HomeMy WebLinkAboutReso 2021-002RESOLUTION NO. 2021-002
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA APPROVING THE THIRD AMENDMENT TO
THE AGREEMENT WITH SOUTHERN CALIFORNIA
PRECISION CONCRETE, INC. FOR CIP STL0443
“SIDEWALK REHABILITATION CITYWIDE (MEASURE P)”
TO INCREASE THE MAXIMUM CONTRACT AMOUNT AND
EXTEND THE TERM OF THE AGREEMENT
WHEREAS, on August 13, 2019, the City Council of the City of Chula Vista adopted
Resolution 2019-159 approving an Agreement with Southern California Precision Concrete, Inc.
(“Contractor”) to provide sidewalk rehabilitation services; and
WHEREAS, the cost and time required to complete the original scope of work exceeds
the limits in the Project contract; and
WHEREAS, on October 22, 2020, the Measure P Citizen Oversight Committee
recommended an allocation of additional funds for CIP STL0443 “Sidewalk Rehabilitation
Citywide (Measure P)” (“Project”) to complete the scope of the project; and
WHEREAS, on December 1, 2020, the City Council of the City of Chula Vista adopted
Resolution 2020-274 which amended the Fiscal Year 2020/2021 budget and transferred
$747,783.54 to CIP STL0443 “Sidewalk Rehabilitation Citywide (Measure P)” increasing the
total Project budget to $1,877,783.54 to complete the additional scope; and
WHEREAS, staff recommends approval of the Third Amendment to the Agreement to
allow the Contractor to complete the scope of the Project.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Chula
Vista, that it approves the third amendment to Agreement No. 19074, between the City and
Southern California Precision Concrete, Inc., in the form presented, with such minor
modifications as may be required or approved by the City Attorney, a copy of which shall be
kept on file in the Office of the City Clerk, and authorizes and directs the City Manager to
execute same.
DocuSign Envelope ID: DE45E320-407C-4CC8-AB41-26A5C0AFFD0B
Resolution No. 2021-002
Page No. 2
Presented by Approved as to form by
William S. Valle Glen R. Googins
Director of Engineering & Capital Projects City Attorney
PASSED, APPROVED, and ADOPTED by the City Council of the City of Chula Vista,
California, this 5th day of January 2021 by the following vote:
AYES: Councilmembers: Cardenas, Galvez, McCann, Padilla, and Casillas Salas
NAYS: Councilmembers: None
ABSENT: Councilmembers: None
Mary Casillas Salas, Mayor
ATTEST:
Kerry K. Bigelow, MMC, City Clerk
STATE OF CALIFORNIA )
COUNTY OF SAN DIEGO )
CITY OF CHULA VISTA )
I, Kerry K. Bigelow, City Clerk of Chula Vista, California, do hereby certify that the foregoing
Resolution No. 2021-002 was duly passed, approved, and adopted by the City Council at a
regular meeting of the Chula Vista City Council held on the 5th day of January 2021.
Executed this 5th day of January 2021.
Kerry K. Bigelow, MMC, City Clerk
DocuSign Envelope ID: DE45E320-407C-4CC8-AB41-26A5C0AFFD0B