forms must be submitted to the Inspection Section prior to final inspection.
PROPERTY OWNER'S FINAL REPORT
This form shall be completed by the property owner or his/her authorized agent of record or the
architect/engineer of record acting as the property owner's agent for the types of work required to have special
inspection, construction materials testing, off-site fabrication or HERS rating, This form must be filed with
the Building Division Inspection Section prior to final inspection,
SPECIAL INSPECTORIINSPECTION AGENCY/TESTING lABORATORY FINAL REPORT
This form shall be completed by the independent special inspector or the special inspection agency or the
construction materials testing laboratory after all work requiring special inspection or testing have been
completed, and must be filed to the Building Inspection Section prior to final inspection.
APPROVED CONSTRUCTION MATERIALS TESTING lABORATORIES
The construction materials testing shall be performed by a testing laboratory listed on the City of San Diego or
the City of Los Angeles most current list of approved materials testing laboratories,
FORM 4539
~(ft.. City of Chula Vista
Building Division Inspection Division PROPERTY
-11- Planning and Building Department
. - - OWNER/CONTRACTOR
- -- 900 Lane Avenue, Suite 200
em OF Chula Vista CA 91914 AGREEMENT
CHUIA VISTA Information (619) 409-58689'Fax (619) 216-7306
Speciallnspection/Construction Materials Testing/Off-Site Fabrication/HERS Rating
Note: Both sections A and B shall be completed, signed and executed,
To: Building Official
City of Chula Vista
Building Division Inspection Section
Planning and Building Department
276 Fourth Ave
Chula Vista CA 91910
PERMIT NO,:
(For projects with multiple permit numbers, you may list all permit numbers on a separate sheet.)
PROJECT ADDRESS: Chula Vista, California
AGREEMENT
I, the undersigned, declare under penalty of perjury under the laws of the State of California, that I have read, understand. acknowledge
and promise to comply with the City of Chula Vista requirements for special inspections, construction materials testing and off-site
fabrication of building components as prescribed in the instructions attached herewith and incorporated by reference herein. I hereby
. agree to have all work requiring special inspection, material sampling and testing, or off-site fabrication of building components for
structure(s) constructed under the subject permit(s) performed in the manner prescribed by the California Building Code or Califomia
Energy Efficiency Standards as adopted by the City of Chula Vista, and in conformance with the plans and specifications, and other
construction documents as approved by the City of Chula Vista,
A. NAME: (TYPE OR PRINT)
(FIRST) (M.!.) (LAST)
I AM THE: (PLEASE CHECK ONE)
0 PROPERTY OWNER 0 PROPERTY OWNER'S AGENT OF RECORD
0 ARCHITECT OF RECORD 0 ENGINEER OF RECORD
State of California Registration Number: Expiration Date:
MAILING ADORESS:
Executed on this day of /
Signature:
8, CONTRACTOR/BUILDER - NAME: (TYPE OR PRINT)
(FIRST) (M.!.) (LAST)
MAILING ADDRESS:
Executed on this day of /
MONTH YEAR
Signature:
FORM 4540
~I!~ City of Chula Vista
Building Division Inspection Section APPLICATION TO
-.- Planning and Building Department PERFORM OFF-SITE
r ~ _
900 Lane Avenue, Suite 200
(flY OF Chula Vista CA 91914 FABRICATION
CHUIA VISTA Information (619) 409-5868oFax (619) 216-7306
MUST BE FILED THREE BUSINESS DAYS PRIOR TO SCHEDULED FABRICATION COMMENCEMENT DATE
DATE: SCHEDULECJ Ff'BRICAïION COM~IENCEME,"T DATE:
FABRICATION CO, NAME: TELE~HONE NO,: L-.J
FABRICATION SHOP ADDRESS: FAX NO.: ( )
CITY: STATE: ZIP CODE:
BUILDING PERMIT NO./S:
(Fer projec:s with multipie ~err.;it r:ufiì:ers, :ICU I";Y lis;: 211 ,:erTL'lit numcers 2.nc ac::resses en a seS2rate s;-,eet.)
JOB SITE ADDRESS:
DESCRIPTION OF COMFO~IEN,S TO EE rF2RICF,T::D:
FABRICA,OR IS CURREN,L Y C,,::;'TIFiED 2Y: ~ iCSO c:: p.jSC i I ACi i=:J FC: [J pti
[J Other C¿;:ificê.te ~c.: - . . ""
CX::::lrë.:Icn '_iê.:e:
SP::CIAL INSP::C,OR FSSIGNEJ (2', "UILc;ING C'NNE~,): C~::¡ficê.te NC.:
(Fsr ncn.........zr3ied :at:nca:cr. cr when re::;'.;ire-: ;:er :~e ::e~l:;'ec ::iar:s ar;:::,'cr 5:e:::-,~;;c~s.:
NOTt=: Tr.~ FABR1CAïOR IS ~=CL!I.:;:=J -:-0 :--:.AV::: F.':"3::\:CA ~;CN :;P"';'/i:NGS 'N~!C:~ :"';,..l,V::: ===N i;.=·-;[E"IV:::J .":',,\JO .~,CC:::?7~:: ='( i~:: CES:GNE~
OF RECORD. SP=C:AL INSP:='CiCR \1LJSi 'i:=.q:.=y Sl.'C:-': ,":',CC='.=ï;',;-"¡C:=: ??ICR 70 C::M,\IE:"iC:NG !NS?::":ìïCN Dt..;'T:::S.
AGREEMENT
We hereby agree to have c.:::ntinuoL.:s s;::ec:al ins;:::ec:icn, sam.:::iing 2nc testjng 2S scec::ied on t.'1e a~proved perrr,it:.ed ¡::Ians anc s¡:::ec;(¡cajcns. We wi1!
further agree that the wcr'", wil! :;e perfcrmec in the IT.2.r.ner ;::resc~t:ed ::y tle Cëlifcmia Building CGee and ~he Stanc:ads as 2.l71enced by the City of Chula
Vista and other regulaticns.
We understand that:he property owr:er er t.'1e eng¡neerië.fc:.¡tec~ CT recore ac:;ng 2.S J'1e ;Jrcperty owner's agent is sele!y res¡:;cnsit:ie fer e:nployment of ene
or more spec:al inspec:ors who shall previde ins¡:ec:icns fer fabr.cation of the ccrr:pcr,ents desc;-ibed herein. We 21so agree to previee wniIm¡ted access to
the fabrication areas, the materials stcrage ar.d mixing areas, other reiated areas, the appreved shcp drawings anc: emer documents fer t1e purpose of
inspection, sampling anc testing by the spee:al inspecters. c;:;nstn..:c:icn materiêls :esting labcratory er Planning and Building Depar'.ment ;::ersonnel during
working hours. We further agree to provide an icentir;lir.g mark on eêch fatriC3ted member or component shipped :0 the to the constructicn site. A
certificate of compliance and a shipping list shall accomc:any eac:-: s,'1ipment and
a copy shaJl be sent to :he Building Division Inspection Sec~;cn and t"'.e 2rc:-:itec: FOR OFFICE USE ONLY
or engineer of record 'Nhen the c.:mponents are shipped.
This agreement is limited to fabrication of the components or members desc:iced
above to be used in the Structures identified by the permit numbers shown and is o APPROVED [J CORRECT AND RESUBMIT
not transferable to any other fabrication work or ether construction sites. o DENIED
Name (Print): COMMENTS:
Title: Date:
Any person signing this application as an agent of the fabricaticn Gcrr.pany
dec!ares under penalty of pe~ury to be an authorized agent of record of the
fabrication ccmpany having the authority to execute this coc:Jment. NA~IE (Print):
SIGNATURE: DATE:
Signature:
FORM 4541
~Ift.. City of Chula Vista
Building Division Inspection Section CERTIFICATE OF
:--~- - Planning and Building Department COMPLIANCE FOR OFF-SITE
------ - 900 Lane Avenue, Suite 200
CIlY OF Chula Vista CA 91914 FABRICATION
(HUlA VISTA Information (619) 409-5868. Fax (619) 216-7306
MUST BE FILED WITH THIS OFFICE AND APPROVED PRIOR TO ERECTION OF FABRICATED COMPONENTS
FABRICATION CO. NAME TELEPHONE NO. L-l
FABRICATION SHOP ADDRESS FAXNO,~
CITY STATE ZIP CODE
BUILDING PERMIT NO./S
(For projects with multiple permit numbers, you may list all permit numbers and addresses on a separate sheet)
JOB SITE ADDRESS
DESCRIPTION OF COMPONENTS FABRICATED
FABRICATOR IS CURRENTLY CERTIFIED BY: OICBO OAISC OACI OPCI Opti
o Other Certificate No, Expiration Date
SPECIAL INSPECTOR ASSIGNED (BY BUILDING OWNER) Certificate No,
(For non certified fabricators, or when required per the approved permitted plans and/or specìfications.)
FABRICATION DRAWINGS REVIEWED AND ACCEPTED BY DESIGNER OF RECORD? OYES ONO
STRUCTURAL FRAMING PLANS, DETAILS & CALCULATIONS REVIEWED AND APPROVED BY THE CITY OF
CHULA VISTA BUILDING DIVISION? OYES ONO
FABRICATION COMMENCEMENT DATE FABRICATION COMPLETION DATE
We hereby certify that the components described and listed herein comply with the approved permitted plans, specifications and
workmanship provisions of the California Building Code as amended by the City of Chula Vista and other applicable regulations, We
further certify that each fabricated member or component has been inspected and meets all the requirements of the California Building
Code as amended by the City of Chula Vista and other applicable regulations, We further certify that each fabricated member or
component listed herein shipped to the project job site with an identifying mark or tag. We understand this certificate shaH be submitted
to the Building Division Inspection Section and the architect/engineer of record prior to erection of the fabricated members and
components
NOTE: This certification is limited to fabrication of the components or members described above to be used in the structures identified
by the permit numbers shown and is not transferable to any other fabrication work or other construction sites,
Name (Print): Title:
Any person signing this application as an agent of the fabrication company declares under penalty of perjury to be an authorized agent
of record of the fabrication company having the authority to execute this document.
Executed on this day of I
MONTH YEAR
Signature:
FORM 4543
City of Chula Vista SPECIAL
Building Division Inspection Section INSPECTOR/INSPECTION
Planning and Building Department AGENCY/TESTING
900 Lane Avenue, Suite 200
CIlY OF Chula Vista CA 91914 LABORATORY FINAL
(HUlA VISTA
Information (619) 409-5868. Fax (619) 216-7306 REPORT
Special inspection and construction materials testing
DATE: I I
SUBJECT: SATISFACTORY COMPLETION OF WORK REQUIRING: (Please check as applicable)
o SPECIAL INSPECTION o CONSTRUCTION MATERIALS TESTING
PERMIT NO,:
PROJECT ADDRESS: Chula Vista. California
o The special inspection services were provided by:
SPECIAL INSPECTION AGENCY:
ADDRESS:
SPECIAL INSPECTOR'S NAME: (TYPE OR PRINT)
(Each special inspector is required to compiete and submit this Final Report form when not an employee of an approved testing
laboratories or inspection agency)
SPECIAL INSPECTOR'S CERTIFICATION NUMBER: EXPIRATION DATE:
ADDRESS:
o The construction materials testing were performed by:
TESTING LABORATORY:
ADDRESS:
RESPONSIBLE MANAGING CIVIL ENGINEER OF THE TESTING LABORATORY: (MR.! MS.)
STATE OF CALIFORNIA REGISTRATION NUMBER: EXPIRATION DATE:
COMMENTS'
I declare under penalty of perjury that, to the best of my knowledge, all the work requiring special inspection, andlor material sampling
and testing, for the structure/s constructed under the subject permit is in conformance with the approved plans and construction
documents, the approved inspection and testing program workmanship provisions of the California Building Code as amended by the
City of Chula Vista,
Executed on this day of I
Signature:
FORM 4542
City of Chula Vista
Building Division Inspection Section PROPERTY OWNER'S
Planning and Building Department
(flY OF 900 Lane Avenue, Suite 200 FINAL REPORT
(HUlA VISTA Chula Vista CA 91914
Information (619) 409-5868, Fax (619) 216-7306
Special Inspection/Construction Materials Testing/Off-Site Fabrication/HERS Rating
DATE: I I
SUBJECT: SATISFACTORY COMPLETION OF WORK REQUIRING SPECIAL INSPECTION,
CONSTRUCTION MATERIALS TESTING, OFF-SITE FABRICATION OR HERS RATING
PERMIT NO.:
(For projects with multiple permit numbers, you may list all permit numbers on a separate sheet.)
PROJECT ADDRESS: Chula Vista, California
NAME: (TYPE OR PRINT)
(FIRST) (M.I.) (LAST)
I AM THE: (PLEASE CHECK ONE)
0 PROPERTY OWNER 0 PROPERTY OWNER'S AGENT OF RECORD
0 ARCHITECT OF RECORD 0 ENGINEER OF RECORD
State of California Registration Number: Expiration Date:
I declare under penalty of perjury that, to the best of my knowledge, all the work requiring special inspection,
material sampling and testing, off-site fabrication of building components or HERS rating for the structure(s)
constructed under the subject permit is in conformance with the approved plans and documents, the
inspection program, and the applicable workmanship provisions of the California Building Code, as amended
by the City of Chula Vista, and the California Energy Efficiency Standards.
Executed on this day of I
Signature:
DRAFT Form 4545
~\ft.. City of Chula Vista
---: Building Division Inspection Section SPECIAL INSPECTOR-
- Planning and Building Department START WORK
cm OF 900 Lane Avenue, Suite 200
(HUlA VISTA Chula Vista CA 91914 NOTIFICATION
Information (619) 409-5868· Fax (619) 216-7306
Prior to the first day a special inspector is scheduled to be on the job site, he/she must do the
following:
1. Notify the Inspection Section of the project, date and approximate time he/she is
scheduled to be on the job site, and a phone number that he/she can be reached at
(preferably his/her cell phone,) This can be accomplished by either calling in the
information or completing this form and faxing it to the Inspection Section. This
information is needed to coordinate a time when the City inspector can meet the
special inspector on site,
2, Fax a copy of his/her qualifications and current driver license/photo 10 to the Inspection
Section.
The two requirements shown above are also required when a repiacement special inspector, other
than the originally approved special inspector, takes over the project on a temporary or permanent
basis.
Today's Date:
Special Inspector Name:
Permit Number:
Project Address:
First Dayan Site; Date: Time of Day:
"\ Telephone number (preferably cell phone):
Type(s) of Special Inspection:
Were the following documents included?
Copy of the inspector's qualification/experience? { } Yes { } No
Copy of the inspector's driver license/photo ID? { } Yes { } No
Date Received: Received by: